Sec. 32-105. - Hydraulics of storm drainage systems.

(a) Allowable pavement encroachments. Street flow capacities. For the purpose of this division, both the ten percent chance and one percent chance storm runoff must be considered, and calculations showing storm runoff at critical sections shall be submitted. The following criteria shall apply in the determination of allowable street flow capacities: (1) Initial (ten percent chance) storm street capacities. Pavement encroachment for the initial design storm shall not exceed the limitations outlined in the following table: ALLOWABLE PAVEMENT ENCROACHMENT DEPTH OF RUNOFF FLOW FOR 10% CHANCE STORM Street Classification | Maximum Encroachment Local | No curb overtopping, flow may spread to crown of street Collector | No curb overtopping, flow spread must leave the equivalent of one 10-foot (3.3 m) driving lane clear of water Arterial (minor and major) | No curb overtopping, flow spread must leave the equivalent of two, 10-foot (3.3 m) driving lanes clear of water. One lane in each direction Freeway | No encroachment allowed on any traffic lane The ten percent chance storm drainage system shall commence at a point where the maximum allowable encroachment occurs. (2) Major (one percent chance) storm street flow capacities. The allowable depth of flow and inundated area for the major storm runoff shall not exceed the limitations outlined in the following table: ALLOWABLE PAVEMENT ENCROACHMENT DEPTH OF FLOW AND INUNDATED AREA FOR MAJOR STORM RUNOFF Street Classification | Maximum Encroachment Street Classification | Allowable Depth and Inundated Area Local and collector | Residential dwellings, public commercial and industrial buildings shall not be inundated at the ground line unless buildings are flood proofed. The storm runoff shall be contained within the right-of-way Arterial | Residential dwellings, public, commercial and industrial buildings shall not be inundated at the ground lines unless buildings are flood proofed. Depth of water at the street crown shall not exceed six inches (0.152m) to allow operation of emergency vehicles. The depth of water over the gutter flow line shall not exceed 12 inches (0.305M). The storm runoff shall be contained within the right-of-way Freeway | No water on crown of street (3) Cross street flow capacities. Cross street flow can occur by two separate means. One is runoff that has been flowing in a gutter and then flows across the street to the opposite gutter, outlet, or inlet. The second case is flow from an external source, such as a drainage way or conduit, which will flow across the crown of a street when the conduit capacity is exceeded. The maximum allowable cross street flow depth based on the worst condition shall not exceed the limitations stipulated in the following table: ALLOWABLE CROSS STREET SECTION FLOW Street Classification | Initial Storm Runoff 10% chance, 24-hour | Major Storm Runoff 1% chance, 24-hour Local | Inch (0.076 m) depth at crown | 6 inches (0.16 m) of depth above crown Collector | Depth of flow shall not exceed 3 inches (0.076 m), at crown. | 6 inches (0.16m) of depth above crown Arterial | None | None Freeway | None | None *Cross street velocity should not exceed ten ft./sec. unless approved by public works director. (b) Storm drains and storm inlets. Storm drains and inlets shall be of sufficient capacity to adequately convey the expected runoff from the ten percent chance design storm. The storm drain system and subsequent storm inlets shall commence at all locations where the allowable street capacity is exceeded or at locations where ponding of water is likely to occur. (1) Minimum pipe diameter. The minimum allowable pipe size to be used in storm drains and laterals is as follows: MINIMUM ALLOWABLE PIPE SIZE Type of Conduit | Minimum Pipe Diameter Main trunk | 24 inches (0.610 m) Individual laterals (to drop inlets) | 18 inches (0.457 m) Elliptical or arch pipe will be allowed where design conditions dictate, provided that the cross sectional area of the arch pipe is not less than the area of the conduits listed above. (2) Allowable pipe materials/applications. Allowable pipe materials and applications are as follows: a. HDPE (first and last joint shall be concrete or CMP where pipe exits soil if no drop inlet). b. Reinforced concrete pipe, class III. c. Corrugated metal pipe: application is dependent on soil conditions and pipe application. d. Life expectancy of all pipe shall be 20 years minimum based on designed usage. Note: