33.430.250 Approval Criteria
An environmental review application will be approved if the review body finds that the applicant has
shown that all of the applicable approval criteria are met. When environmental review is required
because a proposal does not meet one or more of the development standards of Section 33.430.140
through .190, then the approval criteria will only be applied to the aspect of the proposal that does
not meet the development standard or standards.
A.
Public safety facilities, rights-of-way, driveways, walkways, outfalls, utilities, pump
stations, flood control structures, septic systems, land divisions, Property Line
Adjustments, Replats, Planned Developments, and Planned Unit Developments. Within
the resource areas of environmental zones, the applicant's impact evaluation must
demonstrate that all of the general criteria in Paragraph A.1 and the applicable specific
criteria of Paragraphs A.2, 3, or 4, below, have been met:
1.
General criteria for public safety facilities, rights-of-way, driveways, walkways,
outfalls, utilities, pump stations, flood control structures, septic systems, land
divisions, Property Line Adjustments, replats, Planned Developments, and Planned
Unit Developments:
a.
Proposed development locations, designs, and construction methods have the
least significant detrimental impact to identified resources and functional values
of other practicable and significantly different alternatives including alternatives
outside the resource area of the environmental zone;
b.
There will be no significant detrimental impact on resources and functional
values in areas designated to be left undisturbed;
c.
The mitigation plan demonstrates that all significant detrimental impacts on
resources and functional values will be compensated for;
d.
Mitigation will occur within the same watershed as the proposed use or
development and within the Portland city limits except when the purpose of the
mitigation could be better provided elsewhere; and
e.
The applicant owns the mitigation site; possesses a legal instrument that is
approved by the City (such as an easement or deed restriction) sufficient to carry
out and ensure the success of the mitigation program; or can demonstrate legal
authority to acquire property through eminent domain.
2.
Public safety facilities. The public benefits of the proposal outweigh all significant
detrimental impacts;
3.
Rights-of-way, driveways, walkways, outfalls, utilities, and septic systems;
a.
The location, design, and construction method of any outfall or utility proposed
within the resource area of an environmental protection zone has the least
significant detrimental impact to the identified resources and functional values of
other practicable alternatives including alternatives outside the resource area of
the environmental protection zone;
b.
There will be no significant detrimental impact on water bodies for the
migration, rearing, feeding, or spawning of fish; and
c.
Water bodies are crossed only when there are no practicable alternatives with
fewer significant detrimental impacts.
4.
Land divisions, Property Line Adjustments, replats, Planned Developments, and
Planned Unit Developments:
a.
Proposed uses and development must be outside the resource area of the
Environmental Protection zone except as provided under Paragraph A.3 above.
Other resource areas of Environmental Protection zones must be in
environmental resource tracts;
b.
There are no practicable arrangements for the proposed lots, tracts, roads, or
parcels within the same site, that would allow for the provision of significantly
more of the building sites, vehicular access, utility service areas, and other
development on lands outside resource areas of a conservation zone; and
c.
Development, including building sites, vehicular access and utilities, within the
resource area of a conservation zone must have the least amount of detrimental
impact on identified resources and functional values as is practicable.
Significantly different but practicable development alternatives, including
alternative housing types or a reduction in the number of proposed or required
units or lots, may be required if the alternative will have less impact on the
identified resources and functional values than the proposed development.
B.
Resource enhancement projects. In resource areas of environmental zones, resource
enhancement projects will be approved if the applicant's impact evaluation demonstrates
that all of the following are met:
1.
There will be no loss of total resource area;
2.
There will be no significant detrimental impact on any resources and functional
values; and
3.
There will be a significant improvement of at least one functional value.
C.
Public recreational facilities. In resource areas of environmental zones, public trails, rest
points, public viewing areas, and interpretative facilities will be approved if the applicant's
impact evaluation demonstrates that all of the following are met:
1.
Proposed development locations, designs, and construction methods are less
detrimental to identified resources and functional values than other practicable and
significantly different alternatives;
2.
The public benefits of the proposal outweigh all significant detrimental impacts;
3.
