Sec. 18-761. - Other considerations in design preparation.
(a) The predevelopment peak discharge rate shall be computed assuming that all land uses in the drainage area of the proposed facility are in a predevelopment state. The city considers predevelopment state to be woods in good condition for the purposes of determining runoff coefficients. (b) The developer shall incorporate use of natural topography and land cover such as wetlands, ponds, natural swales, and depressions as they exist prior to development to the degree that they can accommodate the additional flow of water. (c) Where storm drainage systems convey off-site stormwater through the property, computations reflecting the drainage area of land tributary to the site, and estimated runoff of the area served by such systems, shall be provided. In addition, a complete drainage study shall be submitted for the site. All storm drainage systems conveying off-site stormwater through property shall be public systems or private systems which shall be designed, constructed and maintained to at least the standards of a public storm drainage system as contained in the standards and specifications manual. The design and construction shall be certified by an authorized registered professional as meeting or exceeding the requirements of this division and the stormwater management technical standards and specifications.
(Ord. No. O-2009-92, § 2, 9-15-09; Ord. No. O-2010-91, § 35, 12-7-10)
Ask a question about Wilmington law
Corpus searches the Wilmington sections it holds and shows the ones that match, with their citations. Free, no sign-in.