§ 27.5-7 — Permanent Stormwater Management—Planning, Design, and Operation and Maintenance
Code of Ordinances, City of Murfreesboro, Tennessee (Supp. No. 18: codified through Ordinance No. 26-O-38, enacted September 17, 2026) · Murfreesboro City Code § 27.5-7
Corpus is an independent public-information project, not the official City of Murfreesboro website. Stable reference: corpuslaw.us/code/a75370eb-c5d9-42c6-92a8-82c02e80605e
Section 27.5-7 - Permanent Stormwater Management—Planning, Design, and Operation and Maintenance.
(A) General Conditions. (1) Design and construction of land development projects shall provide measures for control of the quantity, rate, and quality of stormwater runoff, with the goals to maintain or restore the quality of streams, including the integrity of stream banks, and to prevent flooding detrimental to property; and to achieve compliance with Federal, State and local requirements. (2) Concept plans, stormwater management plans and designs must be presented for review in formats prescribed by the City and with information important for evaluating whether the plans comply with the City's standards. (3) Designs shall consider factors that will affect long-term maintenance of stormwater control measures, with the goal of practicable and reliable long term operation and maintenance, (4) Individual stormwater control measures (SCMs) must be confined to a single lot of record or common area. (5) The City shall promulgate guidance and standards for planning, design, and operation and maintenance of stormwater control measures (SCMs), such as the Stormwater Planning and Low Impact Design Guide and the Stormwater Controls Manual. These may be updated and expanded administratively from time to time. Updated copies are to be maintained available on the City's world wide web site. (6) Stormwater facilities that are designed, constructed, and maintained in accordance with the City's ordinances and design standards will be presumed to meet minimum performance standards. (7) If not specified in City's design manuals, methods for calculating stormwater quantities, flows and quality shall be in accordance with good engineering practices. (8) The City Council must approve any change to the stormwater design manuals which impose a new general requirement or which allows a new credit to the stormwater utility fee. Changes shall be based upon the recommendation of the Director of MWRD, based on improvements in engineering, science, results of monitoring, and on local maintenance experience. City Council approval of proprietary systems is not required. (B) Requirements for Control of Quantity and Discharge. (1) Applicability. (a) Any new development or redevelopment project, whether a site or subdivision or a common plan of development or sale, that will result in disturbance of one acre or involve the construction of 10,000 square feet of impervious surfaces; (b) Within watersheds of waters with unavailable parameters silt, habitat alteration, nutrients, or bacteria, any project that will involve the disturbance of 10,000 square feet; and (c) In the case of construction of a single-family home that is not a part of a larger common plan of development or sale, only if disturbance is one acre or more. Construction of 10,000 square feet of impervious surface refers to construction of, rather than addition of, 10,000 square feet of impervious surface. (2) Required controls. (a) Streambank protection. For new development, discharge must be controlled so that runoff from 75% of the one-year, 24-hour storm event is discharged over a 24-hour or greater period. For redevelopment, runoff from the added impervious area must be controlled so that runoff from 75% of the one-year, 24-hour storm event is discharged over a 24-hour or greater period; or equivalent control. (b) Peak discharge rates post-construction may not exceed the preconstruction peak discharge rates for two-year, ten-year, 25-, 50-, and 100-year storm events. (c) If the site has less than two acres (87,120 square feet) of impervious area, the City will consider on site low impact or green infrastructure design features included in the City's stormwater design manual as an alternative method of achieving control of peak discharge and extended detention. (3) The City may waive some or all required controls in paragraph (2) above if a hydrologic analysis from an engineer shows to the satisfaction of the City that such controls will result in an adverse impact (increased flooding, damage to structures or streambanks, etc.) downstream. (C) Requirements for Control of Quality. (1) Applicability. (a) Any new development or redevelopment project, whether a site or subdivision or a common plan of development or sale, that will result in disturbance of one acre or involve the construction of 10,000 square feet of impervious surfaces; (b) Within watersheds of waters with unavailable parameters silt, habitat alteration, nutrients, or bacteria, any project that will involve the disturbance of 10,000 square feet; and (c) In the case of construction of a single-family home that is not a part of a larger common plan of development or sale, only if disturbance is one acre or more. Construction of 10,000 square feet of impervious surface refers to construction of, rather than addition of, 10,000 square feet of impervious surface. (2) General. (a) Requirements of this section are intended to fulfill standards set forth in Tennessee Rule 0400-40-10-.04 and in the Tennessee small MS4 general permit (NPDES permit TNS000000). (b) Designs of stormwater control measures shall adhere to standards in the City's design manual; except that City staff may allow and approve other SCMs, based on evidence of their treatment efficiency, that can be constructed practicably and can be reliably operated and maintained. (c) The City's design manual should set forth treatment efficiencies of SCMs that correspond to treatment efficiencies set forth in the MS4 permit. (3) Overall treatment standard - 80% TSS removal from WQTV. (a) The water quality treatment design storm is a one-year, 24-hour storm event, as defined by the Precipitation-Frequency Atlas of the United States, Atlas 14 of the National Oceanic and Atmospheric Administration (NOAA). (b) The water quality treatment volume (WQTV) is a