SECTION 8.02 — WATER & WASTEWATER REQUIREMENTS

Code of Ordinances, City of Frisco, Texas (Frisco City Code, Home Rule Charter and Code Appendix current through Ordinance 2026-10-64 adopted October 20, 2026 (eCode360 publication FR6313, scraped 2026-11-18)) · Frisco City Code § SECTION 8.02

Corpus is an independent public-information project, not the official City of Frisco website. Stable reference: corpuslaw.us/code/57d8123e-c536-4734-ac86-b7c84736f537

SECTION 8.02: WATER & WASTEWATER REQUIREMENTS.

(a) Water and Wastewater Basic Policy. (1) Construction Requirements. a. All public water and wastewater mains shall be located in the frontage of the property along streets, or in easements adjacent to the development in order to provide service to adjacent property. b. Public water and/or wastewater mains shall not be located within a private street, drive or access easement unless a public utility easement is provided. c. The minimum easement width for water or wastewater mains shall be fifteen (15) feet, or as determined by the Director of Engineering Services. Where it is necessary for water and wastewater facilities to be located within the same easement, the easement shall be a minimum of twenty (20) feet in width, or as determined by the Director of Engineering Services. d. No portion of a structure (including, but not limited to, walls, foundations, porches/patios and porch/patio covers, canopies, roof extensions/overhangs, chimneys, fire flues, etc.) shall encroach over or into any easement, except that wall-attached window awnings, "bay" style windows, and roof eaves shall be allowed to encroach into an easement a maximum of twenty-four inches (24") upon approval of the Director of Engineering Services. e. A water or wastewater easement between two lots must fall entirely on a single lot. f. Easements shall be dedicated for exclusive use for water and wastewater facilities and shall be shown on the Final Plat for the specific purpose intended. When it is necessary for additional utilities to be placed within an easement, additional width shall be provided and the easement shall be labeled for its intended purpose on the Final Plat. g. When it is necessary to relocate or replace an existing water or sewer facility to accommodate a proposed subdivision, the developer is responsible for all costs associated with the relocation, except as agreed to by City Council for oversize participation. (2) Construction Plans. Plans for construction of all water and wastewater facilities required by these regulations shall be prepared in accordance with the requirements and specifications contained in the Engineering Standards, the regulations of the Texas Commission on Environmental Quality (TCEQ), National Sanitation Foundations (NSF), Texas Department of Insurance, Insurance Services Office, and the City's current adopted Fire Code, which are incorporated by reference and made a part hereof. Plans for the improvements must be prepared by a licensed engineer and accepted by the Director of Engineering Services. (3) Acquisition of Easements. The developer shall be responsible for the acquisition of all required off-site easements. If the developer is unable to acquire the necessary off-site easement, the City shall be provided with easement or right-of way survey documents and exhibits, documentation, including evidence of a reasonable offer made to the affected property owner. Upon receiving a written request for assistance, the City may, at its option, acquire these easements either through negotiations or through condemnation in appropriate situations. The developer shall reimburse the City for the costs of acquiring the necessary easements including but not limited to attorney fees, expert fees and title searches. (b) Preliminary Utility Plan. (1) Concurrent with the submission of a preliminary plat, replat or minor plat, the developer shall submit a map or plan showing the location and size of water and wastewater mains, which will be required to provide adequate service and fire protection to the lots specified in the proposed plat. Plans and specifications for fire hydrant systems shall be submitted to the Fire Marshal for review prior to construction. (2) Plan Document. The plan shall be prepared as noted in the City's Development Application Handbook. (3) Coordination with other Utility Providers. a. Preliminary Plat. When the subdivision is located in an area served by a utility provider other than the City, the developer must provide a water system analysis. b. Minor Plat, Replat. When a subdivision is located in an area served by a utility provider other than the City, the developer must provided a letter from the utility provider stating that facilities existing in the area to provide adequate domestic service and fire protection. If the City has reason to believe that there may be water supply or pressure concerns, a water system analysis may be required. c. Final Plat. The final plat will not be filed with the County until a letter has been provided from the utility provider stating that they have accepted the plans for construction. (c) Miscellaneous Requirements. (1) No building shall be constructed over an existing wastewater, lateral, water main or storm drain unless approved in writing by the Director of Engineering Services and approved by the City Council. (2) Ownership and maintenance of water and wastewater mains and service connections shall be regulated as follows. a. The title to all wastewater lines constructed, including wastewater service connections located in