For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 19.02.070 — Special procedures for Washington State Department of Transportation (WSDOT) Projects

Municipal Code, City of Tacoma, Washington (Tacoma Municipal Code current through legislation adopted 2026-09-30 (eCode360 publication TA6977, scraped 2026-11-18)) · Tacoma Municipal Code § 19.02.070

Corpus is an independent public-information project, not the official City of Tacoma website. Stable reference: corpuslaw.us/code/f0696c4c-0074-4ffa-9e99-192992bc4b48

§ 19.02.070: Special procedures for Washington State Department of Transportation (WSDOT) Projects.

A. Permit review time for projects on a state highway is 90 days after submission of a complete application to the city pursuant to RCW 47.01.485. B. Projects that address significant public safety risks may begin twenty-one days after the date of filing if all components of the project will achieve no net loss of shoreline ecological functions pursuant to RCW 90.58.140.

( Ord. 28612 Ex. A, 2019-09-24 , previously codified as TSMP Section 2.7.)

Ask a question about Tacoma law

Corpus searches the Tacoma sections it holds and shows the ones that match, with their citations. Free, no sign-in.