Sec. 34-31. - Same—Concrete paving.
Before concrete paving is replaced, the edges of the cut shall be trimmed by the use of a concrete saw unless the use of a concrete saw in making the original cut makes such procedure unnecessary.
Except on pavement five years old and newer, all transverse joints shall be made perpendicular to the centerline of the street, and no less than four feet (1.2 m) of the remaining panel from any joint shall remain in place upon completion of street cut repair. The cost of the removal and replacement of any additional pavement to comply with this specification shall be included in the repair fee for the street cut. All pavement cuts shall be designed, where practicable, to minimize the number of additional joints in order to maintain integrity of the remaining street. Any concrete street cuts made by any person or agency within the first five years after the paving or repaving shall require the removal of full pavement panels, including any integral curbs, whenever the cut extends on such new pavement. The replacement of the full panels, inclusive of joint sealing, will be done at the full expense of the individual or agency making the street cut and shall be done in full compliance with those design and construction standards in effect at the time the street cut is made. Notwithstanding the preceding sentence, the costs to be charged for such full panel replacements on cuts made to repair or replace any utility service to an existing single-family or duplex residential structure shall be determined as though the area of the cut was made in conformity with the requirements of this section for a concrete street five or more years old. Any damage that is caused to adjacent panels by improper construction methods shall be replaced in accordance with the methods described above.
During the period between March 2 and November 30, the cut will be paved with concrete as thick as the surrounding concrete pavement, but in no case shall the repair be less than eight inches (200 mm) in thickness in residential streets and alleys and not less than nine inches (230 mm) in thickness in major streets.
During the period from December 1 to March 1, concrete street cuts will be backfilled and a temporary three-inch (80 mm) asphalt patch will be placed to the surface unless the availability of materials, work schedules and weather allows for permanent repair. After March 1 and before December 1, the temporary asphalt and backfill will be removed and replaced with concrete as thick as the surrounding pavement, but in no case shall the permanent repair be less than eight inches (200 mm) in thickness in residential streets and alleys and not less than nine inches (230 mm) in thickness in major streets.
(Code 1980, § 34-31; Ord. No. 34464, § 1, 2-3-98)