15.54.090 - Construction Permit approval, expiration and extension approval.
A. Construction permits shall expire one year from the date of permit approval. The date of approval shall be the date the Construction Permit application is signed by the Town. All work covered by the Construction Permit shall be completed one year from the date of permit approval. 1. The Construction Permit shall be void if work has not commenced within 180 days after approval of the permit. Once the permit is void, the Town will return the applicable performance surety to the applicant, along with all permit review and inspection fees and Use Taxes paid by the applicant, less a two-hundred-fifty-dollar administrative fee. 2. If work has commenced within 180 days after approval of the permit but cannot be completed within the one-year time frame, a construction permit extension request may be submitted to the Town prior to the expiration date of the permit in accordance with the Development Procedures Manual, for consideration by the Town. B. Not more than two one-year permit extensions may be granted administratively, subject to the following criteria: 1. The project site is in conformance with all temporary erosion and sediment control (TESC) requirements, traffic control requirements and plan requirements and construction notes; 2. The project site is in conformance with the Town Construction Methodology and Materials Manual; 3. The project site is in conformance with all improvement agreement provisions and no default thereunder has been declared by the Town; and 4. There are no health, safety or welfare issues related to the site impacting the general population or the immediate neighborhood. C. A Construction Permit extension application shall be submitted in the required form, signed by the applicant, and shall include all mandatory information as prescribed in the Development Procedures Manual. A request for a Construction Permit extension shall be submitted to the Public Works Department no less than 30 days prior to the expiration of the construction permit. The request for a Construction Permit extension shall be accompanied by all necessary fees, in accordance with the Development Services Fee Schedule, and any performance Surety extensions if applicable. The permit shall not expire and work on the project may continue until the Town acts on the extension application. D. If the site is not in conformance with the above-listed criteria, the applicant may bring the site into conformance and reapply for a Construction Permit extension. However, the new application must be received at least 15 days prior to the expiration date of the existing Construction Permit. The Construction Permit shall not expire and work on the project may continue until the Town acts on the extension application. E. If, at the time of Construction Permit extension request, it is determined that any federal, state, county or Town requirements related to health, safety and welfare in effect at the time of application for a Construction Permit extension as well as Town provisions related to lot-to-lot drainage and/or water meter locations have not been incorporated into the Construction Documents, the applicant will be required to submit a Field Change Order to modify the Construction Documents that incorporate such changes as an additional condition of obtaining such Construction Permit extension. F. If the Construction Permit expires before an application is submitted, a new permit must be obtained from the Town, along with all applicable fees at the time of permit application. When approved, the new permit shall be subject to the expiration and extension requirements outlined in this Section.
(Ord. No. 2019-027, § 5, 9-17-2019; Ord. 2012-16 §1, 2012)