§ 1304.03 — Stormwater Management Site Plan

Pittsburgh Code of Ordinances, Pennsylvania (Code 2026-11-04: eCode360 publication current through legislation 2026-11-04 (scraped 2026-11-19)) · Pittsburgh Code § 1304.03

Corpus is an independent public-information project, not the official City of Pittsburgh website. Stable reference: corpuslaw.us/code/50e295c4-d74d-4e7e-b647-375c0e61291a

§ 1304.03: Stormwater Management Site Plan.

The following items shall be included in the SWM Site Plan submission: a. Provisions for permanent access or maintenance easements for all physical SWM BMPs, such as ponds and infiltration structures, as necessary to implement the operation and maintenance (O&M) plan discussed in subsection b.9. below. b. SWM Site Plan in accordance with requirements outlined in the City of Pittsburgh Stormwater Design Manual and containing the following information: 1. The overall stormwater management concept for the project. 2. A determination of site conditions in accordance with the City of Pittsburgh Stormwater Design Manual and DEP PA BMP Manual3. A detailed site evaluation shall be completed for projects proposed in environmentally sensitive areas, such as but not limited to brownfields and areas with steep slopes. 3. Stormwater runoff design computations and documentation as specified in this Title and the City of Pittsburgh Stormwater Design Manual, or as otherwise necessary to demonstrate that the maximum practicable measures have been taken to meet the requirements of this Title, including the recommendations and general requirements in Section 1303.01. 4. Expected project schedule. 5. A soil erosion and sediment control plan, where applicable, as prepared for and submitted to the approval authority. 6. The effect of the project (in terms of runoff volumes, water quality, and peak flows) on surrounding properties and aquatic features and on any existing stormwater conveyance system that may be affected by the project. 7. Plan and profile drawings of all SWM BMPs, including drainage structures, pipes, open channels, and swales. 8. SWM Site Plan shall show the locations of existing and proposed on-lot wastewater facilities and water supply wells, property boundaries, existing and proposed topography, point(s) of interest, utilities, and potential utility conflicts. 9. The SWM Site Plan shall include an O&M plan in accordance with the City of Pittsburgh Stormwater Design Manual for all existing and proposed physical stormwater management facilities. This plan shall address long-term ownership and responsibilities for O&M including type and schedule/frequency of maintenance activities, personnel and equipment requirements, estimated annual maintenance costs, and method of financing continuing O&M. 10. A justification in accordance with the City of Pittsburgh Stormwater Design Manual requirements, acceptable to the Designated Plan Reviewer, must be included in the SWM Site Plan if BMPs other than preferred or approved BMPs are proposed to achieve the volume, rate and water quality controls under this Title. See Chapter 1303 and the City of Pittsburgh Stormwater Design Manual. 11. Plan call outs and tabular information designating proposed stormwater volume control offsets, rate control points of interest, additional or enlarged BMPs qualifying for stormwater management volume or rate incentives, proposed BMPs targeted for innovation track approval, and accounting of points if preferred technology incentives are being requested. 12. Technical feasibility determination reports for any drainage areas for which the applicant intends to pursue in-lieu fee compliance. c. Infiltration testing and geotechnical testing investigation report in accordance with the City of Pittsburgh Stormwater Design Manual. d. For any activities that require state or federal permits, proof of application or approval of those permit(s). e. Proof of submission of a soil erosion and sediment control plan to the Allegheny County Conservation District and approval of non-permitted plan, per 25 PA Code 102.4(b)(2)(i), or approval of General (PAG-02) or Individual NPDES Permit for Stormwater Discharges Associated with Construction Activities, or Erosion and Sediment Permit (ESCP) as applicable.

[ Ord. No. 34-2021 , § 1, eff. 10-11-2021 ]