§ 4.0.20 — Timing of Improvements

Municipal Code of the City of Corvallis, Oregon (Codified through Ordinance No. 2026-31, enacted October 19, 2026. (Supp. No. 70, Update 2)) · Corvallis Land Development Code § 4.0.20

Corpus is an independent public-information project, not the official City of Corvallis website. Stable reference: corpuslaw.us/code/38338490-5b6f-4d1e-a642-4955f1a05240

Section 4.0.20 - Timing of Improvements.

a. The applicant must install, concurrent with development, all improvements the standards in this Chapter require. 1. Where a Land Division is proposed, the applicant must install or secure the required public and franchise utility improvements for each proposed lot prior to approval of the Final Plat, in accordance with the provisions of Chapter 2.4 - Land Divisions, Replats and Property Line Adjustments. 2. Where a Land Division is not proposed, the applicant must install the required public and franchise utility improvements, dedicate right-of-way consistent with standards in the Transportation System Plan, and record the right-of-way dedication prior to issuance of building permits. Applicants with development proposals that require only sidewalk and/or driveway improvements that do not require a Public Improvement by Private Contract permit may obtain building permits prior to securing or installing the improvements. 3. Following an Applicant's request, the Director may issue building permits prior to installation of required public and franchise utility improvements through a discretionary agreement. The Director will approve the agreement if the applicant satisfies the following requirements: a) Where a land division is proposed, the applicant must provide a performance guarantee for the public improvements per Section 2.4.70.07 and record the Final Plat; b) The applicant must provide complete Public Improvement by Private Contract plans which must be authorized for construction; c) The applicant must demonstrate that each lot or parcel, where building permits are requested, will be served by functional public storm, sewer and water utilities, and franchise utilities per Section 4.0.90.a; d) The applicant must submit and receive approval for a fire access plan. The applicant must demonstrate that water mains and fire hydrants will be operational for fire protection, and all street identification signs must be installed to facilitate emergency response and building inspection; e) The applicant may not connect to public water or sewer systems until the City conditionally accepts these systems; f) The applicant must apply for and receive an approved erosion prevention and sediment control permit; g) The applicant must demonstrate that all potential and actual lot purchasers have been informed in writing that required public improvements have not been accepted and the City is not liable regarding the timing of such acceptance and ability to connect or occupy; and h) The applicant must install or secure other needed improvements required to serve the development, as determined by the Director and City Engineer. 4. The applicant must install all required public improvements consistent with City standards prior to issuance of a certificate of occupancy. The Director may allow issuance of a temporary certificate of occupancy prior to completion of the public improvements in cases where unusual situations prevent their completion. 5. Exceptions - Street and alley improvements required by the standards of this chapter, including right-of-way dedication, sidewalk and planter strip improvements, are not required for the following (NOTE: Staff will evaluate the percentage-based thresholds identified below, cumulatively over a five year period): a) Residential accessory development, including Accessory Dwelling Units, except where new access is proposed from an alley, where the applicant must provide City-standard alley improvements. b) The alteration of an existing residential structure that does not result in additional dwelling units. If the alteration affects an existing Group Residential structure, the alteration may not increase the occupant load of the structure by more than 20 percent. c) With the exception of Multi-dwelling (5 units or greater) Building Types, the replacement of a Residential Building Type, as defined in Chapter 1.6, with a new residential building of the same type or a type containing fewer dwelling units, where permit applications for the replacement of the building are submitted within 18 months of the demolition final inspection approval. d) Nonresidential accessory structures that are either: i. 500 sq. feet or less in size; or ii. 3,000 sq. feet or less in size and equivalent to 20 percent or less of the primary structure's gross floor area. e) The alteration of an existing nonresidential building or structure, including nonresidential changes in use and/or occupancy, if all of the following are met: i. The alteration adds floor area of 500 sq. feet or less, or adds floor area of 3,000 sq. feet or less that is equivalent to 20 percent or less of the existing structure's gross floor area; ii. The alteration generates less than 20 new vehicle trips per day according to the ITE Trip Generation Manual; and iii. The alteration is not a Substantial Improvement, as defined in Chapter 1.6 of this Code. f) For mixed-use buildings, the above thresholds apply to each individual use component. 6. Where constrained conditions exist, either natural or built, the City will follow the Street Improvements Implementation Process in the Transportation System Plan to determine the required improvements. Where the applicant demonstrates that development qualifies for an exception to street improvement requirements under this Section, the applicant must configure new buildings and other site improvements to prevent the creation of nonconformities in the future, when the minimum right-of-way pursuant to the standards in the Transportation System Plan is dedicated or acquired. b. Where specific approval for a phasing plan has been granted for a Planned Development and/or Subdivision, the applicant must complete improvements in accordance with that plan.

(Ord. No. 2014-19, eff. 12-11-2014; Ord. No. 2018-20, eff. 7-24-2018; Ord. No. 2018-36, eff. 1-1-2019; Ord. No. 2021-22, eff. 11-24-2021; Ord. No. 2022-12, eff. 6-1-2022)