For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 98-33 — Permit validity—Area, dates

Code of the City of Springfield, Missouri (Supp. No. 23, Update 2: codified through G.O. No. 6973, enacted January 12, 2026) · Springfield, Mo., City Code § 98-33

Corpus is an independent public-information project, not the official City of Springfield website. Stable reference: corpuslaw.us/code/78a1905e-2825-4011-a883-eb5033c159d9

Sec. 98-33. - Permit validity—Area, dates.

(a) Any right-of-way work permit, temporary traffic control permit, or excavation permit shall only be valid for the area specified within such permit. (1) No right-of-way user may cause any excavation or work to be done outside the area specified in the applicable permit, except as provided herein. (2) No right-of-way user may cause temporary traffic control to be done outside the area specified in the temporary traffic control permit, except as provided herein. (3) Any right-of-way user who determines that work or excavation must take place outside the area specified in the applicable permit shall do the following prior to the commencement of work or excavation in that outside area: a. Make application to amend a right-of-way permit or excavation permit, describing the area in which the excavation or work will occur, and b. Pay any additional fees required as a result. (4) Any right-of-way user who determines that temporary traffic control is necessary for an area greater than that which is specified in the temporary traffic control permit must do the following prior to the commencement of temporary traffic control in that greater area: a. Make application to amend a traffic control permit, describing the area in which the temporary traffic control will occur, and b. Pay any additional fees required as a result. (b) Any right-of-way work permit, temporary traffic control permit, or excavation permit shall be valid for 60 days from the date indicated on the permit unless a shorter amount of time is specified in the permit. (1) A right-of-way user shall not commence excavation or work before the right-of-way or excavation permit start date or, except as provided herein, continue excavation or work after the end date. If a right-of-way user does not complete the excavation or work by the permit end date, the right-of-way user must apply for and receive a new right-of-way or excavation permit or an extension for additional time, and pay any additional fees required as a result. (2) A right-of-way user shall not perform any work requiring temporary traffic control before the temporary traffic control permit start date or, except as provided herein, continue any work requiring temporary traffic control after the end date specified in the permit. If work requiring temporary traffic control is required beyond the temporary traffic control permit end date, the right-of-way user must apply for and receive a new temporary traffic control permit or an extension for additional time, and pay any additional fees required as a result. Notwithstanding the above, any temporary traffic control measures necessary to protect public safety shall remain in place until the director authorizes the removal of such measures. (3) If work will continue beyond the length of time specified in any permit, the right-of-way user must apply for another permit or extension of time. To work in the right-of-way without interruption, a supplementary application must be submitted to the city and approved prior to the permit end date. (c) A right-of-way permit, traffic control permit, or excavation permit will only be valid for those persons indicated on the approved permit and may be transferred only with prior written consent of the director of public works.

(G.O. No. 6966, § 1(Exh. A), 12-15-2025)

Ask a question about Springfield law

Corpus searches the Springfield sections it holds and shows the ones that match, with their citations. Free, no sign-in.