§ 22.5-31 — Design standards for attenuation stormwater control measures (SCMs)

Code of Ordinances, City of Knoxville, Tennessee (Supplement 81; codified through Ordinance O-51-2026, June 23, 2026; online September 9, 2026; later unincorporated ordinances excluded) · Knoxville Code of Ordinances § 22.5-31

Corpus is an independent public-information project, not the official City of Knoxville website. Stable reference: corpuslaw.us/code/2787100d-fab9-4922-a6f9-ff6b6d210055

Sec. 22.5-31. - Design standards for attenuation stormwater control measures (SCMs).

(a) The calculated peak flow rate of stormwater runoff resulting from a 1-year, 2-year, 5-year, 10-year, 25-year, and 100-year frequency storm shall be no greater after site development of the site than that which would result from a 1-year, 2-year, 5-year, 10-year, 25-year, and 100-year frequency storm on the same site prior to site development. (b) Adequate attention must be given to safety and sanitation in the design of any stormwater basin. This includes, but is not limited to: (1) A minimum of two (2) percent slope in the bottom of all stormwater basins; a. An exception can be made to the minimum slope requirement in the bottom of the basin if the first flush requirement is not managed in the basin and the basin invert is finished in concrete. (2) A 3:1 (H:V) or flatter side slope used for traversable access to the bottom of a stormwater basin for maintenance; (3) Fifteen (15) percent additional area for each two-foot contour of the stormwater basin based on the appropriately sized basin for the 1-year, 2-year, 5-year, 10-year, 25-year, and 100-year frequency storms; a. When stormwater pretreatment is utilized to treat the first flush prior to discharging water into a stormwater basin, the basin is not required to have fifteen (15) percent additional volume. (4) A minimum of four thousand five hundred (4,500) cubic feet of storage volume in all stormwater basins; and (5) A minimum of one (1) foot of freeboard from the highest water surface elevation for the largest required design storm to the top of the berm before the fifteen (15) percent additional volume is added. (c) The plans shall include sufficient design information to show that the facility will operate as required. This design shall include: (1) Pre-development and post-development peak flow discharges; (2) Volumes of stormwater runoff based on the proposed site development; (3) All computations used to determine the reduced peak flow rates for the design storms; and (4) The capacity of the facility shall be sufficient to control the volume of stormwater runoff resulting from 1-year, 2-year, 5-year, 10-year, 25-year, and 100-year frequency storm within the peak flow requirements stated in this section. (d) Discharge from attenuation SCMs shall be routed to a stormwater system of adequate capacity. (1) Calculations showing the capacity of the adjacent downstream system and its capability to convey a 10-year frequency storm shall be provided. (2) If examination of the adjacent downstream system finds inadequate conveyance of the 10-year frequency storm, the director has authority to condition the approval of a permit upon the compliance with additional requirements, including but not limited to, installation or modification of the stormwater system or other stormwater control measures required to reduce the adverse impact of the proposed development.

(Ord. No. O-145-2025, § 1, 11-25-25)

Ask a question about Knoxville law

Corpus searches the Knoxville sections it holds and shows the ones that match, with their citations. Free, no sign-in.