17.32.160 - Completion of Work, Release of Security, and Issuance of Building Permits.
(a) Key Stages of Work Completion. (1) Rough Grade. When all rough Grading has been completed. Under normal circumstances, all subdrains and Slope drains shall be in place and approved as a condition for rough Grading approval. Rough grades shall be within 0.2 feet of finish grades. (2) Final. After all work, including installation of all drainage structures and other protective devices, has been completed and all written professional approvals and the required reports have been submitted. An as-built plan will be required to document any changes made to the project in the field. (b) Notification of Completion. The Permittee or their agent shall notify the Administrative Authority when the grading operation is ready for rough grade inspection or final inspection. Final approval shall not be given until all work including installation of all drainage facilities and their protective devices and all erosion control measures have been completed in accordance with the City final approved grading plan and the required reports have been submitted. (c) Requests for Release of Security. The Permittee or their agent shall notify the Administrative Authority in writing to initiate the release of securities when work is complete and all required reports, written certifications, drawings, and supplements thereto have been accepted by the Administrative Authority. (d) Final Reports. Upon completion of the rough Grading work and at the final completion of the work the Administrative Authority may require the following reports, written certifications, drawings, and supplements thereto. All required reports, written certifications, drawings, and supplements shall be provided and accepted by the Administrative Authority prior to release of security or issuance of building permits, unless otherwise allowed by the Administrative Authority. (1) Responsibilities Upon Completion of Work—Engineer of Record. a. As-Graded Grading plan prepared by the Engineer of Record including original ground surface elevations, as-graded ground surface elevations, lot drainage patterns and locations and elevations of all surface and subsurface drainage facilities. They shall provide certification that the work was done in accordance with the final approved grading plan. The Engineer of Record also shall be responsible for the preparation of revised plans and the submission of as-graded Grading plans upon completion of the work. The Grading contractor shall submit in a form prescribed by the Administrative Authority a statement of compliance to said as-built plan. b. Grading Certification. The Engineer of Record shall provide a written statement that in their professional opinion, all work incorporated in the grading and drainage plans and authorized under the grading permit, including grading, drainage, and construction of appurtenant structures, has been completed to the lines and grades in substantial conformance with the approved plans, or any approved revisions thereto. c. Structural BMP Self-Certification Package. The Engineer of Record shall provide a written certification in a form acceptable to the Administrative Authority documenting the appropriate design, installation, testing, and function of any required Structural BMPs. At a minimum, the certification package shall include the following: 1. A statement that Structural BMPs have been installed as per the approved Grading plan and any modifications thereto approved by the Administrative Authority; 2. A statement that all modifications to the Structural BMPs have been reflected on the Administrative Authority's record plan set; 3. Delineation of any and all modifications to the Structural BMPs approved by the Administrative Authority since the time of Permit issuance and an explanation of the site conditions and/or the justification for each modification; 4. Final calculations documenting compliance with the current order from the RWQCB; 5. Engineer of Record's inspection reports and notes, photographic documentation, or other evidence in a form acceptable to the Administrative Authority documenting correct and complete construction of the Structural BMPs, particularly sub-surface features and appurtenant drainage facilities; 6. A statement that all Structural BMP facilities and appurtenances have been cleared of any and all construction-related debris, including sediment; 7. A statement that all Structural BMP facilities and appurtenances have been tested and that the Engineer of Record has verified appropriate function consistent with the submitted calculations and with the current order from the RWQCB; 8. The signature and seal of the Engineer of Record; 9. Supplemental information, calculations, covenants, maintenance documents, and certifications as may be required by the Administrative Authority. (2) Responsibilities Upon Completion of Work—Geotechnical Engineer. a. As-Graded Geotechnical Report prepared by the Geotechnical Engineer including locations and elevations of field density tests, summaries of field and laboratory tests and other substantiating data. Such report shall detail changes made during grading and their effect on the recommendations made in the geotechnical engineering investigation report. b. Approval of Adequacy of the Site for the intended use. c. Written Statement that in their professional opinion, all work incorporated in the Grading plan authorized under the permit and soils/compaction report has been constructed in accordance with the approved plans and any approved revisions thereto. (3) Responsibilities Upon Completion of Work—Engineering Geologist. a. Geologic Grading Report prepared by the Engineering Geologist, including final description of the geology of the site including any new information disclosed during the Grading and the effect of same on recommendations incorporated in the approved Grading plan. b. Approval of Adequacy of the Site for the intended use as affected by geologic factors. (4) Responsibilities Upon Completion of Work—Landscape Architect. a. The Landscape Architect, Civil Engineer, or Architect professionally responsible for the inspection of all landscaping and irrigation required as per the grading permit and plans shall provide a written statement that in their professional opinion, all work incorporated in the landscape and irrigation plans authorized under the permit has been constructed in accordance with the approved plans and any approved revisions thereto; that the contractor's work is in conformance with the landscape plans; and that all individual plants show vigorous established growth typical of their species. b. The Landscape Architect shall provide a written statement to the Administrative Authority that all irrigation systems were pressure tested prior to backfilling and after completion and shall show evidence of proper functioning prior to acceptance by the City. Such systems shall not be accepted by the City until plant growth is established and maintenance responsibilities have been accepted by the appropriate party. (5) Certification of Slope Stabilization shall be made by the Geotechnical Engineer or Landscape Architect, when required by the Administrative Authority. Where necessary due to factors beyond the control of the developer, temporary postponement of the installation of a Slope stabilization may be permitted by the Administrative Authority as an exception to the above required certification provided that a secured agreement or other assurance acceptable to the City assuring repair of slopes and related damage, and installation of stabilization work within a satisfactory specified time is first executed by the Permittee. (e) Requirements Prior to Building Permits. Prior to the issuance of building permits for any given lot or lots, the following are required: (1) Responsibilities Prior to Building Permit Issuance: Engineer of Record shall submit a statement as evidence that rough Grading has been completed within standard tolerance in accordance with the approved plans, and that all embankments, cut Slopes, and pad sizing are as shown on the approved plans. (2) Responsibilities Prior to Building Permit Issuance: Geotechnical Engineer shall submit a statement that all fills, under their direction, have been compacted to at least 90 percent maximum density, and all street and parking lot base courses have been compacted to at least 95 percent maximum density.
(Ord. No. 2022-1522, § 2(Exh. A), 9-13-2022)