SECTION 409 STORM DRAIN CULVERT MATERIALS & CONSTRUCTION GENERAL INFORMATION
409.1 The structural design of all box culverts or bridges shall conform to the design standards of the Mississippi State Highway Department for a load capacity of twenty (20) tons minimum.
409.2 Bridges shall be constructed of either reinforced concrete or structural steel with a reinforced concrete deck. No mud sills or timber grills will be permitted for bridge foundations. All bridges shall be provided with substantial guard rails and sidewalks.
409.3 All culverts, cross-drainage and storm sewers shall be constructed in accordance with any Standard Specifications and Standard Drawings adopted by the City of Flowood, Mississippi and the Mississippi Standard Specification for Road and Bridge Construction (Latest Edition).
409.4 All culverts, cross drainpipes, and storm drainpipes shall be reinforced concrete pipe (R.C.P.), Class III or High-Performance polypropylene pipe, dual wall with a smooth interior and shall be installed per the manufacturer’s recommendation for the proposed purpose and location. See Section 410 for more requirements.
409.5 Dual wall corrugated pipes (C.P.P.) may be used for minor roof or yard drains in lieu of HP for site plan projects and pipe that is on private property that will not be maintained by the City.
409.6 Open ends of all culverts (upstream and/or downstream openings) shall have a flared end section.
409.7 Other materials may be approved by the City of Flowood Public Works Department for non-new construction sites.
409.8 All pipe shall be installed in accordance with the latest edition of the Mississippi Standard Specifications for Road and Bridge Construction or per the manufacturer’s recommendation, whichever is more stringent, and as directed by this section.
409.9 The city shall be contacted a minimum of 24 hours prior to the installation of any underground storm drainage pipe so the City may inspect the installation and the connection of any storm drainpipe to drainage structures prior to the commencement of backfill operations. The city may require any pipes that are not inspected prior to backfilling to be re-exposed so that inspection can be performed. Any costs associated with this would not be the responsibility of the City.
Ask a question about Flowood law