§ 16.20.070 — Construction plan submittal, review, and approval

Municipal Code of the City of Evansville, Indiana (legislation through 06-22-2026) · Evansville Municipal Code § 16.20.070

Corpus is an independent public-information project, not the official City of Evansville website. Stable reference: corpuslaw.us/code/a47e9731-174b-4c3a-8610-7d08a720ea78

§ 16.20.070: Construction plan submittal, review, and approval.

(A) Requirement for the Submittal of a Compliant Construction Plan. The owner of a major project site must submit, or cause to be submitted, a construction plan for a major project subject to regulation by this chapter. (B) Submittal in Triplicate. The construction plan must contain the elements, requirements, provisions, and other content as enumerated for the project site in accordance with this chapter, and must be submitted in triplicate, three separate and identical copies, to the agency or MS4 operator, no later than two full weeks prior to the plan approval date of the board or entity to which the plan is routed by the MS4 operator. (C) The agency or MS4 operator will record the time and date of each construction plan submittal, and will manage the three copies of each project’s construction plan in accordance with the following procedure: (1) One copy will be forwarded to agency review staff as directed by the MS4 operator. (2) One copy will be held in a separate file for field use by the agency inspectors and other field representatives of the MS4 operator. (3) One copy will be held in a separate file to facilitate an opportunity for the Vanderburgh County SWCD to make technical comments and recommendations regarding the construction plan. (4) Upon the request of an authorized SWCD representative, the agency or MS4 operator will make one copy of a construction plan available to SWCD staff at any time during normal business hours. SWCD may transport the copy of the construction plan designated for SWCD comment and recommendation to any location of SWCD’s choosing for appropriate viewing, comment, recommendation, and repository. (D) Route of Review. The MS4 operator will determine the appropriate route of review and approval of a construction plan in accordance with this chapter. (E) Plan Approval before Initiation of Construction. Plan approval is required before the initiation of construction activity at a project site for which a construction plan is required. The initiation of construction activity prior to the MS4 operator’s notification of plan approval constitutes a violation of this chapter subject to an enforcement action, penalty or fine. If no land-disturbing activities occur, then initial mobilization of equipment, machinery, and tools to the site is permitted. At the project site owner’s risk for subsequent modification, installation of anticipated ECMs may begin. (F) Two-Week Plan Review Period. If the project site owner does not receive notification from the MS4 operator within 14 days after the construction plan is received by the agency or MS4 operator stating that the MS4 operator finds the construction plan is deficient, the project site owner may submit the required NOI letter of information to the department and, after 48 hours, proceed with construction activity. (G) The MS4 operator will provide the project site owner, or the designated representative of the project site operator, with an NPA as soon as is practicable following the agency or MS4 operator’s review and approval of the plan. The project site owner must include the NPA as verification of plan approval with the NOI sent to the department. (H) Notice of Plan Deficiency. If the MS4 operator determines that a construction plan is deficient, the MS4 operator will issue a notice of deficiency (NOD) letter requiring modifications, terms, and conditions as necessary for the plan to meet the requirements of this chapter. (I) Construction Activity with a Deficient Plan Constitutes a Violation. The initiation of construction activity at a project site following notification by the MS4 operator that the construction plan for the site does not meet the requirements of this chapter constitutes a violation of this chapter subject to an enforcement action, penalty, or fine. (J) Required Resubmittal of a Corrected Construction Plan. If the project site owner receives an NOD letter after the two-week review period expires and following commencement of construction activities at the site, the construction plan must be modified to meet the requirements of this chapter, and resubmitted within 14 days of receipt of the NOD. (K) The MS4 operator will determine the sufficiency of a construction plan based upon the requirements, provisions, and criteria enumerated, referenced, or attached to this chapter.

( 1983 Code § 9.98(B).07 ; Ord. G-2008-11 § 1, passed 4-9-2008 )