portion of the runoff generated from impervious surfaces at the new development or redevelopment project from the design storm. (c) SCMs must be designed to achieve an overall treatment efficiency of 80% total suspended solids removal from the WQTV. (d) Quantity of the WQTV depends on the type of treatment provided, as shown in table below. (4) Treatment types and volumes - table. Water Quality Treatment Volume and the Corresponding SCM Treatment Type for the One-Year, 24-hour Design Storm SCM Treatment Types | WQTV | Notes Infiltration, evaporation, transpiration, and/or reuse | runoff generated from the first one inch of the design storm | Examples include bioretention, stormwater wetlands, infiltration systems. Biologically active filtration, with an underdrain | runoff generated from the first 1.25 inches of the design storm | To achieve biologically active filtration, SCMs must provide minimum of 12 inches of internal water storage. Sand or gravel filtration, settling ponds, extended detention ponds, and wet ponds | runoff generated from the first 75% of the design storm | Examples include, but are not limited to, sand filters, permeable pavers, and underground gravel detention systems. Ponds must provide forebays comprising a minimum of 10% of the total design volume. Existing regional detention ponds are not subject to the forebay requirement. Hydrodynamic separation, baffle box settling, other flow-through manufactured treatment devices (MTDs), and treatment trains using MTDs | maximum runoff generated from the entire design storm | See the City's SCM manual for treatment efficiencies of MTDs. (5) Treatment train calculations. (a) Treatment trains using MTDs must provide an overall treatment efficiency of at least 80% TSS reduction using the following formula: R = A + B - (A X B)/100, Where: R = total TSS percent removal from application of both SCMs, A = the TSS % removal rate of the first SCM in train, and B = the TSS % removal rate of the second SCM. (b) Treatment trains using infiltration, evaporation, transpiration, reuse, or biologically active filtration followed by sand or gravel filtration, settling ponds, extended detention ponds or wet ponds may subtract the treated WQTV of the upstream SCMs from the WQTV of the downstream SCMs. (6) Credits/reductions of WQTV. The City may establish procedures to recognize reductions of the WQTV for a development or redevelopment project up to 20% for any one of the following conditions, and up to a total of 50% for a combination of these conditions: (a) Redevelopment projects (including, but not limited to, brownfield redevelopment); (b) Vertical density (floor to area ratio of at least 2, or at least 18 units per acre); and (c) Other incentives the City has established or recognized, which have been approved in writing by the Tennessee Department of Environment and Conservation, Division of Water Resources and which are incorporated into the City's stormwater management program. The procedures for applying for the credit and for approval will be as described by regulation or promulgated on the City's world wide web pages. (D) Special situations/conditions. (1) Stormwater discharges to critical areas with sensitive resources (e.g., recharge areas, water supply reservoirs) or to priority watersheds may be subject to additional performance criteria or may need application or restriction of certain stormwater management practices. (2) Stormwater discharges from hot spots may require the application of specific SCMs and pollution prevention practices. (3) The City may impose construction and permanent buffers up to 25 feet, where clearing and grading is prohibited, on hydrologically significant waters and karst windows, and practicable protections in addition to those that apply to wet weather conveyances. (4) The City may impose additional controls on volume of discharge and rate of discharge to development within drainage-sensitive watersheds. (E) Stormwater concept plan requirements. The stormwater concept plan shall contain major stormwater elements with sufficient information to allow the City to evaluate the general characteristics and overall stormwater management efforts expected with proposed development of the project Site. To accomplish this goal the concept plan shall include the following: (1) GIS/mapping contours; (2) Storm drainage flow arrows; (3) Potential location of major stormwater structures; (4) Potential location of detention/retention areas; (5) Location of known sinkholes, closed depressions and wetlands; (6) Location of major erosion/sediment control basins, etc.; (7) Ultimate drainage outfall(s); (8) Location of all streams, with a designation of those which are FEMA regulated, and designated floodways; (9) Potential layout of underground utilities, particularly where those are likely to cross streams; and (10) Potential location of water quality protection areas. The stormwater concept plan information shall be submitted with the master plan for the development. The information may be contained in the master plan or submitted separately. (F) Stormwater management plan requirements. The stormwater management plan shall include sufficient information to allow the City to evaluate the environmental characteristics of the project site, the potential impacts of all proposed development of the site, both present and future, on water resources, and the effectiveness and acceptability of the measures proposed for managing stormwater generated at the project site. The stormwater management plan shall be submitted for review and approval as part of the site plan and/or construction plans. To accomplish this goal the stormwater management plan shall include the following: (1) Topographic base map. A topographic base map of an appropriate scale of the site which extends a minimum of 100 feet beyond the limits of the proposed development and indicates: (a) Existing surface water drainage including streams, ponds, culverts, ditches, sinkholes, wetlands; and the type, size, elevation, etc., of nearest upstream and downstream drainage structures; (b) Current land use including all existing structures, locations of utilities, roads, and easements; (c) All other existing significant natural and artificial features; (d) Proposed surface area tabulation showing the