33.475.450 Corrections to Violations of the River Environmental Overlay Zone Regulations
A.
Purpose. The purpose of the correction regulations is to ensure the timely restoration of
natural resources and functional values that have been degraded due to a violation of the
River Environmental overlay zone.
These regulations establish a process to determine which review requirements will be
applied to remedy a violation that takes place in the River Environmental overlay zone. The
type of review required depends on the circumstances of the violation. Section
33.475.450.B details methods for correcting such violations and Title 3 of the City Code
details the enforcement penalties.
B.
Correction Options. Applicants must choose one of the following options to correct a river
environmental code violation.
1.
When these options may be used.
a.
If all of the following are met, the applicant may choose Option One, Option Two,
or Option Three:
(1) No more than 12 diameter inches of trees were removed;
(2) No ground disturbance occurred riverward of the top of bank of the
Willamette River, in the riparian buffer area, or within 30 feet of a wetland
or the top of bank of a stream or other water body. See Map 475-2 for top
of bank;
(3) The correction will remove all illegal development; and
(4) The correction will replant illegal clearing.
b.
If any of the following occurred, the applicant may not use Option One, but may
choose either Option Two or Option Three:
(1) More than 12 diameter inches of trees were removed;
(2) A Madrone, Garry Oak, or Pacific Yew larger than 3 inches was removed; or
(3) Disturbance occurred riverward of the top of bank of the Willamette River,
or within 30 feet of a wetland or the top of bank of a stream or other water
body. See Map 475-2 for top of bank. See Map 475-2 for top of bank.;
c.
If the applicant cannot meet Options One or Two, Option Three must be used.
d.
If the violation occurred within the riparian buffer area, the applicant must use
Option Three. See Map 475-6 for the riparian buffer area.
e.
If the violation also violates a condition of approval of a land use review, no trees
have been removed, and disturbance did not occur riverward of the top of bank
of the Willamette River or within 30 feet of a wetland or of the top of bank of a
stream or other water body, the applicant may choose Option One or the process
described in Section 33.730.140. The applicant may not choose Options Two
or Three.
f.
If the violation also violates a condition of approval of a land use review, trees
have been removed, and disturbance occurred riverward of the top of bank of
the Willamette River or within 30 feet of a wetland or the top of bank of a stream
or other water body, the applicant must use the process described in Section
33.730.140. The applicant may not choose one of the options in this section.
2.
Option One, Remove and Repair. This option results in removal of illegal development
and replanting and repair of any damage. All of the requirements of this paragraph
must be met. Adjustments and modifications to these requirements are prohibited.
a.
All items, materials, and fill placed in the area of violation are removed and no
new disturbance area is created;
b.
Any soil compaction resulting from the violation is tilled or otherwise broken up
to a depth of 6 inches prior to planting;
c.
Violation remediation planting. The area to be planted is the area disturbed by
the violation. All of the following must be met:
(1) The area disturbed by the violation activity must be replanted to meet the
standards of Table 475-3;
(2) For planting areas over 600 square feet, at least two different tree species
and sizes, three different shrub species, and four different groundcover
species must be used. All plants must be native;
(3) A second area, equal in size to the area disturbed by the violation activity,
must also be replanted to meet the standards of Table 475-3;
(4) Any Nuisance or Prohibited Plants listed on the Portland Plant List must be
removed from the planting area and within 10 feet of the planting area;
(5) Trees must be a minimum ½ inch in diameter, bareroot or live stake, unless
they are oak, madrone, or conifer, which may be three- to five-gallon size.
No more than 10 percent of the trees may be oak or madrone. Trees must
not be planted within a Scenic overlay zone. Trees may be clustered. Shrubs
must be a minimum of two-gallon size. All other species must be a minimum
of four-inch pots;
(6) The requirements of Section 33.248.090, Mitigation and Restoration
Planting, must be met; and
(7) For violations involving the removal of trees, two times the number of
diameter inches removed must be planted on the site, in addition to other
remediation vegetation planted. If any tree removed was a Garry Oak,
Madrone, or Pacific Yew, the replacement trees must be of the same
species. Planted trees must be a minimum ½ inch in diameter unless they
are oak, Madrone, or conifer, which may be three- to five-gallon size.
3.
Option Two, Retain and Mitigate. This option results in legalizing the illegal
development and mitigating for any damage. All of the requirements of this
subsection must be met. Adjustments and modifications to these standards are
prohibited.
a.
The applicable standards of paragraphs 33.475.440 must be met; and
b.
Violation remediation planting. The area to be planted is the area disturbed by
the violation. Where development is approved for the area disturbed by the
violation, an area of the same size elsewhere on the site must be planted. All of
the following must be met:
(1) The area disturbed by the violation activity must be replanted to meet the
standards of Table 475-3;
(2) For planting areas over 600 square feet, at least two different tree species
and sizes, three different shrub species, and four different groundcover
species are used. Plants must be native and selected from the Portland
Plant List.
(3) A second area, equal in size to the area disturbed by the violation activity,
must also be replanted to meet the standards of Table 475-3;
(4) Any Nuisance or Prohibited Plants listed on the Portland Plant List must be
removed from the planting area and within 10 feet of the planting area;
(5) Trees must be a minimum ½ inch in diameter, bareroot or live stake, unless
they are oak, madrone, or conifer, which may be three- to five-gallon size.
No more than 10 percent of the trees may be oak or madrone. Trees must
not be planted within a Scenic overlay zone. Trees may be clustered. Shrubs
must be a minimum of two-gallon size. All other species must be a minimum
of four-inch pots; and
(6) The requirements of Section 33.248.090, Mitigation and Restoration
Planting, must be met. When the planting area exceeds 1,000 square feet,
written proof that all specifications of 33.248.090 have been met must be
provided annually for three years after planting is complete. The
requirement for three years of written proof does not apply when the
planting area is less than 1,000 square feet. In this case, written proof that
all specifications of 33.248.090 have been met must be provided one year
after the planting is complete. The property owner must provide this
documentation to Portland Permitting & Development; and
c.
For violations involving the removal of trees, two times the number of diameter
inches removed must be planted on the site, in addition to other remediation
vegetation planted. If any tree removed was a Garry Oak, Madrone, or Pacific
Yew, the replacement trees must be of the same species. Planted trees must be a
minimum ½-inch in diameter unless they are oak, Madrone, or conifer, which
may be three- to five-gallon size.
4.
Option Three, River Review. This option requires River Review, using the approval
criteria and procedures below:
a.
Approval criteria. The applicable approval criteria of Subsection 33.865.120 must
be met.
b.
Review procedures. Reviews are processed as follows:
(1) Type III. A Type III review is required for any development, exterior
alteration, or exterior improvement within a wetland, stream channel,
drainageway, or water body.
(2) Type II. All other reviews to correct violations are processed through a Type
II procedure.
(3) All River Reviews must provide the information required in Section
33.865.040, Supplemental Application Requirements.
Clean Up of Contaminated Sites