§ 104.3.1 — BUILDING PERMIT FEE REVIEW REQUESTS FOR COMPLETED PROJECTS

Atlanta City Code (Code of Ordinances, Part II) (Supp. No. 108, Update 1: codified through Ordinance No. 2026-37 (26-O-1511), enacted September 30, 2026) · Atlanta Land Development Code, App. A, ch. I, § 104.3.1

Corpus is an independent public-information project, not the official City of Atlanta website. Stable reference: corpuslaw.us/code/9cede9df-b57f-492a-b7ff-45c36d1e761a

104.3.1. - BUILDING PERMIT FEE REVIEW REQUESTS FOR COMPLETED PROJECTS.

(a) Applicability. An applicant for a building permit, or the owner of the property which is the subject of the permit (collectively referred to herein as the "owner"), for a project meeting the eligibility requirements herein has the right to request a building permit fee review under the procedures set forth herein. (b) Eligibility. For a project to be eligible for building permit fee review, the director shall find: (i) The project required the submission of plans and the calculation of the building permit fee from such plans using Table 100; (ii) The Table 100 job cost calculation on which the city's building permit fee is based exceeds the actual cost to construct the building or structure which is the subject of the permit (the "project") by more than ten percent as indicated on the building permit application; (iii) The owner paid a plan review fee equal to one-half of the building permit fee based on the cost of construction information provided to the director at the time of the submittal of the application for plan review as required by Sec. 104.1(c); (iv) The owner paid a final building permit fee payment which is the balance of the fee based on the cost of construction information provided to the director at the time of the submittal of the application for plan review as required by Sec. 104.1(c); and (v) The owner gave written notice of the request for a permit fee review, as prescribed herein, at the time of final building permit fee payment. (c) Notice. The notice of a request for a permit fee review must contain, at a minimum: (i) The permit number; (ii) The street address of the project; (iii) The permit fee amount paid; (iv) The permit holder's approximate expected cost to construct that part of the project for which the review is sought; (v) A statement of demand for a permit fee review based on actual cost to construct a completed project including a statement of the amount of the difference (greater than 10%) between the projected permit fee based on Table 100 and the projected permit fee based on owner's expected cost; (vi) The name and street address for the person authorized to receive notices from the director. No post office box may be used to receive notice from the director; and (vii) A statement agreeing that the payment of a review fee associated with the director's review of the permit fee review request as established by city council will be paid before a final certificate of occupancy is issued. (d) Building permit issuance authorized during building permit fee review. If the director finds that an owner is eligible for a building permit fee review, the director may issue a building permit, notwithstanding the requirement of Sec. 104.2(b) that the final permit payment be based on Table 100. While the permit review request is being processed in accordance with the procedures outlined in this section, the director may also conduct all inspections during the course of construction, including final inspection, and issue a temporary certificate of occupancy upon completion of construction. The director shall not issue a final certificate of occupancy until the owner pays the amount set forth in Sec. 104.2(b) or the amount approved by the Atlanta City Council. (e) Required submittals for building permit fee review. (i) Within 30 days of the date of the issuance of the building permit, the owner shall submit: (1) An affidavit from a professional engineer or architect, registered in the State of Georgia swearing that the cost stated in the notice given to the director is expected to be the actual cost to construct the project and shall specifically identify and agree to produce the data on which this statement is based after the temporary certificate of occupancy is issued; and (2) An affidavit from the owner, the leaseholder or the person who is responsible for payment of the cost to construct the project, swearing that all forms of payment used to pay the total amount that will be paid to construct the project will be submitted as proof of payment of the job cost amount and further will agree to produce such documents after the temporary certificate of occupancy is issued in conjunction with the audit required by this section. The proof of payment is required to confirm that Table 100 job cost calculation on which the permit fee is based exceed the actual cost to complete the project. (ii) Within 90 days after issuance of the temporary certificate of occupancy, the owner shall submit an independent audit of the project (the "audit") prepared by a certified construction manager or a certified public accountant licensed to practice in the State of Georgia (collectively referred to herein as the "auditor") on behalf of the owner for the purpose of seeking a permit fee review from the city. The auditor's report shall make a certified finding as to whether the affidavits submitted by the architect or engineer and the owner of the property fairly represent the cost associated with the construction of the project and the amounts actually paid and state their opinion as to the amount by which the permit fee should be adjusted. (iii) A temporary certificate of occupancy issued for the purposes of a permit fee review request shall meet all requirements for the issuance of a final certificate of occupancy so that the most accurate cost to complete the project can be obtained. (iv) It shall not be sufficient for the purpose of the permit fee review request to identify contract documents as the only documents which shall form the basis for either affidavit or the permit fee review request and unless both affidavits contain an agreement to produce any document reasonably relevant to the project when requested by the director and to produce such documents upon the directors request, the director may deny the request; (f) Review by the director. The following review process shall be substantially followed: (i) In evaluating the audit, the director shall be entitled to receive any documentation relied upon by the auditor or such other documents as the director may reasonably deem relevant for review; provided however that such request shall be made by the director within 30 days of the audit. The director may but is not required to engage an auditor to review the