percentage of the different surfacing types (i.e., lawn, asphalt, concrete, etc.); drainage patterns; locations of utilities, roads and easements; the limits of clearing and land disturbance activity; and, (e) Proposed stormwater control measures. (2) Calculations. Hydrologic and hydraulic design calculations for the predevelopment and post-development conditions for the two-, five-, ten-, 25-, 50- and 100-year storms must be submitted. These calculations must show that the proposed stormwater management measures are capable of controlling runoff from the site in compliance with this chapter and the guidelines of the stormwater design and control manuals. Such calculations shall include: (a) A description of the design storm frequency, duration, and intensity where applicable; (b) Time of concentration; (c) Soil curve numbers or runoff coefficients including assumed soil moisture conditions; (d) Peak runoff rates and total runoff volumes for each watershed area; under existing conditions and on built-out conditions; (e) Infiltration rates, where applicable; (f) Culvert, stormwater sewer, ditch and/or other stormwater conveyance capacities; (g) Flow velocities; (h) Estimates on the increase in rate and volume of runoff for the design storms; (i) Description of, or reference to, any model used to estimate the quality of stormwater runoff that will be discharged from the developed site(s); (j) An assessment of the potential for trench excavations (as for utilities) to capture flow of natural stream(s); (k) Documentation of sources for all computation methods and field test results; and, (l) For stormwater control measures or stormwater facilities not described by the City's design and controls manuals, include design parameters and specifications. (3) Soils information. If a stormwater management control measure depends on the hydrologic properties of soils (e.g., infiltration basins), then a soils report shall be submitted. The soils report shall be based on on-site boring logs or soil pit profiles and soil survey reports. The number and location of required soil borings or soil pits shall be determined based on what is needed to determine the suitability and distribution of soil types present at the location of the control measure. (4) Stormwater control measures. Description of SCMs sufficient to explain how the system achieves standards for discharge quality and quantity. (5) Sinkholes and sinkhole treatments. The City may require a geotechnical report on sinkhole(s) and details of sinkhole treatments. For example, sinkholes proposed to be closed, to receive significantly more runoff than exists, or that are within contours of detention ponds. (G) Operation, Maintenance and Repair of Stormwater Management Facilities. (1) Maintenance Plan. (a) The design and planning of all stormwater management facilities shall include detailed maintenance and repair procedures to ensure their continued performance. These plans will identify the parts or components of a stormwater management facility that need to be maintained and the equipment and skills or training necessary. Provisions for the periodic review and evaluation of the effectiveness of the maintenance program and the need for revisions or additional maintenance procedures shall be included in the plan. (b) The plan may, at City's option, require the owner to file periodic inspection reports or certifications that the required maintenance and repairs have been performed and that the facility is functioning as initially designed and installed. A location map of all stormwater management BMP's with a permanent elevation benchmark shall be submitted to assist in the periodic inspection of the facility. (2) Maintenance Easements. The applicant must ensure access to the site for the purpose of inspection and repair by securing all the maintenance easements needed. These easements must be binding on the current property owner and all subsequent owners of the property and must be properly recorded in the office of the Register of Deeds. (3) Maintenance Agreement. (a) The maintenance responsibilities for permanent stormwater runoff control facilities shall be determined based upon the type of ownership of the property which is controlled by the facilities. (b) Where the permanent stormwater runoff control facilities are designed to manage runoff from property in a single entity ownership as defined below, the maintenance responsibility for the stormwater control facilities shall be with the single entity owner. (c) The stated responsibilities of the entity in terms of owning and maintaining the facilities shall be submitted with the stormwater management plan for determination of their adequacy. Approval of the stormwater management plan shall be conditioned upon the approval of these terms. These terms shall be in writing, shall be in recordable form, and in addition to any other terms deemed necessary by the City shall contain a provision permitting inspection at any reasonable time by the City. (d) A single entity shall be defined as an individual, an association, public or private corporation, partnership firm, trust, estate or any other legal entity allowed to own real estate. (e) Unless made specifically clear in the preliminary stages of the stormwater management plan review, it will be assumed that all stormwater detention, retention, treatment or storage facilities and/or devices shall be operated and maintained by a single entity as defined above. (f) Where the City has explicitly and in writing accepted an offer of dedication of the permanent stormwater management facilities, the City shall be responsible for maintenance. (4) Operation, Maintenance and Repair. Notwithstanding the condition of the items described above in this section - the maintenance plan, maintenance easements and maintenance easement - the owner of stormwater management facilities, including stormwater quality control measures, must inspect condition of the facilities and maintain them in good working order so that they perform substantially as designed, to capture pollutants and regulate discharge of stormwater.
(Ord. No. 24-O-24, § 1, 8-22-24)
Ask a question about Murfreesboro law
Corpus searches the Murfreesboro sections it holds and shows the ones that match, with their citations. Free, no sign-in.