Sec. 3.1. - Review and approval of plans; prohibitions.

A. The VESMP Administrator shall review and approve soil erosion control and stormwater management (ESM) plans, except for activities not required to comply with the requirements of the Virginia Erosion and Stormwater Management Act (VESMA). Activities not required to comply with VESMA are defined in 9VAC25-875-90. B. A person shall not conduct any land-disturbing activity in the City until: 1. An application that includes a permit registration statement, if required, a soil erosion control and stormwater management plan or an executed agreement in lieu of a plan, if required, has been submitted to the VESMP Administrator. 2. The name of the individual who will be assisting the owner in carrying out the activity and holds a Responsible Land Disturber certificate is submitted to the VESMP Administrator except that such certificate shall not be required where an agreement in lieu of a plan for construction of a single-family detached residential structure is provided; however, if a violation occurs during the land-disturbing activity for the single-family detached residential structure, then the owner shall correct the violation and provide the name of the individual holding a Responsible Land Disturber certificate. Failure to provide the name of an individual holding a Responsible Land Disturber certificate prior to engaging in land-disturbing activities may result in revocation of the land-disturbance approval and shall subject the owner to the penalties provided by this Ordinance; and 3. The VESMP Administrator issued its land-disturbance approval. In addition, as a prerequisite to engaging in an approved land-disturbing activity, the name of the individual who will be assisting the owner in carrying out the activity and holds a Responsible Land Disturber certificate shall be submitted to the VESMP Administrator may waive the Responsible Land Disturber certificate requirement for an agreement in lieu of a plan for construction of a single-family detached residential structure; however, if a violation occurs during the land-disturbing activity for the single-family detached residential structure, then the owner shall correct the violation and provide the name of the individual holding a Responsible Land Disturber certificate. Failure to provide the name of an individual holding a Responsible Land Disturber certificate prior to engaging in land-disturbing activities may result in revocation of the land-disturbance approval and shall subject the owner to the penalties provided by this Ordinance. C. The VESMP Administrator may require changes to an approved ESM plan in the following cases: 1. Where inspection has revealed that the plan is inadequate to satisfy applicable regulations or ordinances; or 2. Where the owner finds that because of changed circumstances or for other reasons the plan cannot be effectively carried out, and proposed amendments to the plan, consistent with the requirements of this Ordinance, are agreed to by the VESMP Administrator and the owner. D. In order to prevent further erosion, the VESMP Administrator may require approval of an erosion and sediment control plan and a stormwater management plan for any land it identifies as an erosion impact area. Prior to issuance of any land-disturbance approval, the VESMP Administrator may also require an applicant, excluding state agencies and federal entities, to submit a reasonable performance bond with surety, cash escrow, letter of credit, any combination thereof, or such other legal arrangement it finds acceptable, to ensure that it can take measures at the applicant's expense should he fail, after proper notice, within the time specified to comply with the conditions it imposes as a result of his land-disturbing activity. If the VESMP Administrator takes such action upon such failure by the applicant, it may collect from the applicant the difference should the amount of the reasonable cost of such action exceed the amount of the security held. Within sixty (60) days of the completion of the VESMP Administrators' conditions, such bond, cash escrow, letter of credit, or other legal arrangement, or the unexpended or unobligated portion thereof, shall be refunded to the applicant or terminated. E. The City may enter into an agreement with an adjacent VESMP authority regarding the administration of multijurisdictional projects, specifying who shall be responsible for all or part of the administrative procedures. Should adjacent VESMP authorities fail to reach such an agreement, each shall be responsible for administering the area of the multijurisdictional project that lies within its jurisdiction. F. No exception to, or waiver of, post-development nonpoint nutrient runoff compliance requirements shall be granted unless offsite options have been considered and found not available in accordance with Code of Virginia § 62.1-44.15:35(D). G. The City is authorized to cooperate and enter into agreements with any federal or state agency in connection with the requirements for land-disturbing activities in accordance with Code of Virginia § 62.1-44.15:50.

(Ord. No. 3784, 9-17-24)