§ 3.9 — Site Plans
Code of Ordinances of the City of College Station, Texas (Supp. No. 10 Update 2: codified through Ordinance No. 2026-4726, adopted October 22, 2026) · College Station Land Development Ordinances, App. A, § 3.9
Corpus is an independent public-information project, not the official City of College Station website. Stable reference: corpuslaw.us/code/2b58c9ca-985d-4ab0-86af-932ab1d19cba
Sec. 3.9. - Site Plans.
Site Plan Review Process [image omitted; see the official code] A. Applicability. 1. Prior to the development of any use or structure other than single-family (excluding manufactured home parks), duplex, or townhouse, a site plan shall be approved by the City in accordance with this Section. No development shall be lawful or permitted to proceed without final site plan approval. A site plan approved as part of a conditional use permit shall be considered a site plan approval. 2. If the subject property is zoned P-MUD Planned Mixed-Use District or PDD Planned Development District, the City Council may approve a concept plan that provides for general modifications to the site development standards. The general modifications shall be indicated on the approved concept plan. The Administrator shall determine the specific standards that comply with the general modifications of the site development requirements at the time a site plan is approved. The applicant or the Administrator may have the City Council determine the specific standards that comply with the approved concept plan. 3. If the subject property is zoned WPC Wolf Pen Creek, no private development shall be lawful or permitted to proceed without site plan approval. Site plan approval shall be required for all site plans as part of a conditional use permit. The Administrator may require traffic and parking impact studies, a review of existing occupancy, and other reasonable data to determine the impact of the project. B. General Requirements. 1. All improvements reflected on approved site plans must be constructed at the time of development. All terms and conditions of site plan approval must be met at the time of development. 2. If the subject property is zoned WPC Wolf Pen Creek, all associated rehabilitation, façade work, and other construction must be conducted after and in compliance with approved elevations, colors, and materials, and comply with all requirements in the WPC Wolf Pen Creek Subsection of the Design Districts Section of Article 5, District Purpose Statements and Supplemental Standards of this UDO. Such review may take place concurrent with the site plan review or may take place separately as provided in the Development Permits Section above. C. Application Requirements. A complete application for site plan approval shall be submitted to the Administrator as set forth in the General Approval Procedures Section above. The application shall include a landscape plan illustrating compliance with the requirements of the Landscaping and Tree Protection Section of Article 7, General Development Standards of this UDO. Where applicable, applicants shall submit information, documents, and materials required in the Non-Residential Architectural Standards Section and Traffic Impact Analyses Section of Article 7, General Development Standards of this UDO. D. Site Plan Approval Process. Site plan applications shall be processed in accordance with the following requirements: 1. Pre-Application Conference. Prior to the submission of an application for site plan approval, applicants are encouraged to schedule and attend an optional pre-application conference in accordance with the Pre-Application Conference Subsection of the General Approval Procedures Section above. 2. Final Action by the Administrator. If the proposed site plan is determined to be consistent with all applicable provisions of this UDO, the Administrator shall approve or conditionally approve the site plan. A determination that all such requirements and provisions have not been satisfied shall result in disapproval of the site plan and notice of such disapproval shall be given to the applicant in writing. Conditional approval must entail corrections or changes that are ministerial and explicitly spelled out. E. Site Plan Review Criteria. The Administrator may request changes to the site plan to accomplish the following requirements. To be approved, a site plan must provide for: 1. Safe and convenient traffic control, handling, and vehicle queuing; 2. Assured pedestrian safety which may include the provision of sidewalks along the perimeter of the property; 3. Efficient and economic public utilities; 4. Public road or street access; 5. Safe and efficient internal access including public, private, or emergency; 6. Adequate parking and maneuvering areas; 7. Noise and emission control or dispersion that complies with Chapter 7, Health and Sanitation of the City of College Station Code of Ordinances; 8. Runoff, drainage, and flood control; 9. Visual screening of areas offensive to the public or adjacent developments such as detention areas, retaining walls, utilities, and solid waste facilities; 10. Compliance with standards, guidelines, and policies of the Landscape & Streetscape Standards Section of the City of College Station Site Design Standards; 11. Clear indication of what constitutes the building plot for purposes of signage; and 12. Location and density of buildings or dwelling units where topography or characteristics of the site compel a lower density than would otherwise be allowed or require location consistent with accepted engineering practices and principles. F. Additional Site Plan Review Criteria for the WPC Wolf Pen Creek Design District. All development within the WPC Wolf Pen Creek design district shall comply with the Site Plan Review Criteria Subsection above. In addition, the following standards, which affect the appearance of a development, shall govern the evaluation of a design submission in the WPC Wolf Pen Creek design district: 1. Conformance with the Comprehensive Plan, including any associated plans or studies adopted by the City Council; 2. Exterior space utilization; 3. Material selection; 4. Compatibility with existing development in the design district; 5. Vehicular, pedestrian, and bicycle circulation; 6. Building location and orientation; and 7. Specific standards listed in the Design Districts Section of Article 5, District Purpose Statements and Supplemental Standards of this UDO. G. Appeal. Appeals of site plans denied by the Administrator where the denial was based upon or a condition was imposed to assure compliance with the Site Plan Review Criteria Subsection or Additional Site Plan Review Criteria for the WPC Wolf Pen Creek Design District Subsection above shall be submitted to the Design Review Board within thirty (30) days of the decision. If no appeal is filed within thirty (30) days, the decision shall be final. The Design Review Board shall have the same authority and use the same review criteria as the Administrator in reviewing the site plan and taking final action. The Board may impose reasonable site-related conditions to mitigate the impacts of the development; however, they shall not impose architectural changes unless otherwise provided for in this UDO.
(Ord. No. 2023-4453, Pt. 1(Exh. A), 8-10-2023)
Ask a question about College Station law
Corpus searches the College Station sections it holds and shows the ones that match, with their citations. Free, no sign-in.