§ 17.32.080 — Import and Export of Earth Material; Stockpiling
Municipal Code of the City of San Marcos, California (Codified through Ordinance No. 2026-1582, enacted September 22, 2026. (Supp. No. 14)) · San Marcos Municipal Code § 17.32.080
Corpus is an independent public-information project, not the official City of San Marcos website. Stable reference: corpuslaw.us/code/a59666b9-55cf-4164-9d92-85152d6578c3
17.32.080 - Import and Export of Earth Material; Stockpiling.
(a) Haul Route. If the Grading project includes the movement of earth material to or from the site in an amount considered substantial by the Administrative Authority, the Permittee shall submit the haul route for review and approval by the Administrative Authority, in conjunction with the Grading permit. The Administrative Authority may suggest alternate routes, hours of work, or special requirements in consideration of the possible impact on the adjacent community environment, potential impacts considered in any applicable environmental analysis, or effect on the public right-of-way itself, which the Administrative Authority shall prescribe as a condition of the permit. Where excavation or embankment material is imported or exported from one Grading site to another over public streets, whether or not either site is otherwise subject to Grading permit requirements, the Administrative Authority may specify the route to be used in transporting the materials upon public streets. Deviation from this designated haul route shall constitute a violation of the conditions of the permit issued under this Code. The route, if any, shall be specified by written note on the permit document. The approval of the haul route in a Grading permit does not relieve the requirement to obtain a transportation permit for large vehicles/loads. (b) Haul Load Limits. The Administrative Authority may specify load limits when, in the opinion of the Authority, the standard load capacity of vehicles used in such hauling would cause excessive damage to streets on the designated route. Any Grading or hauling contractor moving earth materials in violation of this Chapter shall be financially responsible for any damage to the public streets done by the hauling vehicles, and shall pay to the City the cost, as determined by the Administrative Authority, of repairing the damage. (c) Notification. The Applicant shall also be required to notify the Administrative Authority at least 24 hours before hauling is to commence. The Administrative Authority may require traffic control devices to be provided by the Permittee as may be reasonably necessary to protect the health, safety, and general welfare of the public. (d) Other Conditions. The permit may specify other conditions which the Administrative Authority determines are necessary to minimize a disruption in normal traffic activities and public inconvenience on the public streets. (e) Debris. California Vehicle Code Section 23112(b) forbids the placing, dumping, or depositing of dirt and rocks on the public streets or any portion of the public right-of-way. No person shall, when hauling any earth, sand, gravel, rock, stone or other excavated material over any place, allow such materials to blow or spill over and upon such street, alley, or place, or adjacent private property. No person engaged in hauling materials under a permit issued pursuant to this Chapter shall deposit dirt or debris on the public streets by any means, including but not limited to, spillage from the bed of a truck or other vehicle or the dropping of debris collected on the wheels of the haul vehicle. The Permittee, or person on whose behalf the Grading is done if different than the Permittee, shall be responsible for the complete removal of dirt, rocks or debris from the street, if spilled, dumped, or deposited on a public street as a result of the Grading or hauling action. If the Permittee fails to remove completely such spillage, and it is necessary for the City to cause such removal to be made, the Permittee and the person on whose behalf the Grading is done, shall be jointly and severally liable to pay the City the full cost of the removal work. A cash deposit, bond or other security may be required to ensure the clean-up of public streets, and/or repair of any damage to streets resulting from hauling. (f) Dust Prevention. Where an excess of 5,000 cubic yards of earth per site project is moved on public roadways from or to the site of an earth Grading operation then either water or dust palliative or both must be applied to the transported material to alleviate or prevent excessive dust resulting from the loading or transportation of earth from or to the project site on public roadways. (g) Points of Access. Access roads to the premises shall be only at points designated on the approved Grading plan. The last 50 feet of the access road, as it approaches the intersection with the public roadway, shall have a grade not to exceed three percent. There must be a 300-foot clear, unobstructed sight distance to the intersection from both the public roadway and the access road. If the three percent grade or 300-foot sight distance cannot be obtained, flagmen shall be posted in accordance with the requirements of the Administrative Authority. A stop sign conforming to the requirements of the California Vehicle Code shall be posted at the entrance of the access road to the public roadway. Permittee shall obtain a right-of-way permit to install advance warning signs, traffic control, and safety devices shall be posted on the public roadway in the vicinity of the access intersection in accordance with the latest edition American Public Works Association Work Area Traffic Control Handbook"(WATCH) and the current California Manual on Uniform Traffic Control Devices (CA MUTCD). The advance warning signs and/or other devices shall be covered or removed when the access intersection is not in use. (h) Stockpiling. The Administrative Authority may approve a request for temporary stockpiling of material as part of the review of the grading plan and/or stockpile plan. The erosion and sediment control plans shall depict the location of the stockpile and associated BMPs. Stockpiles shall be included in the Engineer of Record's cost estimate for the grading application to secure the erosion control measures and ultimate removal or appropriate permanent compaction of the stockpiled material in compliance with the security provisions of Section 17.32.065 of this Chapter.
(Ord. No. 2022-1522, § 2(Exh. A), 9-13-2022)