§ 506 — DETENTION\RETENTION SUBMITTAL REQUIREMENTS

Comprehensive Development Regulations for the City of Flowood; partial · Flowood Development Regulations § 506

Corpus is an independent public-information project, not the official City of Flowood website. Stable reference: corpuslaw.us/code/f2c471e1-90e4-48f0-ba00-7438fae8d157

SECTION 506 DETENTION\RETENTION SUBMITTAL REQUIREMENTS

506.1 Construction Plans shall at a minimum include the following information:

a. Finished grade contours on the grading and drainage plan sheets showing the geometry and vertical information of the basins for above ground basins.

b. For underground detention, the system layout shall be shown on the grading and drainage plan sheets.

c. A typical cross section of detention\retention basins showing the side-slopes and width of the embankment top.

d. Detail of any outlet structure(s).

e. Details of emergency spillway.

f. For underground detention, typical cross sections shall be provided along with other detailed information necessary to construct the detention system to meet the manufacturer’s specifications. Cross sections, details and elevation information shall be site specific and not generic in nature.

506.2 Hydraulic calculations including the following information shall be provided in an easy-

to-follow format to the City with the submittal of the construction plans:

a. Map or maps as required to depict the pre-development drainage basins and areas of each basin in acres.

b. Map or maps as required to depict the post-development drainage basins and areas of each basin in acres.

c. Information on each individual drainage basin such as: drainage area, hydraulic length, hydraulic slope, CN, weighted CN, and any other input assumptions.

d. Map depicting the Pre & Post Flow rate at each major drainage exit point for the 2-yr, 25-yr & 100-year events.

e. Calculations (preferably in table format) shall be provided which show the pre- development rate of run-off at each of the exit points for the 2-year, 5-year, 10-year, 25- year, 50-year and 100-year 24-hour storm events.

f. Calculations (preferably in table format) shall be provided which show the post- development rate of run-off at each of the exit points for the 2-year, 5-year, 10-year, 25- year, 50-year and 100-year 24-hour storm events.

g. Stage-Storage-Discharge curves for the detention\retention basins.

h. Inflow hydrographs for the 2, 5, 10, 25, 50, and 100-year 24-hour storm events.

i. Outflow hydrographs for the 2, 5, 10, 25, 50, and 100-year 24-hour storm events.

j. Post-development hydrograph routing the 100-year event through the basin with only the emergency spillway active.

k. Backwater elevations for the flood elevations for 2, 5, 10, 25, 50, and 100-year 24-hour storm events and any impacts on the storage volume.

l. The FEMA 100-year flood elevation at the location of the proposed detention basin and any impacts on the storage volume.