Sec. 14-223. - Erosion and sediment control plan.

(a) Erosion and sediment control plan development. An erosion and sediment control plan shall be developed and implemented by the owner or operator of a construction project. The erosion and sediment control plan must include a description of appropriate control measures (i.e., BMPs) that will be implemented as part of the construction activity to control pollutants and other matter in stormwater discharges. (1) The erosion and sediment control plan shall be submitted to the city with the application for the site development permit and retained at the permitted site or locally available. A copy of the erosion and sediment control plan must be made available to the city inspectors for review at the time of any on-site inspection. (2) BMPs shall be in place upon commencement of construction. (3) The public works director may notify the owner or operator at any time that the erosion and sediment control plan does not meet the minimum requirements of this division. After notification, the owner or operator shall amend the erosion and sediment control plan, implement the changes and certify in writing to the public works director that the requested changes have been made. Unless otherwise approved by the public works director, the requested changes shall be made immediately. (4) The owner or operator shall amend the erosion and sediment control plan and implement the changes before there is a change in construction, operation, or maintenance, which may potentially affect the discharge of pollutants. (5) The owner or operator shall amend the erosion and sediment control plan and implement the changes if the erosion and sediment control plan proves to be ineffective in controlling stormwater pollutants, including, but not limited to, significant sediment leaving the site and non-functioning BMPs. (b) Erosion and sediment control plan details. (1) Owner or operator. The erosion and sediment control plan shall identify the owner or operator as defined in section 14-187. The owner or operator's name, complete mailing address and telephone numbers shall be identified on the plan. (2) Erosion and sediment control plan. The erosion and sediment control plan shall include: a. A scaled site map showing total area of the site, original and proposed contours (if practicable), direction of flow of stormwater runoff, adjacent receiving water bodies, north arrow, all erosion and sediment controls (vegetative and structural), and the increase in impervious area. This map should be at a scale no smaller than one inch to 100 feet. b. A sequence of construction of the development site, including stripping and clearing, rough grading, construction of utilities, infrastructure, and buildings, and final grading and landscaping. Sequencing shall identify the expected date on which clearing will begin, the estimated duration of exposure of cleared areas, and the sequence of clearing, installation of temporary erosion and sediment measures, and establishment of permanent vegetation. c. All erosion and sediment control measures necessary to meet the objectives of this division throughout all phases of construction and permanently after completion of development of the site. Depending upon the complexity of the project, the drafting of intermediate plans may be required at the close of each season. d. Seeding mixtures and rates, types of sod, method of seedbed preparation, expected seeding dates, type and rate of lime and fertilizer application, and the kind and quantity of mulching for both temporary and permanent vegetative control measures. e. Provisions for maintenance of control facilities and including easements. (3) Modification to the plan. a. Major amendments of the erosion and sediment control plan shall be submitted to the city and shall be processed and approved, or disapproved, in the same manner as the original plans. b. Field modifications of a minor nature may be authorized by the city by written authorization to the permittee, which may be noted and initialed on the plan in the field. (4) Erosion and sediment controls. The owner or operator shall list and describe controls appropriate for the construction activities and the procedures for implementing the controls. Controls shall be designed to retain sediment onsite and should: a. Divert upslope water around disturbed areas; b. Limit exposure of disturbed areas to the shortest time possible; c. Disturb the smallest area possible; d. Preserve existing vegetation where possible, especially trees; e. Preserve vegetated buffer zones around any watercourse, creek, drain, lake, pond or wetland; f. Slow rainfall runoff velocities to prevent erosive flows; g. Avoid disturbing sensitive areas, such as: 1. Steep or unstable slopes; 2. Land upslope of surface waters; 3. Areas with erodible soils; or 4. Existing drainage channels; h. Transport runoff down steep slopes through lined channels or piping; i. Minimize the amount of cut and fill; j. Revegetate disturbed areas as soon as possible; k. Implement BMPs to mitigate adverse impacts from stormwater runoff; l. Remove sediment from stormwater before it leaves the site by allowing runoff to pond in controlled areas to drop out sediment; and m. Filter runoff by using natural vegetation, brush barriers, silt fences, hay bales, etc. (5) Design requirements. Grading erosion control practices, sediment control practices, and waterway crossings shall meet the design criteria set by the city and shall be adequate to prevent transportation of sediment from the site. a. Clearing and grading. 1. Clearing and grading of natural resources, such as forest and wetlands, shall not be permitted, except when in compliance all other provisions of this division and all other applicable federal and state laws. 2. Clearing techniques that retain natural vegetation and retain natural drainage patterns, as described in planning and design manual for the control of erosion, sediment and stormwater, shall be used to the satisfaction of the city. 3. Phasing shall be required on all sites disturbing greater than 30 acres, with the size of each phase to be established during plan review and as approved by the city. 4. Clearing, except that necessary to establish sediment control devices, shall not begin until all sediment control devices have been installed and have been stabilized. 