All pipes and conduits must be designed to withstand all structural loads (dead load and live load). State department of transportation standards shall be considered as a minimum guideline for the basis for design. Storm drains and culverts shall not have a cover depth of less than two feet of finished grade at any point unless design analysis and conditions of site dictate otherwise. (3) Manhole spacing. The maximum allowable spacing between manholes or other provisions for cleanouts shall not exceed those listed in the following table: MAXIMUM ALLOWABLE MANHOLE SPACING Pipe Diameter | Maximum Allowable Spacing Between Manholes and Cleanouts 24—36 in. (0.610 m—0.914 m) | 400 feet (122 m) 42—60 in. (1.061 m—1.52 m) | 500 feet (152 m) Greater than 60 in. (1.524 m) | 750 feet (228 m) Manholes shall be placed at any change in grade or direction and at all connections unless approved by the public works director. The storm drain system should be placed under the roadway. Alternate locations may be approved by the public works department if conditions prevent standard location. (4) Calculation of flow capacities in drainage conduits. The capacities of conduits shall be computed using Manning's formula, appropriate flow nomographs, or approved computer modeling program. The value of the roughness coefficient (n) to be used shall not be less than those specified in the following table. The average full-flow velocity in conduits shall not be less than two feet/second (0.61m/s). Included in the table are roughness coefficients that can be used in open channel flow calculations. VALUES OF N FOR THE MANNING FORMULA Flow Condition | n Plastic pipe, PVC, HDPE | 0.009 Smooth metal | 0.010 Ordinary concrete | 0.013 Asphalted cast iron | 0.013 Vitrified clay | 0.014 Cast iron pipe | 0.015 Concrete pipe | 0.015 Brick, dressed stone | 0.016 Smooth earth | 0.018 Firm gravel | 0.020 Corrugated metal pipe | 0.023 Natural channels: Clean, straight, no pools | 0.029 As above, with weeds and stones | 0.035 Winding, pools and shallows, clean | 0.039 Very weedy and sluggish | 0.112 Lined channels: Concrete surface (bottom and sides): Smooth finish | 0.015 Unfinished | 0.017 Curb and gutter | 0.021 Concrete bottom with sides: Mortared stone | 0.020 Dry rubble or riprap | 0.033 Asphalt: Rough | 0.016 Smooth | 0.013 Values quoted in this subsection are averages of many determinations; variations of up to 20 percent must be expected, especially in natural channels. (5) Storm drainage inlets. Storm drainage inlets shall be a grate, curb opening or combination inlet. Combination curb/gutter inlets shall be used at all points where ponding or sump conditions exist. The theoretical capacity and spacing of storm inlets will be analyzed using the criteria outlined in these specifications. The allowable capacity will be determined using the reduction factors listed in the following table. These reduction factors compensate for debris plugging, pavement overlaying, variations in design assumptions and other factors that decrease capacities. (6) The size of outlet pipes from stormwater inlets shall be based upon the theoretical capacity of the inlet, but in no case shall pipes be smaller than 18 inches (0.457 m) in diameter. INLET REDUCTION FACTORS Condition | Allowable Inlet Type | Percent of Theoretical Capacity Allowed | Calculation Sump and continuous grade | Combination curb opening with grate | 65 | 0.65*QT Curb opening only | 85 | 0.85*QT Grate only | 50 | 0.5*QT *QT is the theoretical flow through the inlet. Computations for storm drain and inlet design capacities shall be submitted as part of the final drainage study. Adequate details of the proposed storm drain system; inlets and manholes shall be included in the drainage report and detail drawings within the plan set. Theoretical flow capacities shall be reduced by the reduction factors outlined in this subsection to obtain design flow capacities. (c) Crossing structures and culverts. Crossing structures and culverts shall convey the one percent storm through the structure with additional design that provides for overflow capacity if the structure capacity is reduced due to trash or debris accumulation. Culverts under major arterials shall have sufficient capacity to pass the runoff from the major storm considering that 20 percent of the inlet is plugged. All other culverts shall be designed with emergency overflow that will help convey the major storm event. Capacities shall be calculated for the inlet, pipe, and outlet control