Sec. 18-93. - Lapse of permit; completion of work.
(a) Before any work is commenced or recommended after a building permit has lapsed, a new permit shall be issued at the regular fee rate. In any event, all work shall be completed within 18 months from date of issuance of the permit. (b) A uniform dwelling code permit shall expire 24 months after issuance if the dwelling exterior has not been completed, per Wis. Admin. Code § SPS 320.09.
(Code 1973, § 30.06.030; Ord. No. 0003-24, pt. 8, 6-4-24)