§ 405.100 — Construction Plan Requirements
Code of Ordinances, City of O'Fallon, Missouri (Code 2026-10-22) · O'Fallon City Code § 405.100
Corpus is an independent public-information project, not the official City of O'Fallon website. Stable reference: corpuslaw.us/code/f133c34b-d30f-494a-9c79-f61e236155f8
Section 405.100: Construction Plan Requirements.
A. General. The construction plan for all aspects of the site development shall be prepared by an engineer in an electronic format and shall be submitted for review to the City Engineer and/or his/her designee. Any resubmittal plans shall also be in an electronic format. 1. Electronic copy shall be in PDF format, or format that is deemed acceptable by the Department of Engineering. 2. All plans, details and reports shall be signed, sealed and dated by a registered professional engineer (per Missouri Economic Development requirement). B. The construction plan shall be any scale from 1 inch = 10 feet through 1 inch = 100 feet, so long as the scale is an increment of ten (10) feet and is sufficiently clear in reflecting details of the proposed construction. Construction plans shall be prepared on exhibits nominally twenty-four (24) inches by thirty-six (36) inches. The site plan or title page shall be used as the cover sheet for the construction plan. C. Amenities Plan And Schedule. In regard to amenities required as a condition of Planning and Zoning approval, detailed construction plans and specifications along with progress schedules shall be provided for, but not limited to, recreational buildings, swimming pools and appurtenant structures, tennis courts, jogging trails, fences and decorative landscaping provided as subdivision amenities. Unless otherwise specified by the Planning and Zoning Commission at the time of approval, these improvements are to be started prior to the City issuing building permits for more than thirty percent (30%) of the project and completed prior to the City issuing building permits for more than fifty percent (50%) of the project. D. Easements/Dedications Outside Subdivision Plat Boundaries. Where development or construction will require easements and right-of-way dedications, no approval of construction plans for developments will be granted until verification of the recording of all easements and right-of-way dedications has been received. E. Information Required. In all cases the construction plan submission should include a construction plan application. The Planning and Zoning Commission and City Council shall approve the applications and checklists for construction plans. Should a grading plan not be required to be submitted for a project, a geotechnical report for the site shall be prepared by a registered professional engineer, with their stamp, signature and address, and shall contain a complete set of soil information and descriptions (including but not limited to existing conditions of the site, potential settlement issues, fill treatment and compaction, recommended remediation techniques, etc.) that supply the City staff with all relevant site information. This shall be submitted as part of the Construction Plan submittal. F. Approval/Permits. 1. No person, firm or corporation shall develop, alter or modify any tract of land, roadway or any City-owned utility within the City of O'Fallon or cause the same to be undertaken without first securing the approval of the construction plans as required by this Chapter or other City ordinances, nor shall any person, firm or corporation undertake such work or cause the same to be undertaken without first obtaining the required permits from necessary agencies, including the City of O'Fallon, County, State or Federal Governments for the proposed construction. 2. Applications for building permits shall be filed with the Building Official or his/her duly authorized representative, upon the prescribed forms, setting forth the legal description of the lot, tract or parcel of land, together with a general description of the building or structure to be constructed, erected or altered thereon, including the approximate size and shape, principal material or construction, location of the building or structure upon the lot, tract or parcel and the intended use. 3. There shall be a separate permit for each building or structure to be constructed, erected or altered except accessory buildings which may be included in the permit for the principal building when construction is simultaneous. For each permit issued there shall be charged and collected from the applicant a fee in accordance with ordinances establishing same. 4. No permit shall be issued for any building, structure or construction unless the same is in conformity in every respect with all provisions of this Chapter. 5. The Building Official, or his/her duly authorized representative, shall be empowered to act within the provisions of this Chapter upon all applications for building permits, and the same shall be approved or denied not later than the 10th business day succeeding the day of filing. In the event of refusal to issue a permit upon an application as herein provided, the applicant shall have the right to appeal. 