§ 2-275 — Coordination of excavations: Joint planning and construction
Code of the City of Thornton, Colorado (Supp. No. 65: codified through Ordinance No. 3773, adopted June 9, 2026) · Thornton City Code § 2-275
Corpus is an independent public-information project, not the official City of Thornton website. Stable reference: corpuslaw.us/code/700009a9-cc86-4201-971e-f8134189ffcb
Sec. 2-275. - Coordination of excavations: Joint planning and construction.
(a) Reduction of disruption and interference. Excavations in city ROW disrupt and interfere with the public use of city streets and damage the pavement and landscaping. The purpose of this section is to reduce this disruption, interference and damage by promoting better coordination among all entities making excavations in city ROW and the city. Better coordination will assist in minimizing the number of excavations being made wherever feasible, and will ensure the excavations in city ROW are, to the maximum extent possible, performed before, rather than after, the resurfacing of the streets by the city. (b) Excavation master plan. Any provider owning, operating or proposing to install facilities or structures in or occupying the ROW for providing water, sewer, gas, electric, cable, video or other utility, or informational or wireless communication services, shall meet annually with the director, at the city manager's or designee's request to discuss the provider's excavation master plan. At such meeting, to the extent not already in possession of the city, provider shall submit documentation, in a form required by the director including as built drawings, digital and software compatible GIS formats, showing all locations of the provider's existing facilities in the city ROW. Provider shall discuss with the director, its excavation master plan, and identify planned major excavation work in the city known at that time. The director may make his own record on a map, drawing or other documentation, of each provider's planned major excavation work in the city; provided, however, that no such document prepared by the director shall identify a particular entity, or the planned major excavation work of that particular entity. The provider shall meet with the director to discuss an initial excavation master plan no later than 60 days after submitting a construction permit application. Thereafter, each provider shall submit annually, on the first regular business day of January, a revised and updated excavation master plan. As used in this subsection, the term "planned major excavation work" refers to any future excavations planned by the provider when the excavation master plan or update is submitted that will affect any city ROW for more than five days at any given location, provided that the provider shall not be required to identify future major excavations planned to occur more than two years after the date that the provider's master plan or update is discussed. Between the annual meetings to discuss planned major excavation work, provider shall use its best efforts to inform the director of any substantial changes in the planned major excavation work discussed at the annual meeting. (c) Repaving plan. The director shall prepare a repaving plan showing the street resurfacing planned by the city. For purposes of this section, the repaving plan shall include a landscaping or other ROW improvement plan. The repaving plan shall be revised and updated on an annual basis after meeting to discuss the provider's and the city's master plans and updates. The director shall make the city's repaving plan available for public inspection. In addition, after determining the street resurfacing work that is proposed for each year, the director shall send a notice of the proposed work to all providers that have had an annual meeting with the director. (d) Coordination with repaving plan. Prior to applying for a construction permit, any permittee planning to excavate in the city's ROW shall review the city's repaving plan on file with the director and shall coordinate, to the extent practicable, with the utility and street work shown on such plans to minimize damage to, and avoid undue disruption and interference with the public use of such ROW. (e) Locating facilities. In performing locates of facilities in the ROW in preparation for construction, a provider shall compile all information obtained regarding its or any other facilities in the ROW related to a particular permit to the best of permittee's knowledge, and shall make that information available to the city in a written and verified format pursuant to written city policy. (f) Documentation of location of provider's facilities. Prior to undertaking any work in the ROW the city may notify all providers of a city project involving work to be performed in the ROW. Upon such notification, all users or their designated locate service providers shall, within seven days, locate their facilities in the ROW in which the work will be performed, and provide documentation in a format pursuant to written city policy of the provider's facilities in that ROW. If the provider fails to provide the locate information requested by the city, the city may obtain this information and charge the provider the actual costs for obtaining the information. (g) Joint excavation. (1) Public entity and special districts excavators. Whenever two or more public entity excavators propose major work in the same block [within a year], such [excavation] work shall be performed by one public entity excavator when practical. The participants to the excavation shall pay their pro rata share of the [excavation] work, or as otherwise agreed to by the affected public entities. For purposes of this subsection a, the public entity excavators shall be treated as a single permit applicant and shall submit one application. (2) Private entity excavators. Whenever two or more private entity excavators propose major work in the same block [within a year], such [excavation] work shall be performed by one private entity excavator if possible. For purposes of this subsection b, the private entity excavators will coordinate to determine who will perform that excavation work. Both entities will maintain separate and distinct permits for the purpose of their intended projects. If the city has an interest in installing conduit in the same location, the permittee shall install the city's conduit and charge the city the direct cost associated with such installation if and as provided in this Article. (3) Public entity excavator and private entity excavator. Whenever one or more public entity excavator(s) and private entity excavator(s) propose major work in the same block [within a year], the department shall place conditions on permits for such work in a manner that maximizes coordination and minimizes the total period of construction. If the city has an interest in installing conduit in the same location, the permittee shall install the city's conduit and charge the city the direct cost associated with such installation if and as provided in this Article.
(Ord. No. 2804, § 1, 10-28-03; Ord. No. 3655, § 6, 7-12-23)