Sec. 102-717. - Right-of-way restoration; performance and maintenance bond or other form of security requirements for excavation permit; surety bond requirements for obstruction permit.
(a) Restoration required. The work to be done under an excavation permit issued pursuant to this article and the restoration of the right-of-way as required in this division must be completed within the dates specified in the permit. In addition to its own work, the permittee must restore or pay for the restoration of the general area of the work, and the surrounding areas, including the paving, its foundations and any special features, to its proper and required condition in accordance with the city's utility accommodation and street restoration specifications, unless the city engineer deems other or additional specifications must be utilized in order to secure proper restoration. Further, the permittee shall inspect the area of the work and use reasonable care to maintain the same condition for 48 months thereafter. If special features in the right-of-way at a proposed excavation site, including but not limited to special sidewalk surfaces, heated sidewalks, underground vaults, areaways, and landscaping, cannot be preserved or protected, the city must be notified prior to the applicant beginning work. (b) Performance and maintenance bond. An applicant for an excavation permit shall, at the time of application for an excavation permit, post a performance bond in an amount determined by the city engineer to be sufficient to cover the cost of restoring the right-of-way to its proper and required condition pursuant to the city's utility accommodation and street restoration specifications and in accordance with the current restoration cost schedule established by resolution of the city council. If at the conclusion of the 48-month period after completion of the restoration of the right-of-way, the department determines that the right-of-way has been properly restored, the surety on the performance bond shall be released. (c) Bond condition. The bond shall be conditioned upon: (1) The faithful performance of the right-of-way restoration work required under this article, or payment of the restoration costs incurred by the city; and (2) The faithful performance of the terms of the permit, the provisions of this article, and any other requirements provided by law. If the applicant fails or neglects to properly restore the right-of-way to its proper condition within the time for completion set forth in the permit, or within a reasonable time after notice by the city engineer of such failure or neglect, or fails to pay the restoration costs incurred by the city or fails or neglects to properly maintain the right-of-way to its proper condition within a reasonable time after notice by the city engineer of such failure or neglect, or fails to pay the maintenance costs incurred by the city, the right-of-way shall be restored or maintained by the city and the costs thereof, as certified by the city engineer, shall be promptly paid by the applicant or bonding company as the case may be. (d) Alternate forms of security. In lieu of filing a performance bond in connection with each excavation permit application, an applicant may, in the discretion of the city engineer, be allowed to post with the city treasurer an alternate form of security in the form of an annual performance bond, letter of credit, certificate of deposit, or certified check in an amount deemed sufficient by the city engineer, but in no event less than $25,000.00, to secure the applicant's performance of all restoration work which the applicant will become responsible for during the next 12-month period in accordance with the current restoration cost schedule established by resolution of the city council upon the recommendation of the city engineer. Such alternate form of security shall be conditioned upon the applicant's performance as provided in subsection (c) of this section. If the costs as certified by the city engineer during such year are less than such letter of credit, certificate or deposit, or certified check, or if the maintenance period provided for in the permit has expired with the applicant having satisfied all of its restoration and maintenance responsibilities, the balance thereof shall upon request be returned to the applicant. If it appears to the city engineer at any time after issuance of a permit that the security so provided by letter of credit, certificate of deposit, or certified check is inadequate to secure the performance of all such restoration work, the city engineer may require the permittee to increase such security. If the costs during such year exceed the amount of such additional security provided by letter of credit, certificate of deposit, or certified check, the applicant shall be required to pay such difference to the city. Such excess costs shall be paid before any subsequent application by the applicant for a permit under this article may be processed by the department. If the city incurs any outlay and expense in collecting its costs from the applicant, such outlay and expense shall be paid by the applicant or bonding company in addition to other amounts due. (e) Bond for licensed plumbing contractors. A licensed plumbing contractor may satisfy the requirements of subsections (a) through (d) of this section by maintaining on file with the department a surety bond in the amount of $5,000.00 for the period running concurrently with the plumbing contractor's license, so long as such bond specifically provides coverage for any and all street excavations undertaken pursuant to this article during such period, unless the city engineer determines such bond amount is insufficient to cover the anticipated cost of restoration of the right-of-way for which the permit is sought. A plumbing contractor qualified to perform street right-of-way restoration work who chooses to perform the street right-of-way restoration work itself or through its qualified subcontractor or independent contractor must comply with subsections (a) through (d) and (g) through (i) of this section. (f) Restoration by city or city contractor. If an applicant for an excavation permit is not qualified to perform right-of-way restoration work as provided in this division and requests in the permit application to have the city or the city's contractor restore the right-of-way, the applicant shall pay the costs thereof within 30 days of billing. If, during the 48 months following such restoration, the pavement settles due to the permittee's improper backfilling, the permittee shall pay to the city, within 30 days of billing, the cost of repairing the pavement. (g) Restoration by permittee. An applicant for an excavation permit who has been determined qualified to perform right-of-way restoration work as provided in this section and who intends to itself restore the right-of-way shall so indicate in its application for an excavation permit. The permittee shall perform the work in accordance with the city's utility accommodation and street restoration specifications, unless the city engineer deems other or additional specifications must be utilized in order to secure proper restoration. The city engineer shall have the authority to prescribe the manner and extent of the restoration and may do so in written procedures of general application or on a case-by-case basis. The city engineer in exercising this authority shall be guided by the following standards and considerations: the number, size, depth and duration of the excavations, disruptions or damage to the right-of-way; the preexcavation condition of the right-of-way; the remaining life expectancy of the right-of-way affected by the excavation; whether the relative cost of the method of restoration to the permittee is in reasonable balance with the prevention of the accelerated depreciation of the right-of-way that would otherwise result from the excavation, disturbance or damage to the right-of-way; and the likelihood that the particular method of restoration would be effective in slowing the degradation of the right-of-way that would otherwise take place. Methods of restoration may include but are not limited to patching, replacement of the right-of-way base, and milling and overlay of the entire area of the right-of-way affected by the work. By choosing to restore the right-of-way itself, the permittee guarantees its work and shall maintain it for 48 months following its completion. During this 48-month period, the permittee shall, upon notification from the department, correct all restoration work to the extent necessary using the method required by the department. Such work shall be completed within the period of time allotted therefor as set forth in the notice from the department. If the permittee fails to restore the right-of-way in the manner and to the condition required by the department or fails to satisfactorily and timely complete all repairs required by the department, the city, at its option, may do such work or cause its contractor to do such work. In that event, the permittee shall pay to the city, within 30 days of billing, all costs incurred by the city in restoring the right-of-way. (h) Identity of person performing restoration work. Any person restoring a permanently improved street shall provide permanent identification of the person performing the restoration work and the month and year such work was performed by imprint or medallion within the restored surface, as provided in the city's utility accommodation and street restoration specifications. (i) Bond for obstruction permit. If the city engineer determines in his or her sole discretion that an obstruction permit applicant's proposed use of the right-of-way poses a risk of damage to the right-of-way, the city engineer may require such applicant to post a surety bond before the obstruction permit is issued. Such bond, if required, shall be placed on file with and approved by the city engineer; shall be in the minimum amount of $5,000.00 or such other amount determined by the city engineer to be sufficient to cover the anticipated cost of damage to the right-of-way; and shall be conditioned to ensure removal of the obstruction and restoration of the right-of-way and all public improvements thereon by or before the expiration date of such obstruction permit or such extended time as may be granted by the city engineer.
(C42, § 84-5; C54, C62, § 54-73; C75, C79, § 23-62; C91, § 23-63; O.11,711, 13,638, 14,202, 14,463, 15,092, 15,188)