§ 17.13.100 — Initiation of development
Municipal Code, City of Yakima, Washington (includes legislation through 10-06-2026) · Yakima Municipal Code § 17.13.100
Corpus is an independent public-information project, not the official City of Yakima website. Stable reference: corpuslaw.us/code/d236ee79-a349-43d1-a7e9-95749bf7abe1
§ 17.13.100: Initiation of development.
A. Amortization to Begin Construction. Each permit for a substantial development, shoreline conditional use or shoreline variance issued by the city shall contain a provision that construction pursuant to the permit shall not begin and is not authorized until twenty-one days from the date of filing with Ecology as defined in RCW 90.58.140(6) and WAC 173-27-130, or until all review proceedings initiated within twenty-one days from the date of filing of the decision. The date of filing for a substantial development permit means that date that Ecology received a final decision from the city. With regard to a permit for a shoreline variance or a shoreline conditional use, date of filing means the date the city or applicant receives the written decision of Ecology. B. Forms. Permits for substantial development, shoreline conditional use, or shoreline variance may be in any form prescribed and used by the city, including a combined permit application form. Such forms will be supplied by the city. C. Data Sheet. A permit data sheet shall be submitted to Ecology with each shoreline permit. The permit data sheet form shall be consistent with WAC 173-27-990. D. Construction Prior to Expiration of Appeal Dead-line. Construction undertaken pursuant to a permit is at the applicant’s own risk until the expiration of the appeals deadline.
( Ord. 2015-002 § 1 (Exh. A), 2015 ; Ord. 2017-017 § 2 (Exh. B), 2017 ; Ord. 2021-015 § 2 (Exh. A), 2021 )
Ask a question about Yakima law
Corpus searches the Yakima sections it holds and shows the ones that match, with their citations. Free, no sign-in.