Sec. 32-49. - Stormwater management site plan requirements.

(a) A SWMSP shall be required with site disturbance permit applications and shall include sufficient information to evaluate the environmental characteristics of the site, the potential impacts of all proposed land disturbing activity of the site on the affected water resources, both present and future, and the effectiveness and acceptability of the measures proposed for managing stormwater generated at the site. This information is required to enable the director to determine the type of stormwater management measures necessary for the proposed project, and to ensure adequate planning for management of stormwater runoff from future land disturbing activities. (b) The following information, in addition to the information required by Chapter 10, "Post-Construction Stormwater Best Management Practices," and other applicable sections of the DDM shall be included in the SWMSP: (1) Plan. A map (or maps) depicting the site layout plan that indicates: (A) The location of proposed structural and non-structural stormwater management facilities; (B) The drainage patterns and drainage areas that drain to each stormwater management facility or BMP; (C) The limits of land disturbing activities and any natural areas that are proposed to be preserved; (D) The percentage of the total disturbed area that drains to one or more stormwater BMPs and the limits of CBZs, if applicable; and (E) For BMP credits related to site design BMPs, the map(s) shall show special flood hazard areas, natural features, sensitive areas or erodible soils, as applicable, to demonstrate compliance with the DDM. (2) Engineer Analysis. An engineering analysis is required to show that the proposed stormwater management measures are capable of controlling runoff from the site in compliance with this article, the specifications included within the DDM, and other applicable provisions of this chapter. (3) Inventory. A written or graphic inventory, as described in the DDM, of the natural resources existing at the site and surrounding area (a minimum of 500 feet from the property line) prior to the proposed or actual commencement of land disturbing activities and a description of the applicable watershed and its relation to the site. This description should include a discussion of soil conditions, forest cover, topography, wetlands, and other native vegetative areas in applicable areas. (4) Maintenance and Repair Plan. The design and planning of all stormwater management facilities shall include detailed maintenance and repair procedures to ensure their continued functionality. This plan shall identify the parts or components of a stormwater management facility that need to be maintained and the equipment and skills or training necessary. Provisions for the periodic review and evaluation of the effectiveness of the maintenance program and the need for revisions or additional maintenance procedures, which meet all specifications found in the DDM, shall also be included in this plan. (5) Maintenance easement, covenant and agreement ("agreement"). Except for CBZs, the applicant shall ensure that all proposed BMPs are perpetually maintained. As such, the applicant shall reserve or secure perpetual access and maintenance easements to all stormwater BMPs at the site for the purpose of inspection, repair and perpetual maintenance. The landowner may assign the respective maintenance and repair obligations to a Home Owners Association, upon formal written consent of the same, or retain the same. The agreements shall be presented to the City in draft form as a part of the SWMSP. Following completion and release of all initially required actions contemplated by the SWMSP, the applicable agreements shall be recorded with the SWMSP in the real property records of Bell County at the applicant's expense. The agreement shall also conform to the following: (A) The agreement shall contain affirmative language, in the nature of a covenant running with the land, obligating the landowner, his successors, heirs and assigns, to perpetually preserve, protect and maintain the stormwater BMPs and otherwise comply with this article; (B) The agreement shall identify the city as co-grantee for access and inspection purposes and as a beneficiary to said agreement's obligations; (C) The agreement shall include any and all maintenance easements required to access and inspect the stormwater management facilities, and to perform routine maintenance as necessary to ensure the perpetual functionality of the stormwater management facility in accordance with this article and the applicable SWMSP; (D) The agreement shall provide for access to the facility for periodic inspection by the city for regular or special assessments of the property to ensure that the facility is maintained in proper working condition to meet design standards and any other provisions established by this article; (E) The agreement shall provide a schedule describing necessary maintenance activities and providing a periodic schedule for the same to ensure continued functionality of the stormwater management facility. The agreement shall also include a schedule for interim periodic inspections to ensure proper performance of the facility between scheduled maintenance. Maintenance and inspection schedules shall conform to the DDM and section 32-60 of this article; and (F) The agreement shall provide a provision authorizing the city, upon written notification thereof, to increase the inspection and maintenance requirements as deemed reasonably necessary to ensure proper functioning of the stormwater management facility. (6) Maintenance by city. In its sole discretion, upon written request of the applicant accompanying the SWMSP, the director may agree in writing, under terms the director may deem necessary and beneficial, to accept and maintain easements containing a site's stormwater management facility as a publicly-dedicated improvement following completion of BMP construction and stabilization, if a public benefit to said acceptance is proposed by the applicant and validated by the director. This agreement may be tentatively reached as a substitute for the maintenance easement, covenant and agreement required above. If the facility or facilities are constructed in compliance with the terms of the agreement and this article, it will be accepted by the city. However, this provision shall not be construed as a guarantee of the city's final acceptance of any BMP as a public improvement that does not comply with the terms of any such agreement or this article. (7) A concept plan is required to evaluate the maximum development potential of a site and adjacent properties under current common ownership and its affect on the objectives of this article under existing zoning, regardless of whether the applicant presently intends to develop the site to its maximum potential. (c) For land disturbing activity proposed on a redevelopment site, an applicant shall be required to include within the SWMSP measures for controlling existing stormwater runoff discharges from the site in accordance with the standards of this article, to the maximum extent practicable.

(Ord. No. 12-046, § I, 8-7-12)