§ 23-88 — Duration of industrial discharge permits
Code of Ordinances of the City of Brockton, Massachusetts (Codified through Ordinance No. 07-31-2025(2), approved July 31, 2025 (Supp. No. 28)) · Brockton Code of Ordinances § 23-88
Corpus is an independent public-information project, not the official City of Brockton website. Stable reference: corpuslaw.us/code/5cf46d0c-5054-4160-a85c-1d0744e4ddd8
Sec. 23-88. - Duration of industrial discharge permits.
Industrial discharge permits shall be issued for a specified time period not to exceed five (5) years. An industrial discharge permit may be issued for a period less than a year or may be stated to expire on a specific date. An industrial user shall apply for industrial discharge permit reissuance, on a form prescribed by the commissioner, at least ninety (90) days prior to the expiration of the industrial user's existing permit. Sewer connection permits are exempt from this reapplication requirement, as long as the subject connection has been constructed, effected and maintained in accordance with said permit. Any modification, increase in flow or change in use of said connection is not exempt and shall be the subject of a sewer connection permit application pursuant to section 23-83.
(Ord. No. D395, 10-18-96)
Ask a question about Brockton law
Corpus searches the Brockton sections it holds and shows the ones that match, with their citations. Free, no sign-in.