§ 19.02.070: Special procedures for Washington State Department of Transportation (WSDOT) Projects.
A. Permit review time for projects on a state highway is 90 days after submission of a complete application to the city pursuant to RCW 47.01.485. B. Projects that address significant public safety risks may begin twenty-one days after the date of filing if all components of the project will achieve no net loss of shoreline ecological functions pursuant to RCW 90.58.140.
( Ord. 28612 Ex. A, 2019-09-24 , previously codified as TSMP Section 2.7.)