§ 78-110 — Failure to diligently pursue or complete work within specified time

Code of Ordinances, City of Frisco, Texas (Frisco City Code, Home Rule Charter and Code Appendix current through Ordinance 2026-10-64 adopted October 20, 2026 (eCode360 publication FR6313, scraped 2026-11-18)) · Frisco City Code § 78-110

Corpus is an independent public-information project, not the official City of Frisco website. Stable reference: corpuslaw.us/code/4641c2fc-1661-4ec3-b380-6e7a5571601b

§ 78-110: Failure to diligently pursue or complete work within specified time.

(a) In the event any work governed by this chapter is not completed or diligently pursued to completion by the right-of-way user within the time required or in accordance with the specifications required herein or by the right-of-way manager, the project or facilities that are the subject of the work shall be deemed to be abandoned facilities and any permits issued under this chapter are subject to revocation or suspension. In such an event, the right-of-way manager may cause such work to be performed as is necessary to secure the work area to a safe and passable condition. The right-of-way user shall reimburse the city for the costs of securing the site. It is unlawful for a right-of-way user to fail to complete or diligently pursue to completion work governed by this chapter. (b) For purposes of this section, a right-of-way user shall be considered to have diligently pursued completion of work in the right-of-way when the right-of-way user: (1) does not cease or abandon such work for more than three business days, subject to reasonable delays due to inclement weather or emergencies, and unless an extension of time is granted by the franchise utilities coordinator or right-of-way manager; or (2) completes all work within 120 days of the date of the first written request for relocation of conflicting facilities was made, subject to extensions of time approved by the city's franchise utilities coordinator or right-of-way manager due to inclement weather, emergencies or other good cause.

( Ordinance 02-05-65 , sec. 3(2.38), adopted 5/7/02 ; Ordinance 17-08-58 , sec. 2, adopted 8/15/17 ; Ordinance 2025-05-30 adopted 5/20/2025 )