submission of the owner. The failure to produce the requested documents to the director within 30 days without cause shall be grounds for the director to consider the request for permit fee review withdrawn. (ii) Within 60 days after the director has received all documents requested, the director shall notify the owner in writing of his intent to issue a written recommendation to the Atlanta City Council for either: (1) Approval of the amount of the permit fee based on actual costs as requested; (2) Approval of a different permit fee amount based on the actual cost to construct; or (3) Denial of the permit fee adjustment. (iii) The director shall base his recommendation on the findings of the Auditor's report, including any audit commissioned by the director, and all other available documentation establishing the actual cost of construction. The director's failure to make a finding within 60 days after the director has received all documents requested shall be considered a recommendation of denial of the permit fee adjustment as requested by the Owner unless the Owner provides its written consent to allow the director additional review time. Within a reasonable time after, the director shall cause the necessary legislation to be submitted to the Atlanta City Council, with a copy of the director's for a final decision on the permit fee adjustment request. (g) Decision by the Atlanta City Council. The Atlanta City Council shall, by ordinance, adopt as its final decision, the recommendation of the director unless there is an expressed finding by the council that the director's recommendation was based on an erroneous finding of a material fact, or that he acted in an arbitrary manner. In such a case, the Atlanta City Council shall: (i) approve of the amount of the permit fee based on actual costs as requested; (ii) approve a different permit fee amount based on the actual cost to construct; or (iii) deny of the permit fee adjustment. (h) Post-decision procedure. The following shall apply: (i) Upon the ordinance becoming law in the manner established in the Charter, the director shall so inform the owner in writing within three business days. (ii) If no appeal of the Atlanta City Council's decision is timely filed or the owner waives such appeal, and upon the owner's payment of any outstanding amounts consistent with the Atlanta City Council's decision and any other fee provision, the director shall be authorized to issue a final certificate of occupancy, if otherwise lawful. (h) Appeal. If the owner disputes the Atlanta City Council's decision, upon payment of the director's certified cost to conduct the review, the owner may appeal from such decision to the Superior Court of Fulton County by filing with the clerk of said court a petition in writing setting forth plainly, fully and distinctly wherein such decision is contrary to law. Such appeal shall be filed within 30 days after the decision of the city council is rendered. Upon such filing, the clerk of the superior court shall give immediate notice thereof to the director. Such appeal to superior court shall be served on the director as provided by law. Within the time prescribed by law, the director shall cause to be filed with said clerk a duly certified copy of the administrative record created in connection with the permit fee review request and such evidence on which his decision was based; provided however that the building plans for the project shall not be submitted as a part of the administrative record of the permit fee review request unless the specific plan sheets are identified by the owner and the owner agrees to pay the cost of copying the original plans to be submitted to the court. The process stated herein may also be used to appeal the Atlanta City Council's denial of a permit fee review request for failure to meet the deadlines required for the processing of the permit fee review request provided however that the appeal of the Atlanta City Council's denial of the permit fee review request for failure to meet any of the deadlines for submission of documents shall be filed within 30 days of the date of the written denial. (i) Miscellaneous provisions. (i) Other fees not applicable. This section shall only apply to building permit fee reviews for projects which required the submission of plans and the calculation of the amount of the permit fee using the data set forth in Table 100. No other fee review, including without limitation, impact fees, may be requested under this section and the director is not authorized to accept such requests. The director's refusal to accept a fee review request which did not require the submission of plans and the calculation of the amount of the permit fee using the data set forth in Table 100 shall not be subject to the appeal provisions of this section. This section is provided solely to allow the office of buildings to make a determination through the director whether the determination of the job cost valuations by the use of Table 100 has resulted in a fee amount that is consistent with the actual cost to construct a project and is not intended for any other purpose, including without limitation, the appeal of fees determined by other means. (ii) Abandonment of project or permit fee review request. With respect to any permit fee review request under an issued permit which is abandoned or withdrawn after work is begun but for which no temporary certificate of occupancy is issued or which has been revoked by the director prior to the issuance of the certificate of occupancy, the permit fee review request shall be deemed withdrawn and the owner is liable for any balances due on the permit fee in accordance with Table 100. (iii) Penalty for false statement. Any person who knowingly and willfully makes false statements in an affidavit used or attempted to be used to obtain a permit fee adjustment pursuant to this section may be prosecuted under the City Code or applicable state laws, including without limitation O.C.G.A. § 16-10-71, and punished in the manner provided for conviction of such violations. (iv) Time limit on temporary certificate of occupancy. The temporary certificate of occupancy issued during the pendency of a permit fee review request shall not remain in effect for more than 180 days after the owner presents the result of the Audit to the director unless an appeal of the Atlanta City Council's decision is filed, in which case the temporary certificate of occupancy shall remain in effect until the appeal is settled or a decision is rendered by the court with jurisdiction over the appeal. The failure to obtain a final certificate of occupancy shall be cause for the director to order the discontinuance of the occupancy of the structure.

(Ord. No. 2015-62(15-O-1533), § 1, 12-16-15)