conditions where the most conservative condition shall be used. In determining the amount of overflow required, the following capacity credit shall apply: CAPACITY CREDIT FOR STRUCTURES Cross Section Area of Structure | Capacity Credit Percent of Full Flow Capacity | * Percent of Major Storm Flow to be Considered as Emergency Overflow Less than 20 SF (1.858 m 2 ) | 50 | 50 Greater than 20 SF(1.858 m 2 ) | 80 | 50 * Shall meet street cross flow requirements of this section. Qt*[Capacity Credit] equals allowed structure capacity. The appropriate amount of emergency overflow onto streets shall be taken into account when analyzing storm runoff and allowable street capacities for the major storm. The following design criteria should be used for all culvert design: (1) Culvert. The culvert, including all inlet and outlet structures, shall properly take care of water, bed load and debris at all stages of flow. (2) Inlets. Culvert inlets shall be designed to minimize entrance and friction losses. Inlets shall be provided with either flared end sections or headwalls with wing walls and adequate rip-rap protection. Projecting ends will not be acceptable. For large structures, provisions shall be made to resist possible structural failure due to hydrostatic uplift forces. Structure shall be reinforced concrete with removable, lockable grates. (3) Outlets. Culvert outlets shall be designed to avoid sedimentation, undermining of the culvert or erosion of the downstream channel. Outlets shall be provided with either flared end sections or headwalls with wing walls, aprons (containing energy dissipaters), and toe walls. Additional outlet control in the form of riprap, channel shaping, etc., shall required where excessively high discharged velocities occur, see table 32-105.5.C. Outlets shall have removable galvanized steel grates to facilitate cleaning (rebar racks are not acceptable). No sharp energy dissipaters will be permitted. (4) Slopes. Culvert slopes should be such that neither silting nor excessive velocities and scour occur. Generally the minimum slope of culverts shall be 0.5 percent. (5) Headwater. Generally the headwater to diameter ratios should not exceed the following: RECOMMENDED MAXIMUM HEADWATER TO DIAMETER RADIOS Storm Frequency | HW/D 10% chance storm | 1.0 1% chance storm | 1.25 Excessive ponding above culvert entrances will not be acceptable if such ponding appears likely to cause property or roadway damage, culvert clogging, saturation of fills, detrimental upstream deposits, or inundate existing or future utilities or structures. (6) Tail water. The height of tail water at outlets shall be subject to the criteria listed under headwater criteria above. (7) Rip-rap - The construction of rip-rap surface treatment shall consist of furnishing and placing stone, with or without grout, and with or without wire mesh. Cutoffs shall be provided, to a minimum thickness of three times the required apron thickness, at both the upstream and downstream terminals of the rip-rap apron when a stable feature is not present (i.e. concrete cutoff wall). All rip-rap shall have either a filter material (FM) or a non-woven geotextile between the soil and rip-rap, except where rip rap is grouted. Wire-tied rip-rap shall have stakes and conform to NMDOT serial BRR-001-08. The rip-rap used shall conform to the following: MINIMUM RIP-RAP REQUIREMENTS Water Velocity Fps (m/s) | Weight of Rock lb (kg) | Apron Thickness in (mm) | Rip-Rap Designation | Use N/A | N/A | T/2 | Type FM (filter material) | Filter material only By design | 30 (13.6) | By design | Type WT** (wire tied) | Gabion 0—3.9 (0—1.2) | 50 (22.7) | 18 (457.2) | Type L (very light) | Gabion or loose 4—7.9 (1.2—2.4) | 100 (45.4) | 24 (609.6) | Type L (light) | Gabion or loose Public works approval | 300 (136.1) | By V.S. design ACOE method | Type M (medium) | Loose Public works approval | 750 (340.2) | By V.S. design ACOE method | Type H (heavy) | Loose Public works approval | 2,500 (1,134) | By V.S. design ACOE method | Type VH (very heavy) | Loose ** (Note: For use in 12-inch (0.305 m) high or smaller gabions. _____ Grouted rip-rap shall be hand placed in a mortar bed to a minimum of one-third the diameter or of three inches thick, whichever greater, of type "s" mortar. Rip-rap shall not be placed deeper than one-half the thickness of the grout bed. Voids in the rip-rap shall be completely filled with mortar for the full thickness of the rip-rap. After the grout is placed, the surface of the rip-rap