§ 224A-10 — Abandonment and decommissioning
Code of the City of Mount Vernon, New York · Mount Vernon City Code § 224A-10
Corpus is an independent public-information project, not the official City of Mount Vernon website. Stable reference: corpuslaw.us/code/e28067f8-b026-4e7f-a77c-9caa1bedb845
§ 224A-10: Abandonment and decommissioning.
A. All Tier 3 solar energy systems shall submit a decommissioning plan as set forth in this chapter. B. Upon cessation of electricity generation of a solar energy system on a continuous basis for 12 months, the owner and/or operator of the solar energy system shall implement the decommissioning plan. The decommissioning plan must be completed within 120 days of cessation. C. If the owner and/or operator fails to comply with decommissioning upon any abandonment, the City may, at its discretion, utilize the bond and/or security for the removal of the solar energy system and restoration of the site in accordance with the decommissioning plan.
Ask a question about Mount Vernon law
Corpus searches the Mount Vernon sections it holds and shows the ones that match, with their citations. Free, no sign-in.