Sec. 25-127. Urgent work.
When traffic conditions, the safety or convenience of the traveling public or the public interest require that the excavation work be performed as emergency work, the city shall have the full power to order, at the time the permit is granted, that a crew and adequate facilities be employed by the permittee beyond normal working hours, including up to twenty-four (24) hours a day, to the end that such excavation work may be completed as soon as possible.
(Ord. No. 10-97, 6-16-97)