12.7.3. - Permit Procedures and Requirements
A. Permit Application Requirements. 1. No owner or developer can perform any development activities on a site where an Area of Special Flood Hazard or Area of Future-conditions Flood Hazard is located without first meeting the requirements of this ordinance prior to commencing the proposed activity. 2. Unless specifically excluded by this Section, any landowner or developer desiring a permit for a development activity must submit to the Floodplain Ordinance Administrator a permit application on a form provided by the Floodplain Ordinance Administrator for that purpose. 3. No permit will be approved for any development activities that do not meet the requirements, restrictions and criteria of this ordinance. B. Floodplain Management Plan Requirements. An application for a development project within any Area of Special Flood Hazard or Area of Future-conditions Flood Hazard located on the site shall include a floodplain management/flood damage prevention plan. This plan must include the following items: 1. Site plan drawn to scale, which includes but is not limited to: a. Existing and proposed elevations of the area in question and the nature, location and dimensions of existing and proposed structures, earthen fill placement, amount and/or location of excavation material, and storage of materials or equipment; b. For all proposed structures, spot ground elevations at building corners and 20-foot or smaller intervals along the foundation footprint, or 1-foot contour elevations throughout the building site; c. Proposed locations of water supply, sanitary sewer, and utilities; d. Proposed locations of drainage and stormwater management facilities; e. Proposed grading plan; f. Base flood elevations and future-conditions flood elevations; g. Boundaries of the base flood floodplain and future-conditions floodplain; h. If applicable, the location of the floodway; and i. Certification of the above by a licensed professional engineer or surveyor. 2. Building and foundation design detail, including but not limited to: a. Elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all proposed structures; b. Elevation in relation to mean sea level to which any nonresidential structure will be floodproofed; c. Certification that any proposed non-residential floodproofed structure meets the criteria in Sec. 12.7.5.B.2.; d. For enclosures below the base flood elevation, location and total net area of flood openings as required in Sec. 12.7.5.A.5.; and e. Design plans certified by a licensed professional engineer or architect for all proposed structure(s). 3. Description of the extent to which any watercourse may be altered or relocated as a result of the proposed development; 4. Hard copies and digital files of computer models, if any, copies of work maps, comparison of pre- and post-development conditions base flood elevations, future-conditions flood elevations, flood protection elevations, special flood hazard areas or future-conditions flood hazard areas and regulatory floodways, flood profiles and all other computations and other information similar to that presented in the FIS; 5. Copies of all applicable state and federal permits necessary for proposed development, including but not limited to permits required by Section 404 of the Federal Water Pollution Control Act, Amendments of 1972, 33 U.S.C. 1334; and 6. All appropriate certifications required under this ordinance. The approved floodplain management/flood damage prevention plan must contain certification by the applicant that all development activities will be done according to the plan or previously approved revisions. Any and all development permits and/or use and occupancy certificates or permits may be revoked at any time if the construction and development activities are not in strict accordance with approved plans. C. Construction Stage Submittal Requirements. For all new construction and substantial improvements on sites with a floodplain management/flood damage prevention plan, the permit holder must provide to the Floodplain Ordinance Administrator a certified as-built Elevation Certificate or Flood-proofing Certificate for nonresidential construction including the lowest floor elevation or flood proofing level immediately after the lowest floor or flood-proofing is completed. A final Elevation Certificate must be provided after completion of construction including final grading of the site. Any lowest floor certification made relative to mean sea level must be prepared by or under the direct supervision of a licensed land surveyor or professional engineer and be certified by same. When floodproofing is utilized for nonresidential structures, the certification must be prepared by or under the direct supervision of a licensed professional engineer or architect and be certified using the FEMA Floodproofing Certificate. This certification shall also include the design and operation/maintenance plan to assure continued viability of the floodproofing measures. D. Any work undertaken prior to approval of these certifications is at the permit holder's risk. The Floodplain Ordinance Administrator will review the above referenced certification data submitted. Deficiencies detected by the review must be corrected by the permit holder immediately and prior to further work being allowed to proceed. Failure to submit certification or failure to make the corrections required hereby shall be cause to issue a stop work order for the project. E. Duties and Responsibilities of the Floodplain Ordinance Administrator. Duties of the Floodplain Ordinance Administrator include, but are not limited to: 1. Review all development applications and permits to assure that the requirements of this ordinance have been satisfied and to determine whether proposed building sites will be reasonably safe from flooding; 2. Review proposed development to assure that all necessary permits have been received from those governmental agencies from which approval is required by federal or state law, including but not limited to Section 404 of the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. 1334; 3. When base flood elevation data or floodway data have not been provided, then the Floodplain Ordinance Administrator will require the applicant to obtain, review and reasonably utilize any base flood elevation and floodway data available from a federal, state or other sources in order to meet the provisions of Sec. 12.7.4 and Sec. 12.7.5. 4. Review and record the actual elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all new or substantially improved structures; 5. Review and record the actual elevation, in relation to mean sea level to which any substantially improved structures have been floodproofed; 6. When floodproofing is utilized for a nonresidential structure, the Floodplain Ordinance Administrator must review the design and peration/maintenance plan and obtain certification from a licensed professional engineer or architect; 7. Notify affected adjacent communities and the Georgia Department of Natural Resources (GA DNR) prior to any alteration or relocation of a watercourse and submit evidence of notification to the Federal Emergency Management Agency (FEMA); 8. Where interpretation is needed as to the exact location of boundaries of the areas of special flood hazard or areas of future-conditions flood hazard (e.g., where there appears to be a conflict between a mapped boundary and actual field conditions) the Floodplain Ordinance Administrator will make the necessary interpretation. Any person contesting the location of the boundary must be given a reasonable opportunity to appeal the interpretation, as provided in this ordinance. Where floodplain elevations have been defined, the floodplain is determined based on flood elevations rather than the area graphically delineated on the floodplain maps; 9. All records pertaining to the provisions of this ordinance will be maintained by the Foodplain Ordinance Administrator and made available for public inspection. 10. Coordinate all FIRM revisions with the GA DNR and FEMA; and 11. Review variance applications and make recommendations to the Board of Zoning Appeals.
Ask a question about Roswell law
Corpus searches the Roswell sections it holds and shows the ones that match, with their citations. Free, no sign-in.