§ 4.04 — One Acre or Greater Disturbances
Code of the City of Arlington, Texas (City Secretary chapter PDFs as posted 2026-11-07, each current through the ordinance named on its cover, with the City Secretary's adopted-not-yet-codified Ordinances 25-063, 25-069, 25-073, 25-074, 25-075, 25-084, 26-003, 26-004, 26-019, 26-024 and 26-027 applied; Anti-Discrimination chapter not included) · Arlington City Code, Stormwater Pollution Control Chapter, § 4.04
Corpus is an independent public-information project, not the official City of Arlington website. Stable reference: corpuslaw.us/code/137d74eb-5512-480c-b1a0-6b0a8adf9411
Section 4.04 One Acre or Greater Disturbances
All operators of sites of construction activity, including demolition, clearing, grading, excavation, and landfilling activities, that result in the disturbance of one or 4.04 more acres of total land area, or that are part of a common plan of development or sale within which one or more acres of total land area are disturbed, or who are required to obtain a TPDES permit for stormwater discharges associated with construction activity, shall comply with the following requirements (in addition to those in Section 4.02.): A. Any operator who intends to obtain coverage for stormwater discharges from a construction site under the TPDES General Permit for Stormwater Discharges from Construction Sites ("the Construction General Permit") but not an individual permit shall: For sites five acres and more submit a signed copy of its NOI to the Director of Public Works and Transportation or his/her authorized representative, and to any other responsible City departmental Director, at least two calendar days prior to the commencement of construction activities, or 1. For sites one acre or more but less than five acres submit a copy of the Construction Site Notice required by the TPDES General Permit. 2. For stormwater discharges from construction sites where the operator changes, a revised Construction Site Notice or NOI as appropriate for the site shall be submitted at least two calendar days prior to when the new operator commences work at the site. 3. Adhere to all construction requirements (where applicable) as outlined in the TPDES Construction General Permit (CGP) TXR150000. B. A Stormwater Pollution Prevention Plan (SWPPP) shall be prepared and implemented prior to the beginning of construction activities in accordance with the requirements of the Construction General Permit or any individual NPDES or TPDES permit issued for stormwater discharges from the construction site, and with any additional requirement imposed by or under this Chapter and any other city ordinance. C. The SWPPP shall be prepared and certified by a Licensed Professional Engineer or other professional, approved by the Director or his/her authorized representative, certified in a discipline that includes erosion and sediment control principals appropriate for the site. The signature, date and seal of the Licensed Professional Engineer or other appropriate certification for the professional certifying the plan shall constitute his/her attestation to the best of his/her knowledge that the SWPPP fully complies with the requirements of the Construction General Permit, or with any applicable individual NPDES or TPDES permit issued for stormwater discharges from the construction site, and with any additional requirement imposed by or under this Chapter. The SWPPP 4.04 shall contain the name, title, and business address of the professional signing the SWPPP, and the date that he/she did so. D. The SWPPP shall be updated and modified as appropriate and as required by the NPDES or TPDES permit and this Chapter. Any update or modification to the SWPPP that results in a change in design, construction, operation, or maintenance, which has a significant effect on the potential for the discharge of pollutants to the MS4 or to the waters of the United States shall be prepared, signed, dated, and sealed by a Licensed Professional Engineer or other professional, approved by the Director or his/her authorized representative, certified in a discipline that includes erosion and sediment control principals appropriate for the site. E. The SWPPP shall be prepared and submitted to the Director or his/her authorized representative at least fifteen calendar days prior to the commencement of construction activities. F. A copy of any SWPPP that is required by Section 4.04(B) shall be submitted to the City in conjunction with any application for a building permit, demolition permit, early grading release, site development plan approval, and any other City approval necessary to commence or continue construction at the site. G. If, upon the Director's review of the SWPPP (or any modification to the SWPPP) or review by his/her authorized representative and any site inspection that the Director or his/her authorized representative may conduct, the Director or his/her authorized representative determines that the SWPPP does not comply with the requirements of the Construction General Permit, any individual NPDES or TPDES permit issued for stormwater discharge from the construction site, or any additional requirement imposed by or under this Chapter, the Director or his/her authorized representative may issue an order prohibiting the commencement, or the continuation, of any construction activity at the site. Also, if at any time the Director or his/her authorized representative determines that the SWPPP is not being fully implemented, the Director or his/her authorized representative may similarly issue an order prohibiting the continuation of any construction activity at the site. Any order issued by the Director or his/her representative under the authority of this paragraph may be in the form of a Compliance Order under Section 9.01(E), an Emergency Cease and Desist Order under Section 9.01(G), or a Stop Work Order under Section 9.01(H). 4.04 H. Upon review of the SWPPP and any site inspection that is conducted, the City may deny approval of any building permit, early grading release, or any other City approval necessary to commence or continue construction, or to assume occupancy, on the grounds that the SWPPP does not comply with the requirements of the Construction General Permit, any individual NPDES or TPDES permit issued for stormwater discharge from the construction site, or any additional requirement imposed by or under this Chapter. Also, if at any time the City determines that the SWPPP is not being fully implemented, the City may similarly deny approval of any building permit, early grading release, or any other City approval necessary to commence or continue construction, or to assume occupancy, at the site. I. All owners/developers, contractors and subcontractors identified in an SWPPP shall sign a copy of the following certification statement before conducting any professional service identified in the SWPPP: "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations." The certification must include the name and title of the person providing the signature; the name, address, and telephone number of the contracting firm; the address (or other identifying description) of the site; and the date the certification is made. J. The SWPPP, with the Licensed Professional Engineer's signature, seal, and date affixed, and the certifications of owners, developers, contractors