§ 405.114 — Lot Deposit (Attached And Detached Single-Family) During Building Construction
Code of Ordinances, City of O'Fallon, Missouri (Code 2026-10-22) · O'Fallon City Code § 405.114
Corpus is an independent public-information project, not the official City of O'Fallon website. Stable reference: corpuslaw.us/code/28b5ddc5-40e7-4ff6-947b-9f2146add50a
Section 405.114: Lot Deposit (Attached And Detached Single-Family) During Building Construction.
A. Purpose. The purpose of the lot deposit is to protect existing infrastructure on the site from damage from building construction, on that specific lot. This generally applies to infrastructure (except streets unless as explained below). B. With the various escrow options contained in Chapter 405 of the City Code, only one (1) valid escrow is required for each phase or plat of a project. The City cannot require duplicate escrows, but, at the same time, each lot being constructed on must have a suitable and valid escrow accepted by the City with the escrow being in compliance with Chapter 405 of the City Code. C. For each new building permit, a per-lot deposit must be established to cover potential damage to storm, sanitary and water infrastructure. This per-lot deposit will be done with the building permit for such lot and will also cover items outside of the building structure such as grading and sidewalks. D. When the per-lot deposit is to be initiated by a builder, an inspection of the current conditions within the subdivision will be performed by the City to document the existing conditions of the infrastructure. All parties involved with the per-lot deposit will have to agree on the list of existing deficiencies prior to executing the escrow documents. The builder and escrow holder on this new per-lot deposit will not be required to correct any of the preexisting deficiencies defined by the inspection. The preexisting deficiencies will remain the responsibility of the appropriate party to be repaired. E. With the per-lot deposit in place as noted above, the home builder will be required to post a one thousand dollar ($1,000.00) cash per-lot deposit with each home building permit being issued. This per-lot deposit will be released with the correction of any deficiencies caused by the home construction and issuance of the certificate of occupancy or temporary certificate of occupancy for the home. 1. The builder will have the option to post a single ten thousand dollar ($10,000.00) cash per-lot deposit, in lieu of individual escrows for each lot. This option will cover the per-lot deposit for all the homes being constructed across the City regardless of which subdivision it is in. If the City is required at any time to utilize the per-lot deposit to correct any deficiencies, the full value of the escrow must be restored prior to any additional building permits being issued to the builder. 2. If corrections of any deficiencies have not been completed within three (3) months of receiving the initial inspection report, a penalty of five hundred dollars ($500.00) shall be paid to the City of O'Fallon. If corrections of any deficiencies have not been completed within six (6) months of receiving the initial inspection report, an additional penalty of five hundred dollars ($500.00) shall be paid to the City of O'Fallon and until proper corrections have been made, future permits/reviews will not be conducted by the City of O'Fallon. At the City Engineer's discretion, exceptions can be made. 3. Prior to issuance of an occupancy permit, the builder shall provide a letter signed and sealed by a registered professional engineer verifying and stating the lot for which the building permit is issued complies with the approved grading and drainage plans. If this cannot be accomplished, the Building Official may issue temporary occupancy with the builder's already established per-lot deposit. The temporary occupancy can be replaced with a certificate of occupancy once a letter has been approved by the City. a. If the lot is graded correctly but vegetation has not been performed (established vegetation or sod), erosion control must be in place and the area seeded/strawed per the County vegetation type based on the time of year. F. The City reserves the right to not approve the use of this per-lot escrow in subdivisions where severe deficiencies in the public infrastructure exist with no clear method of resolving those deficiencies. G. Acknowledgment. At the time of application for a building permit, the applicant shall acknowledge, in writing, and with his/her signature, which the applicant is responsible for assuring that the lot for which the building permit is issued complies with the approved construction plans. H. Escrow Type And Agreement. The per-lot deposit must be in the form of cash, check or wire transfer to the City of O'Fallon and accompanied by a signed escrow agreement. I. Term, Length, Extension. The initial term length in which the escrow is in force shall be for a period not to exceed one (1) year, unless extended by the City. If the contractor fails to complete the work within this time frame and obtain an occupancy permit from the City before the end of the initial term length, the escrow shall continue in force until released by the City Engineer. J. Escrow Inspection And Release. 1. At the time the contractor or owner has requested a certificate of occupancy, the site and building shall be inspected for compliance. If no deficiencies are encountered on the building and the site, then a certificate of occupancy will be issued, and the escrow will be released in full. 2. Once the site and building are within compliance, all escrow funds will be returned. An exception to this compliance is weather-related and horticulture. If in the sound opinion of the Building and Code Enforcement Division the weather is not conducive to correct horticultural activities, then a certificate of occupancy can be issued without the site being in compliance. The horticulture must be finalized within six (6) months of the issuance of the certificate of occupancy, or the escrow will be utilized to correct the non-compliance and/or fines established per this Chapter. Any site-related issues, including horticulture activities, shall be completed within six (6) months of the issuance of the certificate of occupancy; otherwise the site will be deemed out of compliance. a. Any violation of the provisions of Subsection (J)(1) above shall be punished as provided in Section 100.010 of this Code of the City of O'Fallon. In addition to any penalties under Section 100.010, equitable relief shall also be available to enforce compliance pursuant to Section 100.011 of this Code of the City of O'Fallon. K. Multiple Additions. If the original site plan and/or building plan has had additions approved through the Planning and Zoning Commission and are on the current or adjacent site, the original escrow agreement can be altered so that only one (1) escrow agreement is in place; however, this is only at the request of the owner. The owner must understand that individual certificates of occupancy will not be approved under this process unless the escrow agreement is modified at the time of an individual site completion.
[R.O. 2008 § 405.114; Ord. No. 6496 , 9-13-2018 ]