shall be swept with a stiff broom. The finished surface of the rip-rap shall not vary more than three inches from the design grade. Riprap stones shall conform to the following: MINIMUM REQUIREMENTS FOR GROUTED RIP-RAP Water Velocity Fps (m/s) | Stone Volume;eol′ 3 (m 3 ) Ex. ⅓ Stone + ⅔ Mortar = 1 Unit Grouted Rip-Rap | *Minimum Dimension in (mm) Min. | Max. 0—5 (0—1.5) | ⅓ (0.009) | 1 (0.028) | 3 (76.2) 5—10 (1.5—3.0) | 1 (0.28) | 2 (0.57) | 6 (152.4) * Minimum size in the least dimension. (d) Open channels. (1) General criteria. Except as modified in this division, open channels shall be designed for the major storm event (one percent chance storm) with additional analysis showing the effects of the initial (ten percent chance) storm. Whenever practical, channels should be designed to avoid flows at or near supercritical depth. Channel capacities should be computed using sound engineering practices, if the city determines potential backwater conditions exist a more extensive analysis (HEC II, HEC-RAS) will be required. No channel shall have a depth less than critical depth plus freeboard. (2) Hydraulics. The channel cross section may be of the type most suited to the location. The drainage report and design hydraulics of flow in channels shall include analysis of the hydraulics indicating the following parameters for existing and proposed channels and drainage ways: a. Flow cross section geometry for each different configuration of channel shape. b. Flow cross sectional area. c. Wetted perimeter. d. Hydraulic radius. e. Manning's roughness coefficient (n). f. Flow velocity. g. The maximum capacity of the channel, including freeboard requirements. h. Design discharge. i. Bed slope. j. Froude number. k. Freeboard requirement based on one percent chance event (minimum 12 inches) (0.305 m). l. Flow type (subcritical, critical, or supercritical). (3) Erosion. All channels shall be designed with the proper and adequate erosion control features. (4) Water surface profile. A water surface profile for the major storm runoff shall be computed for all channels and clearly shown on final drawings submitted for approval. Computations of the water surface profile shall utilize standard backwater methods, taking into consideration all losses due to velocity changes, drops, bridge and culvert openings, and other obstructions. Computations shall be submitted with the final design plan. The energy gradient line should also be computed and be shown on the final drawings. The engineer shall be responsible for obtaining FEMA approval of flood insurance study (FIS) flood hazard zone changes and new/revised flood zone maps as part of the project development. (5) Unlined channels. Unlined channels shall be classified as channels whose slope maintains flows with a Froude number of 0.8 or less. Drops may be used to maintain these criteria. All channels will be evaluated on a case-by-case basis considering, depth, side slopes, lining, velocity, safety, etc. a. Side slopes. Side slopes shall be as flat as practical. Side slopes of 4:1 (horizontal to vertical) shall be considered a normal maximum. Any side slope steeper than this will require written approval from the public works director. b. Flow depth. The maximum design depth for the major storm runoff shall be 4.0 feet (1.219 m) in open channels, unless otherwise authorized by the public works director. c. Design velocity. A maximum velocity for the major storm runoff needs to recognize the scour potential of the soil-vegetative complex. Average velocities need to be determined by mixed flow analysis using HEC-RAS which account for drops, expansions, contractions and other structural controls. Velocities need to be kept sufficiently low to prevent excessive erosion in the channel. The following velocities are recommended as maximums for major storm runoff flows: Table 32-105.5.C Maximum Velocity (fps) (mps) Cover | Clay (Erosion Resistant Soil) | Sandy (Easily Eroded Soil) No cover, dirt lined | 4.0 (1.219) | 2.5 (0.7620) *Buffalo grass, bluegrass, smooth brome, blue gramma, native grass mix | 7.0 (2.134) | 5.0 (1.524) *Lespedeza, lovergrass, kudzu, alfalfa, crabgrass | 4.5 (1.372) | 3.0 (0.914) * Grass cover assumed to be a good stand and well maintained. (6) Lined channels. Lined channels are defined as those exhibiting characteristics which would require lining of the channel to ensure structure stability, to achieve the desired design life of the channel, and to protect areas adjacent to the structure. Contributing