5. Cut and fill slopes shall be no greater than 3:1, except as approved by the city to meet other community or environmental objectives. b. Erosion control. 1. Soil must be stabilized within five days of clearing or inactivity in construction. 2. If vegetative erosion control methods, such as seeding, have not become established within two weeks, the city may require that the site be re-seeded, or that a nonvegetative option be employed. 3. On steep slopes or in drainageways, special techniques that meet the design criteria outlined in the planning and design manual for the control of erosion, sediment and stormwater shall be used to ensure stabilization. 4. Soil stockpiles must be stabilized or covered at the end of each workday. 5. At the close of the construction season, the entire site must be stabilized, using heavy mulch layer, or another method that does not require germination to control erosion. 6. Techniques shall be employed to prevent the blowing of dust or sediment from the site. 7. Techniques that divert upland runoff past disturbed slopes shall be employed. c. Sediment controls. 1. Sediment controls shall be provided in the form of settling basins or sediment traps or tanks, and perimeter controls. 2. Where possible, settling basins shall be designed in a manner that allows adaptation to provide long-term stormwater management. 3. Adjacent properties shall be protected by the use of a vegetated buffer strip, in combination with perimeter controls. d. Waterways and watercourses. 1. When a wet watercourse must be crossed regularly during construction, a temporary stream crossing shall be provided, and an approval obtained from the appropriate governmental agency. 2. When in-channel work is conducted, the channel shall be stabilized before, during and after work. 3. All on-site stormwater conveyance channels shall be designed according to the criteria outlined in the planning and design manual for the control of erosion, sediment and stormwater. 4. Stabilization adequate to prevent erosion must be provided at the outlets of all pipes and paved channels. e. Construction site access. 1. A temporary, approved construction access shall be provided to the site at all times. 2. Other measures may be required at the discretion of the city in order to ensure that sediment is not tracked onto public streets by construction vehicles or washed into storm drains. f. Inspection. The city, or its designated agent, shall make inspections as required in this subsection and shall either approve that portion of the work completed or shall notify the permittee wherein the work fails to comply with the erosion and sediment control plan as approved. Plans for grading, stripping, excavating, and filling work bearing the stamp of approval of the city shall be maintained at the site during the progress of the work. In order to obtain inspections, the permittee shall notify the city at least two working days before each of the following occurs: 1. Start of construction; 2. Erosion and sediment control measures are in place and stabilized; 3. Site clearing has been completed; 4. Rough grading has been completed; 5. Final grading has been completed; 6. Close of the construction season; and 7. Final landscaping. The permittee or his agent shall make regular inspections of all control measures in accordance with the inspection schedule outlined on the approved erosion and sediment control plans. The purpose of the inspections will be to determine the overall effectiveness of the control plan, and the need for additional control measures. All inspections shall be documented in written form and submitted to the city at the time interval specified in the approved permit. (6) Minimum requirements. At a minimum, the controls must be in accordance with the standards set forth in, or other recognized manual of design as appropriate for the state. The erosion and sediment controls shall address the following minimum components: a. Vegetative practices shall be designed to preserve existing vegetation where possible and revegetate disturbed areas as soon as practicable after grading or construction. Such practices may include surface roughening, temporary seeding, permanent seeding, mulching, sod stabilization, vegetative buffer strips, and protection of trees. b. Structural practices shall divert flows from exposed soils, store flows or otherwise limit runoff from exposed areas. Such practices may include construction entrance/exit, straw bale dikes, silt fences, earthen dikes, brush barriers, drainage swales, check dams, subsurface drains, pipe slope drains, level spreaders, drain inlet protection, outlet protection, detention/retention basins, sediment traps, temporary sediment basins or equivalent sediment controls. c. Post-construction control measures shall be installed to control pollutants in stormwater after construction is complete. These controls include, but are not limited to, on-site infiltration of runoff, flow attenuation using open vegetated swales, exfiltration trenches and natural depressions, constructed wetlands and retention/detention structures. Where needed, velocity dissipation devices shall be placed at detention or retention pond outfalls and along the outfall channel to provide a nonerosive flow. (7) Housekeeping practices. The owner or operator shall describe and list practices appropriate to prevent pollutants from entering stormwater from construction sites due to poor housekeeping. The owner or operator shall: a. Designate areas for equipment maintenance and repair and concrete chute wash off; b. Provide waste receptacles at convenient locations; c. Provide regular collection of waste; d. Provide protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially hazardous materials; e. Provide adequately maintained sanitary facilities; and f. Provide secondary containment around on-site fuel tanks. (8) Reporting requirements. Any releases into the environment of hazardous substances, oil, pollutants or contaminants, which pose a threat to applicable water quality standards or causes a film, sheen or discoloration of waters, shall be reported to the state emergency management agency, the national response center and the city.

(Code 1974, app. D, § 303; Ord. No. 2004-365, §§ 1, 2, 10-19-2004)