a right-of-way or dedicated easement, shall be vested in the City or the applicable utility provider. b. The developer, or single customer, shall be responsible for all maintenance of the wastewater service connection, unless replacement of the service is required under the roadway or pavement. When replacement is determined to be necessary by the Director of Engineering Services, the City shall assume the responsibility for replacement of that portion under the pavement. c. The title to all water mains and water meters constructed, and installed, including the title to service connections, shall be vested in the City or the applicable utility provider. (3) The City makes no guarantee that water supply or wastewater capacity will be available at any particular time or place. (4) Water or wastewater service lines shall not cross any adjacent lot. The public main shall be extended so as not to require the service to extend across another lot. Water and wastewater service lines shall be maintained by the property owner. (5) Public water and wastewater mains adjacent to federal, state, or county roadways shall be constructed outside the right-of-way in a separate easement unless otherwise agreed by those agencies and the City. (d) Water. (1) Design & Construction. a. Installation of Water Facilities. Where water is to be provided through the City system, the property owner shall install adequate water facilities, including fire hydrants, in accordance with the City's Engineering Standards, the adopted Fire Code, the current Rules and Regulations for Public Water Systems of the Texas Commission of Environmental Quality (TCEQ), and the firefighting standards of the Texas Board of Insurance. If any such requirements conflict, the most stringent requirement shall apply. b. Facilities for Health and Safety Emergencies; Alternative Water Sources. All water facilities connected to the City's water system shall be capable of providing water for health and emergency purposes, including fire protection and suppression. Water supply facilities shall be in accordance with the Engineering Standards. The design and construction of water system improvements and alternative water sources shall also comply with the following standards: i. Design and construction of a water source on the site shall be in accordance with applicable regulations of the Texas Commission of Environmental Quality (TCEQ). ii. Design and construction of water service from the City shall be in accordance with the standards in the City's Engineering Standards. iii. Design and construction of a fire protection and suppression system shall be in accordance with the standards in the Engineering Standards, and in accordance with the City's Fire Department and adopted Fire Code. (2) Location. a. Shown on Construction Plans. The location and design of all fire hydrants, all water supply improvements and the boundary lines of special districts, private systems and certified water service areas, indicating all improvements proposed to be served, shall be shown on the Construction Plans. b. Extension of Lines. Extension of water lines shall be made along the entire frontage of the development adjacent to a street. If the subdivision is not adjacent to a street, the extension of water lines shall be accomplished in such a manner as to allow convenient future connections to said lines by new subdivisions. c. Waiver for Requirement. If new subdivisions will never be constructed beyond a developing subdivision due to physical constraints, the Director of Engineering Services may approve a Minor Waiver for this requirement in accordance with Section 9.01 of this Ordinance prior to action on the Construction Plans or prior to action on any Plat. (3) Cost of Installation. The cost of installing all water supply improvements to be made by the developer, including off-site improvements, shall be included in the performance guarantees and Improvement Agreement, if applicable (refer to Section 5.04). (4) Cost of Extension. Where the City's water distribution system is not planned to be extended in time to serve a proposed new development, all necessary water facilities to serve such development shall be provided by and at the expense of the developer. If oversizing of a water facility is deemed necessary by the Director of Engineering Services for future developments, then the City may participate in such oversizing costs as part of a Development Agreement. (5) Alternative Water Systems. Developments may be approved with alternative water facilities according to the following criteria: a. Water well operation and quality shall meet the minimum requirements of the Texas Commission on Environmental Quality, Collin and Denton Counties, City health ordinances, and all other regulatory agencies, if applicable. b. Water wells may not be used for commercial sale of water. c. The cost to tie onto the public water system must exceed the certified initial capital cost of a well by twenty-five percent (25%). All costs and engineering designs shall be submitted by a licensed professional engineer. All costs and engineering designs shall be subject to approval by the Director of Engineering Services. If a residence is located within one thousand feet (1,000') of a domestic water supply, that residence must hook up to that service. (6) Individual Wells. a. Within the City's Extraterritorial Jurisdiction (ETJ). Individual wells within the City's ETJ shall be subject to approval by the applicable County health official, and this approval shall be documented by the