§ 46-215: Casing generally.
In the drilling of an oil and/or gas well, new pipe with a mill test pressure of not less than 1,000 pounds per square inch shall be set for surface casing at a depth below the surface of not less than that required by the state railroad commission for the McAllen Field, and shall be cemented from the bottom of the pipe to the surface with proper mixture of cement. Cementing shall be by the pump and plug method. Cement shall be allowed to stand under pressure a minimum of 12 hours, and a total of 24 hours shall elapse before drilling plug or initiating tests. Casing shall be tested by pump pressure in the following manner: Apply pump pressure of at least 1,000 pounds per square inch; if at the end of 30 minutes the pressure shows a drop of 100 pounds or more, corrective measures shall be required, and after such corrective operation, the casing shall again be tested in the same manner until it shall be found to comply with the specifications set out in this section.
( 1966 Code, § 20-47 )
Ask a question about McAllen law
Corpus searches the McAllen sections it holds and shows the ones that match, with their citations. Free, no sign-in.