Sec. 32-275. - Utility construction.

(a) Prior to any base material being placed, all underground work that is to be within the right-of-way or the right-of-way subgrade shall be completed and backfilled with stone, if necessary. This includes all drainage, sewerage, water, telephone, electrical, gas, cable television, and other utilities to the end that the completed roadway will not be disturbed for the installation of any utility main or service connection for any utility. ..... (b) Sanitary sewer shall be constructed in accordance with City of Chattanooga Design and Construction standards and Tennessee Department of Environmental Health requirements. ..... (c) Storm sewers shall be constructed in accordance with Best Management Practices (BMP) and City of Chattanooga design and construction standards. ..... (d) All underground utility conduits and piping shall be installed prior to proof rolling and placement of base material. Installation and backfill shall be observed by the Geotechnical Engineer. In the event all utility construction is not complete due to circumstances beyond the control of the developer and/or contractor, proof rolling and placement of base material may begin subject to completion of all underground conduits and piping beneath the road and two (2) feet beyond the edge the proposed base material. A City representative will be present for up to two (2) sanitary sewer tests. One (1) test will be performed prior to proof rolling and placement of base material. A second test will be performed after all utility construction within the right-of-way is complete. In the event all utility construction is complete prior to the first test, only one (1) test will be performed. ..... (e) Utility trenches shall be backfilled with either crushed rock, soil, or flowable fill according to the following requirements: ..... (1) Bedding: All utility trenches shall be bedded with a six (6) inch layer of either open-graded crushed rock or sand. Bedding shall be placed and compacted using a vibratory compactor. Where necessary, bell holes shall be cut into the bedding at pipe joints locations. ..... (2) Initial Fill: After the utility line has been placed, the utility trench shall be backfilled with open graded crushed rock or sand to at least twelve (12) inches over the top of the utility. The backfill shall be compacted using a vibratory compactor. ..... (3) Secondary Fill: From twelve (12) inches over the top of the utility to eighteen (18) inches below the subgrade elevation, the utility trench may be backfilled with either open-graded crushed rock, sand, or soil fill. Sand or soil backfill shall be placed in maximum one (1) foot layers and compacted. Sand or soil backfill shall be compacted to achieve at least ninety-five percent (95%) of the standard Proctor maximum dry density. Density tests shall be conducted for every one (1) foot layer of backfill at a frequency of one (1) test per one hundred (100) feet for utilities running along the longitudinal axis of the road, or one (1) test for utilities crossing the road. Open-graded crushed rock backfill does not require compaction in lifts, but must be consolidated using vibratory compaction equipment. The placement and consolidation must be observed by the geotechnical engineer. ..... (4) Final Backfill: The final eighteen (18) inches of the utility trench backfill shall be backfilled with dense-graded crushed rock. The backfill shall be compacted to achieve at least ninety-five percent (95%) of the standard Proctor maximum dry density. Density tests shall be conducted at a frequency of one (1) test per fifty (50) feet for utilities running along the longitudinal axis of the road, or two (2) tests for utilities crossing the road. ..... (5) Flowable fill: Flowable fill may be used as backfill for utility trenches. The material shall be designed to achieve a compressive strength of one hundred fifty (150) to five hundred (500) psi. The material shall meet the requirements of ACI 229R-99, Standard Specifications for Controlled Low Strength Cementitious Materials. Flowable fill may be used instead of the secondary fill and the final backfill. The material supplier shall submit a mix design verified by an independent testing laboratory within the past six (6) months. .....

(Ord. No. 11451, § 1, 9-2-03; Ord. No. 11882, § 1, 9-5-06; Ord. No. 14093, § 1, 3-12-24)