§ 5 — Trench excavation and general underground construction requirements for major and minor projects
Code of the City of Mobile, Alabama (Supp. No. 67: codified through Ordinance No. 36-017-2026, adopted March 1, 2026) · Mobile City Code, App. B, § 5
Corpus is an independent public-information project, not the official City of Mobile website. Stable reference: corpuslaw.us/code/c55d20e2-27ce-4ff9-bf36-b134ed9b20c9
Section 5. - Trench excavation and general underground construction requirements for major and minor projects.
5.1. Excavation. A) Trench excavation methods shall be used to keep the width of the trench to a minimum. Extra wide excavation to accommodate equipment will not be permitted. Sheeting, bracing and other trench restraint system will be used to keep trench width to a minimum and to comply with OSHA regulations. B) Hazardous materials. The applicant will comply with all federal, state, and local laws, regarding hazardous material. For purposes of this section, hazardous material shall mean any material, substance or waste which, because of its quantity, concentration, or physical or chemical characteristics, is deemed to pose a present or potential hazard to human health, safety or to the environment. C) Utility construction. The construction of utilities will be in conformance with the plans which constitute a part of the approval permit. 1) Depth requirements for underground installation: a) Within roadway limits. The minimum clear depth for open cut installation, and jacking, boring, and pushing operations shall be thirty-six (36) inches, unless otherwise authorized or directed by the city engineer. b) Outside roadway limits and driveways. The minimum clear depth for open cut installation and jacking, boring, and pushing operations shall be thirty (30) inches, unless otherwise authorized or directed by the city engineer. D) Housekeeping and removal of excavated material the applicant shall keep the area surrounding the excavation clean (including trash, loose materials or other debris). 5.2. Backfill material. A) Backfill material for major projects will be select granular soil material approved by the geotechnical engineering company or the city engineer. Excavated material from the trench will not be used unless approved. Material excavated from utility poles, guy wire installation, replacing existing poles and routine pole inspections may be used for backfill. B) Backfill material for minor projects within the roadway shall be comprised of crushed stone material up to subgrade elevation, unless otherwise approved by the city engineer. Backfill material for other areas will be select granular soil material approved by a geotechnical engineering company or the city engineer. C) Installation of backfill material: 1) Backfilling of the excavated area shall follow closely behind the installation project. 2) The backfill material shall be compacted at near optimum moisture content, in layers not exceeding six (6) inches compacted thickness, to a density of not less than ninety-five (95) percent, unless otherwise approved by the geotechnical engineering company. Mechanical tampers shall be used unless another method of compaction is approved. Jetting will not be permitted. The backfill material shall be installed uniformly and brought up evenly in layers for the full length of the trench. D) Geotechnical testing and compaction for major and minor projects: 1) Major projects. A geotechnical engineering company will perform compaction tests at intervals of no more than 200 feet along the main trench line. Tests will be conducted at the installation of service lines within these limits where directed by the city engineer. The geotechnical engineering company will perform tests at as many levels of backfill installation, and at lateral locations to certify that compaction requirements have been achieved. Documented test reports will be prepared and submitted to the city engineer before any right-of-way restoration proceeds. 2) Minor projects. Compaction tests may be requested for minor projects at specific locations. In-house geotechnical engineers may be employed for performing compaction tests for minor projects. E) General public safety: Every effort will be taken by the contractor to protect the safety, health and welfare of the general public and to ensure compliance with the safety and traffic plans submitted with the permit applications. F) Steel plates may be required by the city engineer, in congested or heavily traveled areas, to cover open trenches. Temporary patching will be required for any trench excavation in the roadway prior to opening the area to traffic. G) For major projects a construction sign will be placed adjacent to the utility construction area where traffic flow is to be obstructed. The signs will be placed seventy-two (72) hours prior to construction, at least every five hundred (500) feet along the project. The name of the utility involved and phone numbers that may be contacted on a twenty-four-hour basis to be shown on the sign(s).
Ask a question about Mobile law
Corpus searches the Mobile sections it holds and shows the ones that match, with their citations. Free, no sign-in.