4-23-6. - EROSION AND SEDIMENT CONTROL PLANS.

Erosion and sediment control plans shall incorporate the following items: (A) Detailed construction phasing plan identifying erosion and sediment control measures to be in place for each phase. (B) Erosion and sediment control measures to be installed initially prior to stripping existing vegetation or mass grading. (C) Methods for conveying flows through the sire during construction. These methods must include the temporary and permanent stabilization measures to be used to reduce velocity and erosion from flow through the construction zone. (D) A maintenance schedule for each measure used. At a minimum, all erosion and sediment control measures onsite shall be inspected weekly or after a one-half inch or greater rainfall event. (E) Identification of sensitive areas and any areas that require buffers.

(Ord. No. 43-O-19, § 1, 5-13-2019)