§ 2.4.7.4 — Building Permit Required

Code of Ordinances of the City of Abilene, Texas (Supp. No. 15: codified through Ordinance No. 85-2026, enacted September 24, 2026) · Abilene Code of Ordinances § 2.4.7.4

Corpus is an independent public-information project, not the official City of Abilene website. Stable reference: corpuslaw.us/code/5e4488bb-0afc-4d1f-8677-f8d8096538f4

Section 2.4.7.4 - Building Permit Required

a. A building permit shall be required for the installation of a wind energy system: (1) The owner shall submit an application to the Building Official. The application shall be accompanied by standard drawings of the wind turbine structure, a line drawing of the electrical components, and two copies of the site plan for the wind energy system, and any fee the City requires for an accessory use or building. (2) No permit for a wind energy system shall be issued until evidence of written approval has been given to the City that the utility company has been informed of the customer's intent to install an interconnected customer-owned generator, and the utility company has expressed written approval for the system. Off-grid systems shall be exempt from this requirement. (3) Building permit applications for wind energy systems shall be accompanied by standard drawings of the wind turbine structure, including the tower, base and footings. An engineering analysis of the tower showing compliance with the City's Building Code, and certified by a licensed professional engineer, shall also be submitted. This analysis is frequently supplied by the manufacturer. (4) Building permit applications for wind energy systems shall be accompanied by a line drawing of the electrical components in sufficient detail to allow for a determination that the manner of installation conforms to the City's Electrical Code. This information is frequently supplied by the manufacturer. (5) A building permit issued for a wind energy system shall expire if the system is not installed, functioning and passed City inspection within six (6) months (i.e., 180 calendar days) following the date the permit is issued.

(Ord. No. 8-2010, pt. 1(Exh. A), 4-22-10; Ord. No. 8-2012, pt. 1(Exh. A), 1-12-12)

Ask a question about Abilene law

Corpus searches the Abilene sections it holds and shows the ones that match, with their citations. Free, no sign-in.