health official's signature on the water system statement on the Preliminary and Final Plat. The property owner must submit with the Preliminary and Final Plat applications a certificate from a professional engineer who is registered, or a geoscientist who is licensed, to practice in the State of Texas verifying the adequacy of the proposed well water supply and potability prior to Preliminary Plat and Construction Plans approvals. b. Compliance with Other Regulations. Installation, operations and maintenance of individual wells shall comply with City standards, regulations of the Texas Commission on Environmental Quality (TCEQ), and any other applicable County or State rules and regulations. In the event of conflict among these regulations, whichever is the most stringent shall apply. (e) Wastewater. (1) Extension of and Connection to the City's Wastewater Collection System. Extension of, and connection to, the City's sanitary sewer system shall be required for all new developments within the City's limits. Extension of, and connection to, the municipal sewer system shall also be required for new developments within the City's ETJ for any proposed development, lot, tract or parcel that is less than one (1) acre in size. The City is not in any way obligated to allow extension of municipal sewers outside the City's limits. The required extension of, and connection to, the municipal sewer system may be waived as a Minor Waiver, in accordance with Section 9.01, by the Director of Engineering Services if the Director of Engineering Services determines that such extension would require unreasonable expenditures and that an on-site wastewater disposal system (see subsection (e)(5)) will function properly and safely. (2) Design & Construction. It is the policy of the City to require all wastewater collection lines to have gravity flow. The use of lift stations and force mains is prohibited unless a gravity design is impractical, as determined by the Director of Engineering Services. The location, design and sizing of all wastewater improvements shall be shown on the Construction Plans and are subject to approval by the Director of Engineering Services. (3) Cost of Installation. The cost of installing all wastewater improvements to be made by the developer, including off-site improvements, shall be included in the performance guarantees and Improvement Agreement, if applicable (refer to Section 5.04). (4) Extension. a. Cost. Where the City's wastewater system is not planned to be extended in time to serve a proposed new development, all necessary wastewater facilities to serve such development shall be provided by and at the expense of the developer. If oversizing of a wastewater facility is deemed necessary by the Director of Engineering Services for future developments, then the City may participate in such oversizing costs as part of a Development Agreement. b. Future Extensions. Pipe stub-outs shall be located in manholes to facilitate the future extension of wastewater lines. The Director of Engineering Services will determine the location and size of the stub-outs. (5) On-Site Wastewater Disposal Systems. a. In cases where the Director of Engineering Services determines that extension of, and connection to, the City's sewer system is impractical or not feasible, and where the Director of Engineering Services approves the use of an on-site wastewater disposal system(s), such on-site system(s) shall provide adequate sewage disposal for all lots, tracts, parcels and structures in the development that cannot be connected to the City's sewer system. b. All on-site wastewater disposal systems shall be designed, permitted, constructed, operated and maintained in compliance with all applicable local, County and State regulations, and a permit for such system shall be acquired prior to Preliminary Plat and Construction Plans approvals. c. On-site wastewater disposal facilities requiring soil absorption systems may be prohibited where such systems will not function properly due to high ground water, flooding, unsuitable soil characteristics, or other topographical or environmental issue. d. Each lot, tract, parcel and structure that utilizes an on-site wastewater disposal system shall have a minimum land area of at least one (1) acre. e. No portion of any on-site wastewater disposal system shall be constructed within a minimum one hundred and fifty foot (150') radius around any water well either on- site or on other properties. f. All properties and structures that are allowed to utilize an on-site wastewater system shall, at the owner's expense or using funds escrowed by the developer (see below), tie onto the City's sanitary sewer system when such municipal system is extended to the service area as determined by the Director of Engineering Services. Such connection to the City's system shall occur within one (1) year after the system is made available to the area. The developer of any new subdivision shall provide escrow funds, the amount of which shall be subject to approval by the Director of Engineering Services, for this future connection to the City's sanitary sewer system. g. In order to protect the public health, safety and welfare, an existing on-site wastewater disposal system shall be upgraded, or reconstructed if necessary, to comply with the City's standards by the owner, at the owner's expense, if the operation of the facility does not comply with government regulations or if it causes objectionable odors, unsanitary conditions, pollution, etc.

( Ordinance 19-08-70 adopted 8/20/2019 )