6. Work on any project may be suspended by the City Official at any time prior to the completion of the improvement, building or structure for which the approval/permit was issued, when it shall appear to him/her that there is departure from the plans, specifications or conditions as required under terms of the permit, that the same was procured by false representation, or that any provisions of this Chapter are being violated. Written notice of such stop work order shall be served upon the owner, his/her agent or contractor, or upon any person employed on the building or structure for which such approval/permit was issued, or shall be posted in a prominent location, and thereafter no such construction shall proceed. G. Violation And Penalty. 1. In case any building or structure is erected, constructed, reconstructed, altered, converted or maintained or any building, structure or land is used in violation of this Chapter, the City, in addition to other remedies, may institute any appropriate action or proceedings to prevent such unlawful erection, construction, reconstruction, alteration, conversion, maintenance, or use to restrain, correct or abate such violation; to prevent the occupancy of said building, structure or land; or to prevent any illegal act, conduct, business or use in or about such premises. 2. Failure to obtain and display the required permit prior to making such improvement shall constitute a violation of this Chapter. Each day of such non-compliance shall constitute a separate violation. 3. The owner or general agent of a building or premises where a violation of any provision of the regulations of this Chapter has been committed or shall exist, or the lessee or tenant of an entire building or entire premises where such violation has been committed or shall exist, or the owner, general agent, lessee or tenant of any part of the building or premises in which such violation has been committed or shall exist, or the general agent, architect, builder, contractor or any other person who commits, takes part or assists in any such violation or who maintains any building or premises in which any such violation exists shall be guilty of a violation of this Chapter punishable by a fine of not less than ten dollars ($10.00) and not more than one hundred dollars ($100.00) for each and every day that such violation continues or by imprisonment for ten (10) days for each and every day such violation continues, or by both such fine and imprisonment in the discretion of the court. Any such person who, having been served with an order to remove any such violation, shall fail to comply with such order within ten (10) days after such service or shall continue to violate any provision of this Chapter in the respect named in such order shall also be subject to a civil penalty of two hundred fifty dollars ($250.00). H. Permit Applicants. The applicant shall be the owner(s) of record or authorized representative designated by the owner(s). I. Plans And Fees. See Title IV, Appendix B, Schedule of Fees, Costs and Expenses, for fee schedule. 1. Refunds Of Fees. This Section addresses how refunds are to be handled in the event of cancelled projects. a. If plans have been submitted and reviewed (regardless of the status of the permit), any submittal fee for that permit is non-refundable. (1) Any plan that was submitted (with a paid submittal/permit/application fee) but an immediate request was made to cancel, then the unutilized fee(s) will be refunded. b. If plans were issued (all fees paid), and no construction has commenced, and a request to cancel has been submitted, then a refund can be issued for fifty percent (50%) of the total application fees (outside of additional review fees). (1) For commercial projects with a minimum fee, there will be no refunds. c. If construction has been occurring, requiring an inspector to visit the site, and a request to cancel has been submitted, then there are no refunds available. d. Under any of these scenarios, should the cancelled project wish to come back to the City for consideration, then it will need to pay all current, applicable permit fees as if it was a brand-new permit. 2. Expired Plans. a. If plans have been reviewed and expire, then there are no refunds available. (1) If all fees are paid, and no construction has commenced, and the plans have expired, then a refund can be issued for fifty percent (50%) of the total application fees (outside of additional review fees). b. An expired set of plans, who previously paid permit fees and desires to come back for review, will need to pay all current, applicable permit fees as if it was a brand-new permit.
[R.O. 2008 § 405.100; Ord. No. 6496 , 9-13-2018 ; Ord. No. 7056 , 10-26-2023 ; Ord. No. 7138 , 9-26-2024 ]
Ask a question about O'Fallon law
Corpus searches the O'Fallon sections it holds and shows the ones that match, with their citations. Free, no sign-in.