§ 13-124 — Time limits on applicability of design criteria and grandfathering
Code of the City of Alexandria, Virginia (Supp. No. 156: codified through Ordinance No. 5616, adopted January 24, 2026) · Alexandria Zoning Ordinance § 13-124
Corpus is an independent public-information project, not the official City of Alexandria website. Stable reference: corpuslaw.us/code/5ee077f7-5167-47eb-95fa-c6d318ab836b
13-124 - Time limits on applicability of design criteria and grandfathering.
(A) The time limits on applicability of design criteria shall apply provided: (1) Land-disturbing activities that obtain an initial state permit or commence land disturbance prior to July 1, 2014 shall be conducted in accordance with the technical criteria in 9VAC25-875-670 et seq. Such projects shall remain subject to these technical criteria for two additional state construction general permit cycles. After such time, portions of the project not under construction shall become subject to any new technical criteria adopted by the board. (2) Land-disturbing activities that obtain an initial state construction general permit on or after July 1, 2014 shall be conducted in accordance with the technical criteria in sections 13-109(E) and (F), except for as provided in subsection (B) below, and shall remain subject to this technical criteria for two additional state permit cycles. After such time, portions of the project not under construction shall become subject to any new technical criteria adopted by the board. (3) Nothing in this section shall preclude an operator from constructing to a more stringent standard at his/her discretion. (B) Grandfathering provisions established in 9VAC25-875-490 shall apply to this article as applicable. Any land-disturbing activity shall be considered grandfathered by the VESMP authority and shall be subject to the technical criteria of Article 4 (9VAC25-875-670 et seq) of Part V of the Regulations, provided: (1) A proffered or conditional zoning plan, zoning with a plan of development, preliminary or final subdivision plat, preliminary or final site plan, or any document determined by the locality to be equivalent thereto (i) was approved by the locality prior to July 1, 2012, (ii) provided a layout as defined in 9VAC25-875-670, (iii) will comply with the technical criteria of 9VAC25-875-670, (iv) has not been subsequently modified or amended in a manner resulting in an increase in the amount of phosphorus leaving each point of discharge, and such that there is no increase in the volume or rate of runoff; (2) A state permit has not been issued prior to July 1, 2014; and (3) Land disturbance did not commence prior to July 1, 2014. (C) Locality, state and federal projects shall be considered grandfathered and shall be subject to the technical criteria in 9VAC25-875-490 provided: (1) There has been an obligation of locality, state or federal funding, in whole or in part, prior to July 1, 2012, or the department has approved a stormwater management plan prior to July 1, 2012; (2) A state permit has not been issued prior to July 1, 2014; and (3) Land disturbance did not commence prior to July 1, 2014. (D) Land-disturbing activities grandfathered under subsections (A) and (B) of this section shall remain subject to Article 4 of Part V of the Regulations, 9VAC25-875-670 et seq. technical criteria for one additional state permit cycle. After such time, portions of the project not under construction shall become subject to any new technical criteria adopted by the board. (E) In cases where governmental bonding or public debt financing has been issued for a project prior to July 1, 2012, such project shall be subject to the technical criteria of Article 4 of Part V of the Regulations, 9VAC25-875-670. (F) Nothing in this section shall preclude an operator from constructing to a more stringent standard at his discretion. (G) However, these applicable land-disturbing activities are also subject to more stringent City criteria effective prior to July 1, 2014. This includes the definition of "site," treating the entire Alexandria water quality volume in section 13-109(E), the pre/post-development peak flow rate requirement for the ten-year 24-hour storm event in section 13-109(F)(2), the requirements in section 13-109(F)(3), and the requirements in section 13-109(F)(7).
Ask a question about Alexandria law
Corpus searches the Alexandria sections it holds and shows the ones that match, with their citations. Free, no sign-in.