Areas disturbed during construction, that do not contain permanent development, will
be restored with native vegetation that is similar to the vegetation existing on the site
and found on the Portland Plant List; and
4.
There will be no significant detrimental impact on resources and functional values in
areas designated to be left undisturbed.
D.
Modification of zone boundaries. Modifications of environmental zone boundaries that
reflect permitted changes in the location or quality of resource areas will be approved upon
finding that the applicant's statement demonstrates that either Paragraph D.1 or D.2 below
are met. For the minor modification of environmental zone boundaries based on a more
detailed site specific environmental study, the applicant's impact evaluation must
demonstrate that Paragraph D.3 below is met:
1.
Successful mitigation. An approved mitigation plan has been successful and a new,
restored, or enhanced resource exists which, depending on its degree of significance,
should be included in either the resource area of an Environmental Conservation zone
or the resource area of an Environmental Protection zone; or
2.
Approved loss of resource area. All of the following must be met:
a.
All approved development in a resource area has been completed;
b.
All mitigation required of this development has been successful; and
c.
The identified resources and functional values at the developed site no longer
exist, or have been subject to a significant detrimental impact.
3.
The proposed environmental zone line location accurately reflects the location of the
significant or highly significant resources and functional values on the site, plus 25 feet
of transition area. The significant or highly significant resources are identified in the
Resource Site Inventory of the relevant Environmental Study Report,
see 33.430.020.
E.
Other development in the Environmental Conservation zone or within the Transition
Area only. In Environmental Conservation zones or for development within the Transition
Area only, the applicant's impact evaluation must demonstrate that all of the following
are met:
1.
Proposed development minimizes the loss of resources and functional values,
consistent with allowing those uses generally permitted or allowed in the base zone
without a land use review;
2.
Proposed development locations, designs, and construction methods are less
detrimental to identified resources and functional values than other practicable and
significantly different alternatives;
3.
There will be no significant detrimental impact on resources and functional values in
areas designated to be left undisturbed;
4.
The mitigation plan demonstrates that all significant detrimental impacts on resources
and functional values will be compensated for;
5.
Mitigation will occur within the same watershed as the proposed use or development
and within the Portland city limits except when the purpose of the mitigation could be
better provided elsewhere; and
6.
The applicant owns the mitigation site; possesses a legal instrument that is approved
by the City (such as an easement or deed restriction) sufficient to carry out and ensure
the success of the mitigation program; or can demonstrate legal authority to acquire
property through eminent domain.
F.
Other development in the Environmental Protection zone. In Environmental Protection
zones the applicant's impact evaluation must demonstrate that all of the following
are met:
1.
All sites within the Portland city limits, in which the proposed use or development is
possible, are also in the resource areas of Environmental Protection zones;
2.
Of these sites, development on the proposed site would have the least significant
detrimental environmental impact;
3.
There is a public need for the proposed use or development;
4.
The public benefits of the proposed use or development outweigh all significant
detrimental impacts;
5.
There will be no significant detrimental impact on resources and functional values in
areas designated to be left undisturbed;
6.
The mitigation plan demonstrates that all significant detrimental impacts on resources
and functional values will be compensated for;
7.
Mitigation will occur within the same watershed as the proposed use or development
and within the Portland city limits except when the purpose of the mitigation could be
better provided elsewhere; and
8.
The applicant owns the mitigation site; possesses a legal instrument that is approved
by the City (such as an easement or deed restriction) sufficient to carry out and ensure
the success of the mitigation program; or can demonstrate legal authority to acquire
property through eminent domain.
G.
Corrections to violations. For corrections to violations of this Chapter the application must
meet all applicable approval criteria stated in subsections A through F above, and
paragraphs 1, 2.b and 2.c, below. If these criteria cannot be met, then the applicant’s
remediation plan must demonstrate that all of the following are met:
1.
The remediation is done in the same area as the violation; and
2.
The remediation plan demonstrates that after its implementation there will be:
a.
No permanent loss of any type of resource or functional value;
b.
A significant improvement of a least one functional value; and
c.
There will be minimal loss of resources and functional values during remediation
until the full remediation program is established.