Sec. 702. - Building permit.
A. Applicability. 1. Whenever any structure or building is to be improved or erected, moved or structurally altered, a building permit shall be obtained from the inspection services administrator. 2. No building permits may be issued for any structure on any lot in a subdivision unless the lot has been included in a final plat which has been recorded or unless the lot qualifies under the following exceptions: a. Unless the prior lot of record fronts on a publicly dedicated and opened street, or; b. Unless such lot is exempt from these regulations. 3. Building permits required pursuant to N.C.G.S. § 160D-1110 may be denied for lots that have been illegally subdivided. In addition to other remedies, a city may institute any appropriate action or proceedings to prevent the unlawful subdivision of land, to restrain, correct, or abate the violation, or to prevent any illegal act or conduct. B. Application and site plan. Every applicant for a building permit application shall furnish the following information: 1. A plot, drawn to scale, showing the exact size, shape and dimension of the lot to be built upon, the exact size and location on the lot of all existing buildings, structures and easements, and the exact size and location on the lot of the structure or building proposed to be repaired, altered, erected or moved, and the size, arrangements, number or parking stalls, movement of vehicles and ingress and egress and egress drives for all off-street parking and loading facilities. 2. A declaration of the existing and intended use of each existing and proposed building or structure on the lot and the number of a families and housekeeping units that each existing building currently accommodates and is proposed to accommodate upon completion of construction. 3. Any additional information deemed necessary by the director of development services or designee to determine compliance with these regulations. 4. The director of development services or designee may require a survey of the boundaries of the lot on which the improvement is proposed to be located. If required, a surveyor registered in the State of North Carolina shall prepare such survey. C. Review and action by inspection. The director of development services and inspection services administrator shall be responsible for conducting reviews to determine if intended uses, buildings or structures comply with all applicable regulations and standards, including this LDC and the building code. The inspection services administrator shall not issue a building permit unless the plans, specification and intended use of such building or structures or part thereof conform in all respects to the provisions of this LDC and the building codes. D. Expiration and lapse of approval. 1. If the work described in any building permit has not begun within six (6) months from the date of issuance, the building permit shall expire and be of no further effect. In such cases, no further work shall occur until a new building permit has been obtained. 2. If, after commencement of construction, work is discontinued or no substantial work has occurred for a period of twelve (12) months or more, the building permit shall expire and be of no further effect. Work shall be stopped until a new building permit is obtained.
(Ord. No. O-2005-34b, § 1(Att. A), 5-9-05; Ord. No. 0-2006-2, § 3, 1-9-06; Ord. No. O-2018-78, § 3, 8-13-18; Ord. No. O-2021-43, § 7, 6-14-21)
Ask a question about Rocky Mount law
Corpus searches the Rocky Mount sections it holds and shows the ones that match, with their citations. Free, no sign-in.