§ 12-5-5 — Installation of grease interceptors

Code of Ordinances of the City of Rochester, Minnesota (Codified through Ordinance No. 4589, enacted June 1, 2026 (Supp. No. 8, Update 2)) · Rochester Code of Ordinances § 12-5-5

Corpus is an independent public-information project, not the official City of Rochester website. Stable reference: corpuslaw.us/code/93f867f3-7960-418f-abe5-28a3d2ca3043

Sec. 12-5-5. - Installation of grease interceptors.

Grease interceptors required by this chapter shall be installed in accordance with the plumbing code as adopted by the state and as follows: (1) Grease interceptors shall be installed at the expense of the building owner or operator of the FSE which is contributing wastewater to the POTW. (2) All wastewater streams containing FOG within FSEs shall be directed into an appropriately sized grease interceptor before discharge to the POTW. (3) Grease interceptors shall be designed, constructed, and installed in accordance with the plumbing code as adopted by the state and in compliance with this chapter. (4) A plumbing permit and inspection is required for each grease interceptor installation made pursuant to this chapter. The plumbing inspector shall review all relevant information regarding the rated performance of the grease interceptor and the building plan and facility site plan for the building and site where the grease interceptor has been installed, and shall approve such grease interceptor installation upon determination that the grease interceptor meets all requirements of the plumbing code, as adopted by the state. (5) Gravity grease interceptor installation is preferred over hyrdromechanical grease interceptors due to lower maintenance costs and better FOG removal. Excluding all scenarios covered by section 12-5-3(e), the FSE has the option to install the compliance grease interceptor of their choosing and will be required to maintain such as specified in this chapter. (6) Hydromechanical grease interceptors shall be sized and installed in compliance with the requirements of the plumbing code as adopted by the state and in accordance with this chapter. (7) Gravity grease interceptors shall be sized and installed in accordance with the requirements of the plumbing code as adopted by the state and in accordance with this chapter. Gravity grease interceptors shall have a minimum capacity of 1,000 gallons and shall not exceed 3,000 gallons for a single unit. Where a capacity greater than 3,000 gallons is required, several smaller units shall be installed in series. If an FSE wishes to install a gravity grease interceptor smaller than 1,000 gallons or larger than 3,000 gallons, the owner of the FSE must file an exemption form with the manager with sufficient evidence that the interceptor can be cleaned and maintained properly. (8) Gravity grease interceptors shall have access manholes with a minimum diameter of 24 inches over each chamber and sanitary tee. Access manholes shall extend from the gravity grease interceptor to at least the finished surface grade and be designed and maintained to prevent stormwater or surface water inflow and groundwater infiltration. The manholes shall also have readily removable covers to facilitate inspection and grease removal. If an FSE wishes to install a gravity grease interceptor with manhole lids smaller than 24 inches, the owner of the FSE must file an exemption form with the manager with sufficient evidence that the interceptor can be cleaned and maintained properly. (9) Gravity grease interceptors shall be installed on private property and shall not be installed within a public right-of-way or public easement unless an application for a revocable encroachment permit is presented to and approved by the city council. (10) Gravity grease interceptors shall be designed and manufactured in accordance with the plumbing code as adopted by the state and this section. Concrete tank gravity grease interceptors shall be approved by building safety officials and constructed out of concrete with admixtures and/or coatings in order to decrease problems associated with corrosion or decaying of poured concrete in sanitary sewer applications. (11) Gravity grease interceptors shall be designed, constructed, and installed for adequate AASHTO H-20 vehicle traffic load bearing capacity or greater regardless of installed location for safety purposes. (12) Where gravity grease interceptors are shared by more than one FSE, the building owner shall be the responsible party for record keeping and maintaining of the interceptor. (13) Sewer lines that are not grease-laden, that are not likely to contain FOG, or that contain sanitary wastes shall not be connected to a grease interceptor.

(Code 1965, § 76C.05; Ord. No. 4453, § 9, 12-6-2021; Ord. No. 4489, § 2, 2-6-2023)