and subcontractors required by Section 4.04(I), and with any modifications attached, shall be retained at the construction site from the date of commencement of construction through the date of final stabilization. K. The operator shall make a copy of the SWPPP and any modification thereto available to the Director and any other authorized City inspector at the construction site upon request (as well as to EPA and state inspectors). L. The Director or his/her authorized representative may notify the operator at any time that the SWPPP does not meet the requirements of the Construction General 4.04 Permit, any applicable individual NPDES or TPDES permit issued for stormwater discharges from the construction site, or any additional requirement imposed by or under this Chapter. Such notification shall identify those provisions of the permit or Ordinance which are not being met by the SWPPP and identify which provisions of the SWPPP require modifications to meet such requirements. Within seven calendar days of such notification from the Director or his/her authorized representative (or as otherwise provided by the Director or his/her authorized representative), the operator shall make the required changes to the SWPPP and shall submit to the Director or his/her authorized representative a written certification that the requested modifications have been made. M. The operator shall modify the SWPPP whenever there is a change in design, construction, operation, or maintenance, which has a significant effect on the potential for the discharge of pollutants to the MS4 or to the waters of the United States, and which has not otherwise been addressed in the SWPPP, or if the SWPPP proves to be ineffective in eliminating or significantly minimizing pollutants, or in otherwise achieving the general objective of controlling pollutants in stormwater discharges associated with construction activity. In addition, the SWPPP shall be modified to identify any new contractor and/or subcontractor that will implement a measure in the SWPPP. All modifications to the SWPPP shall be signed, dated, and sealed by a Licensed Professional Engineer or other professional, approved by the Director of Public Works and Transportation, certified in a discipline that includes erosion and sediment control principles appropriate for the site, then submitted to the Director or his/her authorized representative within seven calendar days of a change, determination of ineffectiveness (self or City inspection), or effective date of changes in contractor and/or subcontractor. N. Qualified personnel (provided by the operator of the construction site) shall inspect disturbed areas of the construction site that have not been finally stabilized, areas used for storage of materials that are exposed to precipitation, structural control measures, and locations where vehicles enter or exit the site, every seven days or at least once every fourteen calendar days and within twenty-four hours of the end of the storm that is 0.5 inches or greater. Disturbed areas and areas used for storage of materials that are exposed to precipitation shall be inspected for evidence of, or the potential for, pollutants entering the drainage system. Erosion and sediment control measures identified in the SWPPP shall be observed to ensure that they are operating correctly. Where discharge locations or points are accessible, they shall be inspected to ascertain whether erosion control measures are effective in preventing significant impacts to receiving waters or the MS4. Locations where vehicles enter or exit the site shall be inspected for evidence of off-site sediment tracking. 4.04 O. Based on the results of the inspections required by Section 4.04(N), the site description and/or the pollution prevention measures identified in the SWPPP shall be modified as appropriate, but in no case later than seven calendar days following the inspection. Such modifications shall provide for timely implementation of any changes to the SWPPP within seven calendar days following the inspection. All modifications to the SWPPP shall be submitted to the Director or his/her authorized representative within seven calendar days of the date of inspection. P. A written report summarizing the scope of any inspection required by Section 4.04(N), and the name(s) and qualifications of personnel making the inspection, the date(s) of the inspection, major observations relating to the implementation of the SWPPP, and actions taken in accordance with Section 4.04(O) above shall be made and retained as part of the SWPPP for at least three years from the date that the site is finally stabilized. Such report shall identify any incidence of noncompliance. Where a report does not identify any incidence of noncompliance, the report shall contain a certification that the facility is in compliance with the SWPPP, the facility's NPDES or TPDES permit, and this Chapter. The report shall be certified and signed by the person responsible for making the report and consistent with the signing requirements of the permit. Q. The operator shall retain copies of any SWPPP and all reports required by this Chapter or by the NPDES or TPDES permit for the site, and records of all data used to complete the NOI, for a period of at least three years from the date that the site is finally stabilized. R. Where a site has been finally stabilized and all stormwater discharges from construction activities that are authorized by this Chapter and by the NPDES or TPDES permit for those construction activities are eliminated, or where the operator of all stormwater discharges at a facility changes, the operator of the construction site shall submit to the Director of Public Works and Transportation, and to any other responsible City departmental Director, a NOT that includes the information required for Notices of Termination by Part II, Section F of the TPDES Construction General Permit. S. Upon final stabilization of the construction site, the owner (or the duly authorized representative thereof) shall submit to the responsible Director written certification that the site has been finally stabilized. (See definition of final stabilization in this Chapter.) The City may withhold an occupancy or use permit for any premises constructed on the site until such certification of final stabilization has been filed and the responsible Director has determined, following any appropriate inspection, that final stabilization has, in fact, occurred and that any required permanent structural controls have been completed. 4.04 T. Final plans or other documents that will be archived must be submitted in an electronic format specified by the Director of Planning and Development Services ("PDS Director") as a condition to issuance of any type of permit, approval, or other action related to the final plans or documents. The City may provide an electronic conversion service for a fee in the amount set forth by City Council resolution. The PDS Director shall provide a schedule indicating which documents must be provided electronically, at which point during the approval process, and other information as necessary to implement an electronic archiving program.
Ask a question about Arlington law
Corpus searches the Arlington sections it holds and shows the ones that match, with their citations. Free, no sign-in.