§ 22.5-33 — Requirements for developments draining to a sinkhole
Code of Ordinances, City of Knoxville, Tennessee (Supplement 81; codified through Ordinance O-51-2026, June 23, 2026; online September 9, 2026; later unincorporated ordinances excluded) · Knoxville Code of Ordinances § 22.5-33
Corpus is an independent public-information project, not the official City of Knoxville website. Stable reference: corpuslaw.us/code/ddecb2d4-5339-4ced-8ae5-9c4ebed3a5ef
Sec. 22.5-33. - Requirements for developments draining to a sinkhole.
(a) Special attenuation is required for developments that meet the requirements for attenuation and are located in areas draining to sinkholes or areas of known flooding, where deemed necessary by the director. (b) In addition to the standard attenuation requirements, stormwater facilities providing special attenuation shall be designed such that: (1) The volumetric difference in the pre-developed and post-developed 100-year frequency storm is retained. (2) In watersheds where there is a documented historical drawdown time for the sinkhole or region, it may be acceptable for a stormwater facility to slowly release the retained storm. The drawdown time of the stormwater facility must be the greater of the: a. Documented historical drawdown time; or b. Six (6) days. (c) Developments requiring attenuation with sinkholes entirely on site: (1) Calculations shall be provided showing that 100-year frequency storm will not flood any structures assuming plugged conditions for the sinkhole, zero (0) cfs outflow. (2) Calculations must include the entire contributing watershed for the sinkhole. (3) An easement is required around the sinkhole to include an area extending to the greater of: a. Five (5) feet horizontally outside the 100-year water surface elevation; or b. One (1) foot above the 100-year water surface elevation. (d) Developments requiring attenuation with sinkholes partially on site: (1) Calculations must be provided showing that there will not be a rise in water surface elevations between the pre-development and post-development 100-year frequency storms assuming plugged conditions for the sinkhole, zero (0) cfs outflow. (2) An easement is required at a minimum of five (5) feet horizontally outside the 100-year water surface elevation on the section of the sinkhole located on the developed property. (3) A rise in the 100-year water surface elevation is allowable when no structures will be flooded and all parties with ownership of the sinkhole agree in writing to allow the rise. When a rise is allowed, an easement is required around the sinkhole to include an area extending to the greater of: a. Five (5) feet horizontally outside the 100-year water surface elevation; or b. One (1) foot above the 100-year water surface elevation.
(Ord. No. O-145-2025, § 1, 11-25-25)
Ask a question about Knoxville law
Corpus searches the Knoxville sections it holds and shows the ones that match, with their citations. Free, no sign-in.