Sec. 109-43. - Same—Class 3 permits.
(a) Authority. The city public works department is hereby authorized to require all persons to obtain a permit for excavation, filling and construction including, but not limited to, seawalls, groins, breakwaters, wharves, docks, piers, boat lifts and slips, dams, locks, levees, pumps, control gates and similar structures in, upon or contiguous to bays, lakes, canals and other water areas and waterfronts under the direct control of the city by virtue of ownership, dedication by plat, right-of-way easement, reservation, or right-of-way and access agreement or instrument. (b) Application for city approval. A city construction permit for work proposed under a class 3 permit shall be obtained from the city public works department. The proposed work must be completed prior to the stated expiration date which must be less than one year from the date of issuance of the permit, although extension may be granted for good cause, subject however, to receipt of written request for extension of time by the city public works department prior to the original expiration date. The construction permit may be issued to a certified contractor provided: (1) Construction plans and specifications are submitted, which have been prepared to comply with the requirements of the city public works standards. (2) The permit fees established by section 109-44 for construction work have been paid. (3) A performance bond is posted in an amount determined by the director of public works department to be essential to protect the interest of the public and of landowners in the vicinity of the work; provided however, that the minimum amount of such bond shall be $1,000.00 or 25 percent of the estimated cost of the work, whichever is lesser, and the maximum amount of such bond shall be 100 percent of the estimated cost of the work, the bond being to guarantee compliance with terms of the permit and to be in force for at least three months after the approved completion date of the work. (4) Certification is provided by a registered engineer that he/she has been retained to provide engineering supervision throughout the construction period, his or her certification to include a letter from the appropriate governmental authority that the proposed work does not violate any zoning law or restriction which may be applicable to the work or work area; provided however, that such certification may be waived by the director of public works department for canal culvert permits.
(Code 1958, § 9A-14; Code 1991, § 8-29; Code 2006, § 109-43; Ord. No. 2067, § 4, 12-18-1973)
Ask a question about Coral Gables law
Corpus searches the Coral Gables sections it holds and shows the ones that match, with their citations. Free, no sign-in.