§ 12.08C.430 — Industrial wastewater discharge permit transfer
Municipal Code, City of Tacoma, Washington (Tacoma Municipal Code current through legislation adopted 2026-09-30 (eCode360 publication TA6977, scraped 2026-11-18)) · Tacoma Municipal Code § 12.08C.430
Corpus is an independent public-information project, not the official City of Tacoma website. Stable reference: corpuslaw.us/code/f2bfd99a-aca3-48ef-88c4-d9dab79571f0
§ 12.08C.430: Industrial wastewater discharge permit transfer.
A. Industrial wastewater discharge permits may be transferred to a new owner or operator subject to approval by the Control Authority. A permittee and new owner or operator seeking such transfer shall submit a joint or concurrent written request(s) to the Control Authority at least thirty (30) days in advance of the scheduled transfer date requesting the Control Authority to approve the transfer and modify the industrial wastewater discharge permit as needed to reflect the new owner or operator. Failure to provide a request for transfer in accordance with this section shall operate to revoke any and all rights granted under the industrial wastewater discharge permit to discharge to the POTW effective as of the date of the facility transfer to the new owner or operator. The joint or concurrent request(s) to the Control Authority under this section shall (each) include a written certification by a duly authorized representative of permittee and the new owner or operator which: 1. States that there is no immediate intent to change the facility’s operations and processes; 2. Identifies the specific date on which the facility transfer will occur; 3. Identifies the legal name and trade name, if any, of the new owner and operator, and the address of its corporate offices; 4. Identifies the name and contact information of the duly authorized representative of the new industrial user, the mailing address at which such representative may receive notice(s) from the Control Authority, and the name and contact information for the facility manager, if different than the duly authorized representative of the industrial user; and 5. Acknowledges and agrees that: a. The new owner or operator has a legal, valid and binding obligation to comply with all requirements of the transferred industrial wastewater discharge permit; b. Such transfer is within the power and authority of the permittee and the new owner or operator without consent of any other party and has been authorized by all requisite corporate or partnership action on the part of the permittee and new owner or operator; c. Neither the transfer nor the Control Authority’s approval of the transfer shall relieve the permittee of any obligation or liability arising under the industrial wastewater discharge permit occurring prior to the transfer; d. The Control Authority waives none of its rights with respect to the permittee’s or the new owner’s or operator’s compliance with the terms and conditions of the permit; e. The Control Authority grants its approval of the transfer in reliance upon the representations, documents, and information provided by the permittee and new owner or operator in connection with the request for transfer; and that the approval of the transfer shall not in any way be deemed a representation by the Control Authority that the permittee or new owner or operator are in full compliance with the terms and conditions of the industrial wastewater discharge permit; and f. The facility is subject at reasonable times to inspections and gathering of samples by the Control Authority to determine whether an industrial user is complying with the requirements of this chapter and any industrial wastewater discharge permit or other control mechanism issued thereunder.
( Ord. 28761 Ex. C, 2021-05-25 )
Ask a question about Tacoma law
Corpus searches the Tacoma sections it holds and shows the ones that match, with their citations. Free, no sign-in.