Sec. 18-92. - Time in which permit becomes void.
The building permit shall become void unless operations are commenced within four months from the date thereof, or if the building or work authorized by such permit is suspended at any time after work is commenced for a period of 60 days. Such period of time may be extended by the chief building inspector if the delay was due to conditions beyond the control of the applicant.
(Code 1973, § 30.06.020)