Sec. 23-20. - Base material.
Base material shall be constructed as designated on the construction permit and as required pursuant to the most recently adopted guiding documents. A user shall notify the city engineer not less than two hours prior to the placement of base material. Failure to do so may result in the suspension of construction and the removal of any base material placed without prior approval.
(Ord. No. 2001-41, § 1, 10-2-01; Ord. No. 2013-069, § 1, 2-5-13; Ord. No. 2025-477, § 9, 6-17-25)