§ 18.205.150 — Permits – Time limits and conformance to terms

Fremont Municipal Code (Fremont Municipal Code current through Ordinance 02-2026 passed May 5, 2026 (Code Publishing Company, codepublishing.com, scraped 2026-11-18)) · Fremont Municipal Code § 18.205.150

Corpus is an independent public-information project, not the official City of Fremont website. Stable reference: corpuslaw.us/code/8633f57d-8f77-412b-9e06-80d46607c3c0

18.205.150 Permits – Time limits and conformance to terms.

In issuing any permit under this chapter, the city engineer ordinarily shall specify a time limit for completing the work. If no time limit is specified, the work shall be completed within 80 working days from the date of issuance of the permit. The permittee shall complete the work diligently in accordance with the permit and within the time limit herein specified. The city engineer shall inspect the progress of the work and see that it conforms at all times to the terms and conditions of the permit; he/she may refuse any building permits, any inspections and any approval required of his/her department in connection with any structure on the premises on which the excavation or fill is being or has been made, until the excavation conforms to the terms and conditions of the permit. Permittees unable to complete the work within the specified time shall present requests for an extension of time to the city engineer. Such requests shall be presented before permit expiration and shall set forth the reason for the request and extension. (Ord. 9-2014 § 29, 3-4-14.)

Ask a question about Fremont law

Corpus searches the Fremont sections it holds and shows the ones that match, with their citations. Free, no sign-in.