SECTION 411 FINAL INSPECTION AND ACCEPTANCE
411.1 After all underground utilities are installed and prior to acceptance by the city, the City reserves the right to require a CCTV video inspection by an approved CCTV inspection company at the expense of the Owner.
411.2 Any construction debris found shall be removed, and any separated joints, misaligned pipe, or any other defects which may be found shall be corrected by the contractor prior to formal
acceptance by the city.
411.3 If required, the inspection firm shall furnish the city with two full versions of a detailed report of the inspection. The reports shall include two printed and bound color copies of the report and an electronic copy in .pdf format as well.
411.4 If any defects are found, a post correction inspection will be required as well. The report format and variance classifications shall follow NASSCO PACP (Pipeline Assessment Certification Program) standards.
411.5 The city shall also be contacted a minimum of 24 hours prior to the installation of any underground storm drainage pipe to allow the City time to perform an inspection. The city shall inspect any storm drainpipe and the connection of any storm drainpipe to drainage structures prior to the commencement of backfill operations. The City may require any pipes or structures not inspected by the City prior to backfilling to be uncovered by the Contractor so that an inspection may be performed.