factors in the analysis to channel lining requirements include bed slope, flow rate, soil type and stability, and any flow conditions that cause velocity changes. Generally, in most soil conditions, channels exhibiting hydraulic characteristics which result in a Froude number of 0.8 or greater during the ten percent chance or one percent chance storm will require stabilization in the form of a lining. All channels will be evaluated on a case-by-case basis considering, depth, side slopes, lining, velocity, safety, etc. a. Side slopes. Side slopes of a channel shall be those best suited to the terrain and location. Maximum channel slopes with minimal slope protection and/or stabilization, as in table 32-105.5.c shall be no steeper than 2:1 (horizontal:vertical). b. Depth of flow. The depth of flow shall be kept to a minimum, considering velocities involved and land areas needed for drainage easements. c. Lining materials. Lining materials shall be composed of one of the following: 1. Concrete of sufficient strength and thickness to support all design loads, including maintenance equipment. Roughening of concrete surfaces is encouraged. Roughening may be accomplished by use of darbies, exposed aggregate, or other suitable methods approved by the public works director. 2. Asphalt of sufficient strength, including base materials, to support all anticipated design loads, including maintenance equipment. Asphalt linings shall be of a mix design which will resist damage due to erosion and lack of vehicular traffic for the design life of the lining which shall be 20 years. 3. Riprap, set in concrete or mortar, shall have the rock size and weight sufficient to resist displacement of the rock by the energy present in the flow of the major storm event. Riprap may be stabilized by grouting, can be set in concrete, or may be wire tied. Standard gabions may be used to stabilize rock under some conditions. 4. Other types of linings such as wood, metal, tile, wire-tied rip rap, reno mattress, brick, fibermesh concrete, or other materials may be used when approved by the public works director. d. Freeboard. The design of channels at supercritical stages shall be taken into account; requirements for freeboard to provide a splash and hydraulic jump phenomenon. For conditions of uniform flow, the minimum lined elevation shall include freeboard above the flow surface of the major storm and shall be calculated using the following equation: [Sub-Critical Flow] Freeboard (in feet) = d/4 + 0.025*(v)*(d) 1/3 Where: d = Depth of flow (feet) v = Velocity of flow (ft./sec.) Freeboard (in meters) = d/4 + 0.025*(v)* d) 1/3 Where: d = Depth of flow (meters) v = Velocity of flow (m/s) For conditions where the total energy content of the flow must be considered, such as bends, drops, abrupt changes in grade or area, convergence of flows, obstructions within the channel, and other conditions which may produce a hydraulic jump, the minimum freeboard above the flow surface of the major storm runoff shall be calculated using the following equation: [Super Critical and Critical Flow] Freeboard (in feet) = 0.5 + (v 2 /(2*g)) Freeboard (in meters) = 0.152 + (v 2 /(2*g)) Where: v = Velocity of flow (m/ 3 ) g = Gravity constant = 9.81 m/s 2 Where: v = Velocity of flow (ft./sec.) g = Gravity constant 32.3 ft./sec. 2 Minimum freeboard under bridges shall be two feet (0.610) (7) Walls adjacent to open channels shall be constructed to an elevation that is a minimum of six inches (0.152 m) above the finish lot grade at the time of roadway construction. (e) Storm drain lift stations. The use of storm drain lift stations is strongly discouraged and will be considered only in cases involving extenuating circumstances. All lift stations will be designed to handle twice the 100-year routed peak flow rate and have a detention pond capable of removing silt, debris and, floatable material before entering the lift station entrance works. Under no circumstance shall a channel feed directly into a lift station. At a minimum, all lift stations must have an exerciser in the control panel and be equipped with a supervisory control and data acquisition (SCADA) system compatible with the existing city system. The pumps will be driven by a three-phase power system and have a redundant power source such as another electrical grid or an automated generator capable of driving all the pumps simultaneously.

(Ord. No. 949, § 3.1E, 9-8-87; Ord. No. 1224, § 1, 3-18-91; Ord. No. 1929, §§ I, II, 8-5-02; Ord. No. 2187, 4-4-05)